MODIFICATION # 2TO GRANT AGREEMENT BETWEEN
THE DEPARTMENT OF COMMUNITY AFFAIRS AND
GRANTEE NAME : Indian River County
This Modification is made and entered into by and between the State of Florida, Department of
Community Affairs ("the Department"), and Indian River County ("the Recipient") , to modify DCA
Contract Number 06DB-3C- 10-40-01 -W 14 , ("the Agreement').
WHEREAS, the Department and the Recipient have entered into the Agreement, pursuant to
which the Department has provided a subgrant of $ 7 . 500. 000. 00 to the Recipient under the Small Cities
Community Development Block Grant program as set forth in the Agreement; and
WHEREAS, the Department and the Recipient desire to modify the Agreement by modifying the
Attachment A, Program Budget and Scope of Work, section of the Agreement; and
WHEREAS , the Department and the Recipient desire to modify the Agreement by modifying the
Attachment B, Work Plan , section of the Agreement.
NOW, THEREFORE , in consideration of the mutual promises of the parties contained herein, the
parties agree as follows:
1 . The Attachment A, Program Budget and Scope of Work section is hereby deleted and is replaced
by the revised Attachment A, the Program Budget and Scope of Work, which is attached hereto
and incorporated by herein reference .
2. The Attachment B, Activity Work Plan section is hereby deleted and is replaced by the revised
Attachment B, Activity Work Plan , which is attached hereto and incorporated herein by reference.
3. All provisions of the Agreement and any attachments thereto in conflict with this Modification shall
be and are hereby changed to conform with this Modification , effective as of the date of the
execution of this Modification by both parties.
4 . All provisions not in conflict with this Modification remain in full force and effect, and are to be
performed at the level specified in the Agreement.
IN WITNESS WHEREOF, the parties hereto have executed this document as of the dates set
herein .
DEPAR ENT F C/ qMNITY AFFAIRS Recipient: Indian River'County
By. A140
J i e Browni64, Divisi Director Gary C *&r,', Chairrn2,rr',�
Housi g and Communi evelopment Board CountyGq'rl :, i loners
Date: �� � � Date: March 20 , 2007
BOARD OF COUNTY COMMISSIONERS
1840 25th Street, Vero Beach, Florida 32960-3365
Telephone: (772) 567-8000
March 26, 2007
Tara S . Walters
Florida Department of Community Affairs
Division of Housing and Community Development
CDBG/Disaster Recovery, Room 300C
2555 Shumard Oaks Boulevard
Tallahassee, Florida 323 99-2 100
RE : Amendment Number Two
Indian River County Disaster Recovery Initiative CDBG
DCA Contract #06DB -3C- 10-40-01 -W14
Dear Ms. Walters,
Please consider this as a request for an amendment for the above referenced Grant contract
between the Florida Department of Community Affairs and Indian River County (Amendment
92) . Amendment #2 will accomplish the following:
• Removal of the Rockridge Subdivision Stormwater project from the grant contract.
• Reallocation of $440,695 .00 of the $2, 100,000 in Rockridge Subdivision Stormwater
project funds to the Fire Station #4 project.
• Reallocation of the remaining $ 1 ,659,305 .00 in Rockridge Subdivision Stormwater
project funds to the Rockridge Subdivision Sanitary Sewer project.
• Reallocation of $691 ,599 from the Engineering line item to the Rockridge Subdivision
Sanitary Sewer project.
• Reallocation of $ 175 ,000. 00 of unobligated funds in the West Wabasso Phase I water line
project to address Phase II of the West Wabasso water line project.
• Revision of the beneficiaries in Phase I of the West Wabasso Water Line project to more
accurately reflect the individuals living in the units that were impacted.
The removal of the Rockridge Subdivision Stormwater project from the contract is a result of
delays with obtaining approval of Hazard Mitigation Grant Program (HMGP) funding, problems
finalizing the property on which the storm water pumps could be installed, and intensive
environmental permitting required. In addition, there was an increase in the estimated volume of
water that will have to be diverted to other locations based on the engineering design completed
to date. Because of these issues, the Rockridge Subdivision Stormwater project cannot be
completed within the time remaining in the Disaster Recovery Grant contract.
Because the County is near completion of Phase I of the West Wabasso Water Line Construction
Project and because that project will be completed under budget, this amendment includes a
request to utilize the funds remaining in the West Wabasso Water Line Construction project to
expand the project area to include the properties in the West Wabasso Phase JI project area. The
residences within this area are more than 51 % low to moderate income. Residences within Phase
II of the Wabasso Water Project area were impacted by well infiltration from over flowing septic
tanks during the same storms that qualified the Phase I area for the above referenced grant.
Enclosed please find the Amendment #2 request package consisting of the following :
Three (3 ) original copies of the DCA Form entitled "Modification #2 to Grant Agreement";
DCA Form "Request for Amendment (07. 02)";
Amended DCA Small Cities CDBG Program Project Work Plans;
Minutes from the CATF meeting held March, 12, 2007;
Certified copy of the public hearing advertisement;
Minutes from the public hearing held by the Board of County Commissioners, at which
Amendment #2 was approved; and
Revised Application Narrative incorporating the changes in amendment #2 .
If you have any questions regarding this Amendment, please contact Mr. Fred Fox, the County' s
Grants Administrator, at (904) 810-5183 or Mr. Robert Keating, the County' s Community
Development Director at (772) 226 - 1254.
Sincerely,
C, U)
Gary C. Wheeler
Board of County Commissioners Chairman
Enclosures
cc : Joseph A. Baird, County Administrator
Michael C. Zito, Assistant County Administrator
Robert M. Keating, AICP, Community Development Director
Fred Fox, Fred Fox Enterprises, Inc .
Jason E. Brown, Management and Budget Director
Sasan Rohani, AICP, Chief Long Range Planning
Bill Schutt, AICP, Senior Economic Development Planner
Ted Court, DRP Grants Management Coordinator
F:\Community Deve1opmen6Uscrs\CDBG%cdbg 20051Amendments\Amendment #2 - March 20071Amendment PackageTinal VersionslCover
letter.doc
t-: E GIPIENT Indian River County CONTRACT # . 06DB-3C- 10-40-0144 14
ATTACHMENT A - DISASTER RECOVERY INITIATIVE PROGRAM
PROGRAM BUDGET AND SCOPE OF WORK SUMMARY PAGE
1 2 3 4 5 7 8 9 10 11
ACTIVITY ACCOMPLISHMENTS BENEFICIARIES BUDGET
'NUMBER DESCRIPTION UNIT NUMBER LMI TOTAL CDBG AMOUNT "OTHER FUNDS `SOURCE # OB.IECTi � z
i t
€, IIA ADMINISTRATION $$432 .500.00 ^_ —
S . ? 18 ENGINEERING I ^_ $89.451 . 00
p0A3,10A3,1Sewer Facilities LF 21 , 500 1 ,049 1 ,667 $3 , 970 .404 . 00 $1 , 505. 500. 00 2
-
031 Potable Water Lines LF 8700 189 209 $825.000. 00 $31 .200. 00 3 _
r__._._._._..
030 Fire Station Replacement _ Buildin I 10. 190 25 .669 $2 . 182 .645 . 00 $56068.00 4
t
(
TOTALS 30. 201 t 28 27 . 545 $7,500,000 . 00 - $1 . 592
L4 ' 6800 6800
SOURCES AND AMOUNTS OF "OTHER FUNDS" (COLUMNS 9 AND 10 ABOVE)
1 5 $
- - — -_ -_—_- _ _—_--- - - - -- -- -- - -- - - -- - -- ---- - _ - - - --- ------ ---- --- - --- -- -_ -- - _ _ _ - _ -- - - - -
2 Local Gov't ReservesiFEMA/Utiiities Reserve $ 1 , 50 -------- -_ _ - -- - - - - -__ ___ — _ - -
3 Florida Housing Finance Corp _Hurricane Housing_ $as 200 .00 7 S
- ,- -------- _ _ - - - ---- - - - - - -- - . . _ _ . - ..
4 Local Gov't Reserves `FEMA/Prtvate Contr;butions $ 356, 684 . 00 8 $
RECIPIENT: Indian River County CONTRACT NUMBER: 06DB-3C-10-40-01 -W14
ATTACHMENT A
PROGRAM BUDGET AND SCOPE OF WORK
Service Area — Fire Station #4
1 2 3 4 5 6 7 8 9 10 11
ACTIVITY ACCOMPLISHMENTS BENEFICIARIES BUDGET
NUMBER DESCRIPTION UNIT NUMBER LMI VLI TOTAL CDBG AMOUNT *OTHER FUNDS *SOURCE # PROG. INC.
030 Fire Station Replacement Building 1 10, 190 N/A 25,669 $ 2, 182,645.00 $ 56,068.00 2 Urgent Need
TOTALS 1 10, 190 25,669 $2, 182,645.00.00 $ 56,068 .00
* SOURCES AND AMOUNTS OF "OTHER FUNDS' (COLUMN 9 & 10 ABOVE)
1 . $ 5. $
2. Local Gov't Reserves/FEMA/Private $56 ,068 .00 6. $
Contributions/Utilities
Reserve/Insurance
3. $ 7. $
4. $ 8. $
Attachment A - Indian River County- 06DB-3C- 10-40-01-W 14 - March 20, 2007
RECIPIENT: Indian River County CONTRACT NUMBER : 06DB-3C-10-40-01 -W14
ATTACHMENT A
PROGRAM BUDGET AND SCOPE OF WORK
Service Area — Rockridge Subdivision Sanitary Sewer
1 2 3 4 5 6 7 8 9 10 11
ACTIVITY ACCOMPLISHMENTS BENEFICIARIES BUDGET
NUMBER DESCRIPTION UNIT NUMBER LMI VLI TOTAL CDBG AMOUNT 'OTHER FUNDS "SOURCE # PROG. INC.
031 Sewer Facilities LF 21 ,500 1 ,049 N/A 1 ,667 $ 3,970,404.00 $ 1 ,505,500.00 2 UMI
TOTALS 21 ,500 1 ,049 10667 $ 3,970,404.00 $ 1 ,505,500.00
* SOURCES AND AMOUNTS OF "OTHER FUNDS" (COLUMN 9 & 10 ABOVE )
1 . $ 5. $
2. Local Gov't Reserves/FEMA/Private 6, $
Contributions/Utilities
Reserve/Insurance $ 1 ,505,500.00
3. $ 7. $
4. $ 8. $
Attachment A - Indian River County- 06DB-3C- 10-40-01-W 14 - March 20, 2007
RECIPIENT: Indian River County CONTRACT NUMBER: 06DB-3C-10-40-01 -W14
ATTACHMENT A
PROGRAM BUDGET AND SCOPE OF WORK
Service Area — Potable Water Lines (Phase 1)
1 2 3 4 5 6 7 8 9 10 11
ACTIVITY ACCOMPLISHMENTS BENEFICIARIES BUDGET
NUMBER DESCRIPTION UNIT NUMBER LMI VLI TOTAL CDBG AMOUNT *OTHER FUNDS *SOURCE # PROG. INC.
03J Potable Water Lines LF 7,050 141 N/A 161 $ 650,000.00 $ 20,000.00 3 LMI
TOTALS 1 7,050 141 161 $ 650,000.00 $ 20,000.00
* SOURCES AND AMOUNTS OF "OTHER FUNDS" (COLUMN 9 & 10 ABOVE)
1 . $ 5. $
2. $ 6. $
3. Florida Housing Finance Corp. — $ 20,000.00 7. $
Hurricane Housing RecoveryProgram
4. $ 8. $
Attachment A - Indian River County- 06DB-3C- 10-40-01-W 14 - March 20, 2007
RECIPIENT: Indian River County CONTRACT NUMBER: 06DB-3C-10-40-01 -W14
ATTACHMENTA
PROGRAM BUDGET AND SCOPE OF WORK
Service Area — Potable Water Lines (Phase II)
1 2 3 4 5 6 7 8 9 10 11
ACTIVITY ACCOMPLISHMENTS BENEFICIARIES BUDGET
NUMBER DESCRIPTION UNIT NUMBER LMI VLI TOTAL CDBG AMOUNT *OTHER FUNDS 'SOURCE # PROG. INC.
03J Potable Water Lines LF 1 ,650 48 N/A 59 $ 175,000.00 $ 11 ,200.00 3 UMI
TOTALS 1 ,650 48 59 $ 175,000.00 $ 11 ,200.00
SOURCES AND AMOUNTS OF "OTHER FUNDS" (COLUMN 9 & 10 ABOVE)
1 . $ 5. $
2. $ 6. $
3. Florida Housing Finance Corp. — $ 11 ,200.00 7. $
Hurricane Housing RecoveryProgram
4. $ 8. $
Attachment A - Indian River County- 06DB-3C-f0-40-01-W 14 - March 20, 2007
Attachment B
DEPARTMENT OF COMMUNITY AFFAIRS SMALL CITIES CDBG PROGRAM
PROJECT WORK PLAN
( Page 1 of 4)
RECIPIENT Indian River County DATE PREPARED March 5 , 2007
CONTRACT NO, 06DB-3C- 1 0-40-01 -W 14 PROJECT BUDGET $ 71500 , 000 . 00
West Wabasso Water Line
Project Name : Phase II
Date Start Date End Describe Proposed Action to be Undertaken # Units to be Proposed $$ to
(month & (month & or Contract Special Condition Clearance Documentation completed by " Date be Requested
ear ear to be submitted b " Date End" End" b " Date End"
AUG 2005 SEPT 2005 Submit Request for Release of Funds & Environmental Conditions 0.00
SEPT 2005 OCT 2005 Submit documentation to clear Special Conditions 0.00
OCT 2005 DEC 2006 Decision made to include West Wabasso Phase II in contract 0.00
DEC 2006 MAR 2007 Complete survey and design of the project 0.00
MAR 2007 APRIL 2007 Submit amendment to include West Wabasso Phase II to DCA and obtain approval 0.00
MAR 2007 APRIL 2007 Design Review by DCA 0.00
APRIL 2007 MAY 2007 Permitting/Advertising/Receive and Award Bids 0.00
MAY 2007 MAY 2007 Enter into Construction ContractsNerification of Contractor Eligibility 0.00
MAY 2007 MAY 2007 Hold Preconstruction Conference/Issue NTP 0.00
MAY 2007 JUNE 2007 Construction Phase 33% Complete 50,000.00
JUNE 2007 JULY 2007 Construction Phase 67% Complete 50,000.00
JULY 2007 AUG 2007 Construction Phase 100% Complete 50,000. 00
AUG 2007 AUG 2007 Final Inspection / Punchlist 1650 LF Water Line 25,000.00
AUG 2007 AUG 2007 Submit Administrative Closeout 0.00
Note: More than one activity may be included per form . ( Rev. Aug 2004)
'Includes Administration for all activities.
DEPARTMENT OF COMMUNITY AFFAIRS SMALL CITIES CDBG PROGRAM
PROJECT WORK PLAN
(Page 2 of 4)
RECIPIENT Indian River County DATE PREPARED March 5 , 2007
CONTRACT NO. 06DB-3C- 1 0-40-01 -W 14 PROJECT BUDGET $ 795009000 . 00
Project Name : Rockridge Sanitary Sewer
Date Start Date End # Units to be Proposed Proposed
(month & (month & completed by $$ to be Engineering
Describe Proposed Action to be Undertaken
year) year) or Contract Special Condition Clearance Documentation " Date End" Requested $$ All
to be submitted by " Date End" by " Date Activities to be
End" Requested by
" Date End"
AUG 2005 SEPT 2005 Submit Request for Release of Funds & Environmental Conditions 0.00 0.00
SEPT 2005 OCT 2005 Submit documentation to clear Special Conditions 0.00 0.00
OCT 2005 DEC 2005 Solicit for, contract with and obtain DCA approval of Engineer 0.00 0.00
DEC 2005 FEB 2007 Complete survey and design of the pro ect 0.00 0.00
FEB 2007 MAR 2007 Desi n Review by DCA 0.00 0.00
MAR 2007 APRIL 2007 Permitting/Advertising/Receive Bids 0.00 18,000.00
APRIL 2007 MAY 2007 Enter into construction ContracWerification of Contractor Eligibility 0.00 25,000.00
MAY 2007 MAY 2007 Hold Preconstruction Conference/Issue NTP 0 .00 25,000.00
MAY 2007 MAY 2007 Purchase Equipment 1 ,200,000.00 21 ,451 .00
MAY 2007 JUNE 2007 Construction Phase 33% Complete 5-0-0-10-0-0-00 0.00
JUNE 2007 JULY 2007 Construction Phase 67% Complete 500,000.00 0.00
JULY 2007 AUG 2007 Construction Phase 90% Complete 750,000.00 0.00
AUG 2007 AUG 2007 Final Inspection / Punchlist 21 ,500 LF sewer 500,000.00 0.00
AUG 2007 AUG 2007 Construction Complete 520,404.00 0.00
AUG 2007 AUG 2007 Submit Administrative Closeout 0.00 0.00
Note: More than one activity may be included per form . (Rev. Aug 2004)
DEPARTMENT OF COMMUNITY AFFAIRS SMALL CITIES CDBG PROGRAM
PROJECT WORK PLAN
( Page 3 of 4)
RECIPIENT Indian River County DATE PREPARED March 5 , 2007
CONTRACT NO, 06DB-3C- 1 0-40-01 -W 14 PROJECT BUDGET $ 71500 , 000 . 00
West Wabasso Water Line
Project Name : Phase I
Date Start Date End # Units to be Proposed Proposed
(month & (month & completed by $$ to be Administration
ear Describe Proposed Action to be Undertaken
year) year) or Contract Special Condition Clearance Documentation "Date End" Requested $$ All
to be submitted by " Date End" by " Date Activities to be
End" Requested by
" Date End"
AUG 2005 SEPT 2005 Submit Request for Release of Funds & Environmental Conditions 0.00 0.00
SEPT 2005 OCT 2005 Submit documentation to clear Special Conditions 0.00 0.00
OCT 2005 NOV 2005 Obtain Wage Decision 0.00 0.00
NOV 2005 DEC 2005 Design Review by DCA 0.00 0.00
DEC 2005 FEB 2006 Permitting/Advertising/Receive Bids 0.00 37,273.00
FEB 2006 MAR 2006 Enter into Construction ContracWerification of Contractor Eligibility 0.00 24,425.00
MAR 2006 APR 2006 Hold Preconstruction Conference/Issue NTP 0.00 48,265.00
APR 2006 MAY 2006 Construction Phase 10% Complete 0.00 0.00
MAY 2006 JUL 2006 Construction Phase 33% Complete 0.00 0.00
JUL 2006 SEPT 2006 Construction Phase 50% Complete 40,725.00 24,000.00
SEPT 2006 NOV 2006 Construction Phase 67% Complete 0.00 0.00
NOV 2006 JAN 2007 Construction Phase 90% Complete 185,510.00 36,038.00
JAN 2007 FEB 2007 Final Inspection / Punchlist 7,050 LF Water 175,000.00 50,000.00
FEB 2007 MAR 2007 Construction Complete 248 ,765.00 50,000.00
MAR 2007 AUG 2007 Submit Administrative Closeout 0.00 162 ,499.00
Note: More than one activity may be included per form. (Rev. Aug 2004)
DEPARTMENT OF COMMUNITY AFFAIRS SMALL CITIES CDBG PROGRAM
PROJECT WORK PLAN
(Page 4 of 4)
RECIPIENT Indian River County DATE PREPARED March 5 , 2007
CONTRACT NO. 06DB-3C- 1 0-40-01 -W 14 PROJECT BUDGET $ 73500 , 000 . 00
Project Name : Fire Station #4 Replacement
Date Start Date End Describe Proposed Action to be Undertaken # Units to be Proposed $$ to
(month & (month & or Contract Special Condition Clearance Documentation completed by be Requested
ear ear) to be submitted b "Date End" "Date End" b " Date End"
AUG 2005 SEPT 2005 Submit Request for Release of Funds & Environmental Conditions 0.00
SEPT 2005 OCT 2005 Submit documentation to clear Special Conditions 0.00
SEPT 2005 OCT 2005 Solicit for, select and obtain DCA clearance of Design - Build firm 0.00
OCT 2005 DEC 2005 Obtain Wage Decision 0.00
Design — Build firm completes design of Fire Station #4/Contrail with Design - Build firm
NOV 2005 FEB 2006 for construction of Fire Station #4/Obtain DCA approval of Design-Build firm's
construction contract 0.00
FEB 2006 MAR 2006 Design Review by DCA 0.00
MAR 2006 APR 2006 Preconstruction Conference Issue NTP 0.00
APR 2006 JUN 2006 Construction Phase 10% Complete 0.00
JUN 2006 AUG 2006 Construction Phase 33% Complete 384,806.00
AUG 2006 OCT 2006 Construction Phase 50% Complete 0.00
OCT 2006 DEC 2006 Construction Phase 67% Complete 471 ,052.00
DEC 2006 FEB 2007 Construction Phase 90% Complete 360,584.00
FEB 2007 MAR 2007 Final Inspection / Punchlist 1 Facility 356,775.00
MAR 2007 APR 2007 Construction Complete 1 , 500,000.00
APR 2007 AUG 2007 Submit Administrative Closeout 897, 187.00
Note: More than one activity may be included per form .