HomeMy WebLinkAbout2004-311 dm*
CHANGE ORDER NO . 002 Cil -3 t
DATE OF ISSUANCE : July 24 , 2004 EFFECTIVE DATE : October 30 , 2003
OWNER : Indian River County
CONTRACTOR : DICKERSON FLORIDA , INC .
Project : EAST GIFFORD STORMWATER IMPROVEMENTS
OWNER's Project No , 9219
OWNER/ ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents ,
1 . Description : Delete the concrete thrust blocks requested in Change Order No . 001
and physically relocate the water line from the path of a proposed stor water
drainage pipe .
Reason : To provide a more cost-effective alternative to a conflict between a
proposed stormwater drainage pipe and an existing water main .
The change in Contract Price is determined as follows :
DELETION to the Contract Price = $2 ,400 . 20
Attachments : None
CHANGE IN CONTRACT PRICE :
Description Amount
Original Contract Price $ 6881853 . 6
Net Increase from previous Change Order
No . 001 : $ 9 , 319 . 0
Contract Price prior to this Change Order: $698 , 172 . 1 F6
Net decrease of this Change Order: $2 , 400 . 2
Contract Price with all approved Change
Orders : $ 695 , 772 . 56
CHANGE IN CONTRACT TIMES
Description Time
Original Contract Time ( Final Completion ) December 21 , 2003
180 calendar days
Net change from previous Change Order
No . 001 : 2 days
Contract Time prior to this Change Order: 182 calendar days
Net increase decrease this Change Order: -0 - calendar days
Contract Time with all approved Change December 23 , 200
Orders : 182 calendar da
Charge Order #002
Change Order - 1
FAPublic WorksWeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #002 .doc Last revise 9/27/01
AC CEP E RECOMMENDED , APPROVED :
By : By: B
C NTRACTOR ( Signature ) ENGINEER (Signature) OWNS "A Sjona uro '
Keith McCully, P . E . , Indian Arth + Neuberger ` eta rman
River County Stormwater Board q;f G unty Commissio' ,pers
Engineer ;;
( Name and Title )
t
Date : Date : 7- 23 - D q r 7 } Ofl4
/ �' Date : 2,
Change Order #002
Change Order - 2
F :\Public Works\KeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #002 .doc Last revised /27/01
1 •
CHANGE ORDER NO . 003
DATE OF ISSUANCE : July 24 , 2004 EFFECTIVE DATE : October 30 , 2003
OWNER : Indian River County
CONTRACTOR : DICKERSON FLORIDA , INC .
Project : EAST GIFFORD STORMWATER IMPROVEMENTS
OWNER's Project No . 9219
OWNER/ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents :
1 . Description : Delete the barbed wire from the site fence and install standard fence
post tops .
Reason : The barbed wire is not needed .
The change in Contract Price is determined as follows :
DELETION to the Contract Price = $908 . 60
Attachments : None
CHANGE IN CONTRACT PRICE :
Description Amour t
Original Contract Price $ 6889853 . 5
Net Increase from previous Change Orders
No . 001 and 002 : $69919 . 0
Contract Price prior to this Change Order: $695 , 772 . 5
Net Decrease of this Change Order: $ 908 . 6
Contract Price with all approved Change
Orders : $ 6949863 . 9
CHANGE IN CONTRACT TIMES
Description Time
Original Contract Time ( Final Completion ) December 21 , 2003
180 calendar days )
Net change from previous Change Orders
No . 001 and 002 : 2 daVs
Contract Time prior to this Change Order: 182 calendar days
Net increase decrease this Change Order: -0- calendar days
Contract Time with all approved Change December 23 , 2003
Orders : 182 calendar days)
Change Order #003
Change Order - 1
FAPublic WorksWeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #003 .doc Last revised 9/27/01
y . p
F _
l ,
ACCEPTED : RECOMMENDED : APIR!ROVEDt
By : By :
CONTRACTOR (Signature ) EN iNEER (Signature) `,' (5WNER (Sighe
Keith McCully, P . E . , India A *Mqr Nein fir , ' rman
River County Stormwater ogrd .pf County Cgnimissioners
p1ec0, � G�4�SN ' ` ✓'r�7 �' Engineer J ` � ?, �3 � , .
( Name jad TitleiDate : 7 - 23 -0¢ Dater 1 2 07 2004
Change Order #003
Change Order - 2
F :\Public Works\KeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #003 .doc Last revised 9/27/01
r
CHANGE ORDER NO . 004
DATE OF ISSUANCE : July 24 , 2004 EFFECTIVE DATE : July 2 , 2004
OWNER : Indian River County
CONTRACTOR : DICKERSON FLORIDA , INC .
Project : EAST GIFFORD STORMWATER IMPROVEMENTS
OWNER's Project No , 9219
OWNER/ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents .
1 . Description : Deduct costs from Carter Associates , Inc . for additional service work
required to replace AutoCad surveying files lost by the Contractor' s survey
subconsultant .
Reason : The survey subconsultant lost the original AutoCad files provide to it by the
County.
The change in Contract Price is determined as follows :
DELETION to the Contract Price = $ 177 . 50
Attachments : None
CHANGE IN CONTRACT PRICE :
Description Amour t
Original Contract Price $ 688 , 853 . 5
Net Increase from previous Change Orders
No . 001 , 002 , and 003 : $ 6 , 010 . 4
Contract Price prior to this Change Order: $ 6949863 . 9
Net Decrease of this Change Order: $ 177 . 50
Contract Price with all approved Change
Orders : $6940686 . 4
CHANGE IN CONTRACT TIMES
Description Time
Original Contract Time ( Final Completion ) December 21 , 2003
180 calendar days )
Net change from previous Change Orders
No . 001 and 002 : 2 days
Contract Time prior to this Change Order: 182 calendar days
Net increase decrease this Change Order: -0- calendar days
Contract Time with all approved Change December 23 , 2003
Orders : 182 calendar da s
Change Order #004
Change Order - 1
R\Public Works\KeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #004 . doc Last revised /27/01
t
r
s ~
"i.
ACCEPTED • RECOMMENDED : APPROVED:
By . �a /� B
� � y .
CONTRACTOR (Signature ) EN NEER (Signature ) WNER Signa e
Keith McCully, P . E . , India rthur ie rger ,or
�aman
River County Stormwater Board of dpbVty ConTmispfoners
. 140e Engineer
( Name a Title)
Date : /'`/ o Date : 7� 23 - G Date : 12 / 02 0Q4'
Change Order #004
Change Order - 2
FAPublic Works\KeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #004 .doc Last revised 9/27/01
CHANGE ORDER NO . 005
DATE OF ISSUANCE : November 17 , 2004 EFFECTIVE DATE : November 17 , 2004
OWNER : Indian River County
CONTRACTOR : DICKERSON FLORIDA , INC .
Project : EAST GIFFORD STORMWATER IMPROVEMENTS
OWNER' s Project No . 9219
OWNER/ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents .
1 . Description : Delete Bid Item 5 . 08 — Miscellaneous Stormwater Measuring and
Recording Equipment .
Reason : Indian River County will purchase this equipment directly from the
manufacturer.
The change in Contract Price is determined as follows :
DELETION to the Contract Price = $ 8 , 550 . 00
Attachments : None
CHANGE IN CONTRACT PRICE :
Description Amou t
Original Contract Price $ 6881853 . 5
Net Increase from previous Change Orders
No . 001 , 002 , 003 , and 004 : $ 51832 . 9
Contract Price prior to this Change Order: $ 6949686 . 4
Net Decrease of this Change Order: $ 81550 . 0
Contract Price with all approved Change
Orders : � �$ 686 , 1136AIS
CHANGE IN CONTRACT TIMES
Description Time
Original Contract Time ( Final Completion ) December 21 , 2003
180 calendar days )
Net change from previous Change Orders : 2 days
Contract Time _prior to this Change Order: 182 calendar da s
LINJetncrease decrease this Chan a Order: -0- calendar da s
ract Time with all approved Change December 23 , 2003
rs : 182 calendar da s
Change Order - 1 Change Order #005
FAPublic WorksWeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #005.doc Last revised /27/01
ACCEPTED : RECOMMENDED : APPROVED :
By : By :
CONTRACTOR (Signature ) EN ( NEER allignghm- 1auN "(Sign t )
Keith McCully, P . E . , Indian AI`thur�uk Neuberger
V River County Stormwater Chairperso` ny' Board of County
2 �� • . Engineer Comri � iti?ners
( Name and Title )
Date : t t - j 4 - oq LDate - / 7- D¢
Date :
Chang Order #005
Change Order - 2
FAPublic Works\KeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #005.doc Last revised /27/01