CHANGE ORDER NO . 001 O 3 , a l S
DATE OF ISSUANCE : August 19 , 2003 EFFECTIVE DATE : August 19 , 2003
OWNER : Indian River County
CONTRACTOR : DICKERSON FLORIDA , INC .
Project : EAST GIFFORD STORMWATER IMPROVEMENTS
OWNER's Project No . 9219
OWNER/ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents :
1 . Description : Add two Type " E " Inlets .
Reason : To adjust elliptical pipe route (along U . S . Highway No . 1 ) to avoid conflicts
with power poles and an existing water main .
The change in Contract Price is determined as follows :
ADDITION to the Contract Price = (2 Type " E " Inlets ) ($ 2 , 200 per Inlet)
= $4, 400 . 00
2 . Description : Additional labor to modify two Type " E " Inlets on site .
Reason : Inlets required modification due to adjustment of elliptical pipe route (along
U . S . Highway No . 1 ) to avoid conflicts with power poles and an existing water main .
The change in Contract Price is determined as follows :
ADDITION to the Contract Price = $ 990
3 . Description : Construct thrust blocks for an existing water main .
Reason : To protect an existing water main against resultant thrust from internal
pipeline pressure in order to allow the installation of a drainage structure near the
water main . The water main must be exposed in order to install the drainage
structure and the thrust blocks will prevent the water main ' s internal pressure from
blowing the fittings or pipe sections from the pipeline .
The change in Contract Price is determined as follows :
ADDITION to the Contract Price = $ 3 , 307 . 70
ADDITION to the Contract Time = 2 calendar days
4 . Description : Remove and replace an existing 15-inch corrugated metal pipe ( CMP )
at an existing drainage structure .
Reason : Since the construction drawings were prepared , a new pipe was added ( by
others ) to an existing drainage structure that the Contractor must connect to as part
of this project . This pipe must be removed to allow the Contractor to perform its
work and then the Contractor must reinstall the pipe .
The change in Contract Price is determined as follows :
ADDITION to the Contract Price = $ 621 . 50
Change Order #001
Change Order - 1
R\Public WorksWeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #001 .doc Last revised 9/27/01
Attachments : ( List documents supporting change )
1 . See attached Change Order Requests from Derrico Construction Corporation
(subcontractor to Dickerson Florida , Inc . )
CHANGE IN CONTRACT PRICE :
Description Amount
Original Contract Price $ 688 , 853 . 56
Net Increase ( Decrease ) from previous $-0 -
Chan a Orders No . N/A to N/A :
Contract Price prior to this Change Order: $ 688 , 853 . 56
Net increase of this Change Order: $ 99319 . 20
Contract Price with all approved Change $ 6981172 . 76
Orders :
CHANGE IN CONTRACT TIMES
Description Time
Original Contract Time ( Final Completion ) December 21 , 2003
180 calendar days )
Net change from previous Change Orders
No . N/A to N/A : -0- days
Contract Time prior to this Change Order: 180 calendar days
Net increase decrease this Change Order: 2 calendar days
Contract Time with all approved Change December 23 , 2003
Orders : 180 calendar da s
ACCEPT D : RECOMMENDED : APPRO D :
By: By: B
r
6"4
CO RACTORignatt� re ) E ( NEER (Signature) ER ( nature )
�Z4r � l (S Keith McCully, P . E . , Indian Kenneth R . Macht, Chairman ,
River County Stormwater Board of County Commissioners
/Y Engineer
(N me and Title)
Date : !j d ' Date : Sf 13 2043 Date : August 19 , 2003
Indian River County Approved Date
Administration fie q/&
Budget $
Co . Attorney
Risk Management
Department _ t , _ G:
Division Change Order #001
Change Order - 2
FAPublic Works\KeithM\Stormwater Projects\Gifford East\Change Orders\Change Order #001 .doc Last revised 9/27/01