FOURTH AMENDMENT TO
INDIAN RIVER COUNTY EMERGENCY CONTRACT
[Sheriffs Office 911 Center — Additional Repairs]
[Barth Construction , Inc . ]
THIS FOURTH AMENDMENT to Indian River County Emergency Contract ( " Fourth
Amendment" ) is made and entered this 6th day of December, 2005 , nunc pro tunc to March 1 ,
2005 , by and between INDIAN RIVER COUNTY , a political subdivision of the State of Florida
("County" ) and BARTH CONSTRUCTION , INC . , 1717 Indian River Blvd . , Suite 202A , Vero
Beach , FL 32960 ("Contractor" ) .
BACKGROUND RECITALS :
A . The County and the Contractor have entered into an Emergency Contract for Repairs to
an existing facility at the Sheriff' s Office Complex dated September 28 , 2004 (the "Agreement" )
for the repair and construction of certain emergency projects at the Sheriff' s Office Complex .
B . Pursuant to Paragraphs 2 . 1 and 14 of the Agreement , the County and Contractor desire
to amend the Agreement to include the additional emergency work at 'the Sheriff' s Office
Complex as more fully set forth on Exhibit "A" attached hereto and made a part hereof.
NOW, THEREFORE , for good and valuable consideration , the receipt and sufficiency of
which are hereby acknowledged , and intended to be legally bound , the parties hereto agree as
follows :
1 . The Agreement is hereby amended to allow for the additional services by Contractor at the
Sheriffs Office Complex on the specifications and at the price more specifically set forth on
Exhibit "A . "
2 . All remaining terms and conditions of the Agreement not changed by this Fourth
Amendment remain in full force and effect .
3 . The Background Recitals are true and correct and form a material part of the Agreement ,
as supplemented by this Fourth Amendment .
IN WITNESS WHEREOF , the parties have executed this Fourth Amendment as of the
day and year first written above .
BARTH ONS RUCTION , INC . IND IVER GOUNTY
„ :
By By s�
PROVED : hilli H . Barth , President Thomas S .' Lowther, Chairman
BCC Approved : December &, 2005
Atte arton , Clerk
C my Ad nistrator
B
A PROVEL7 AS TO FORM Deputy Clerk
'
DL
AL SUFFICIENCY
MA ANASSISTANT COEY
BARTH
Construction , Inca -�-
General Contractor CGCO07847
November 15 , 2005
Lynn Williams
Indian River County Buildings & Grounds
184025 th Street
Vero Beach , FI 32960
Re : Indian River County Sheriffs Office
Proposal Request #6
Lynn ,
We are submitting herewith our costs for Misc . Additional Work (See Attached Back up) in the
amount of, Sixty Five Thousand Two Hundred Seventy Four and 001100 Dollars ($65 ,274 .00) and
a time extension of 0 days .
1 ) The work is limited in scope to the attached back up
2 ) Specifically excluded ;
All electrical work
All mechanical work
No permit costs have been included for these changes to the contract documents .
Should you require any additional information , please feel free to contact me .
Sincerely,
Jason Fykes
Barth Construction Inc .
Approved by:
Owner
Date .•
{T, -� �, °•aJ. ,ter+ J}� C
Indian River County Sheriffs Office Work 11 . 14 .05
Proposal Request #6
Demolition ($22 , 800 . 00 allowance by C . O . # 1 - Total cost $ 30 ,446 . 00) = $ 7 , 646 . 00
Drywall Patching ($4, 000 . 00 Allowance by C . O . #3 — Total Cost $ 8 , 063 . 00) = $ 4 , 063 . 17
Re Painting in 911 Area due to changes (Schlitt Inv. # ' s 3178 & 3234) $ 733 . 00
F .A Parts for 911 Area $ 438 . 70
Pull & set plumbing fixtures in 911 Area (Southern Plumbing Inv. # ' s 3654 ,
4328 & 4446) $ 408 . 00
Paint Room Rooms 311 and Crime Scene Lab Room $ 2 , 380 . 00
Soil Testing @ chiller enclosure $ 468 . 00
Concrete Testing @ chiller enclosure $ 72 . 00
Drain Pipe behind chiller enclosure $ 248 , 72
Sidewalk in front of chiller enclosure $ 700 . 00
Relocate hose bib at chiller enclosure $ 267 . 00
Dry Wall Repair in Garage (Phoenix FWO # ' s 8014 & 8015 ) $ 983 .48
Install VCT in Room # ' s 303 , 308 & 309 $ 858 . 75
Install VCT in Hall # 306 $ 432 . 00
Aluminum Canopy @ Garage $221892 . 00
Footings for canopies $ 35700 . 00
Remove/Replace Wall Coverings in Lobby $ 3 , 338 . 00
Replace Door in Room # 695 in Uniform Area $ 298 . 00
Re-install plexiglass into window on North side $ 159 . 00
Replace Door into Detectives & Auditorium
Door & Frame Materials $ 877 . 00
Demo @ door into Auditorium In Demolition $$ Above $
Installation of frames & Doors TQS $ 418 . 00
Drywall Patching In Drywall Patch $ $ Above $
Wood Trim Materials $ 34 . 56
Wood trim Labor $ 150 . 00
Labor to Install Fill Behind Chiller $29100 . 00
Field Supervision/Project Management (2/01 /05 thru 11 /02/05 ) $ 2 , 532 . 23
Subtotal $ 56 , 197 . 61
OH & P @ 15 % $ 8 ,429 . 64
Subtotal $ 64, 627 . 25
Bond @ 01 % $ 646 . 27
Proposal Request # 6 Total $659273 .52