HomeMy WebLinkAbout2004-240 Addendum No.4 OA `2grj ORIGINAL. Scope of Services Indian River County Department of Utility Services Fellsmere/Pine Grove Appendix General PBS&J has been providing Master Planning and Hydraulic Modeling services to Indian River County Department of Utility Services (the COUNTY) under Addendum No . 1 and Addendum No . 2 to the September 4, 2001 Master Utility Plan Update Contract. The County has requested that PBS&J evaluate the potential to serve the Fellsmere/Pine Grove Development as a part of the on-going Master Plan Update . The County currently provides the City of Fellsmere (the CITY) limited bulk sewer service and has an emergency interconnect in place to provide potable water service if needed . Changes in drinking water standards, large scale planned growth, and other factors may affect the ability of City of Fellsmere to adequately provide service to its growing population . The County has shown interest in providing bulk water and wastewater service to meet all of the CITY ' s existing (current County commitments) and future water demands and wastewater flows but not a retrofit of the CITY . PBS &J will evaluate the impact of extending the County ' s water and wastewater service areas to include the Fellsmere/Pine Grove Development according to the following scope of services . Scope of Work The purpose of this planning effort is to analyze the impact of providing bulk service to the Fellsmere/Pine Grove Development on the Master Plan Update recommendations that were being updated exclusive of the City of Fellsmere or any other large bulk service customer . The County requested that PBS &J analyze two scenarios : 1 ) What level of service can be provided by the current Master Plan Update recommendations and 2) what transmission and treatment improvements would be necessary to incorporate the Fellsmere/Pine Grove Development water demands and wastewater flows as projected by others . The task of analyzing the reclaimed water system/treated wastewater disposal was not included in this authorization . Also , the retrofit of existing CITY customers and future growth within the CITY but not included in the reports by Masteller & Moler, Inc . and Hartman & Associates , Inc . was not included in this analysis . A technical memorandum (TM), which will be included as a separate appendix of the Master Plan Update, shall address the following major tasks : • Gather and evaluate data from Water Capacity Study/Report for the Pine Grove Development by Masteller & Moler, Inc . • Gather and evaluate data from City of Fellsmere CDBG Wastewater Transmission System Report by Hartman & Associates, Inc . 0 Develop feasible integrated water supply and treatment and wastewater collection and treatment alternatives . • Evaluate the water distribution and wastewater collection systems to accommodate the projected flows, from studies by others , within various service alternatives and the limits of County hydraulic standards . Pagel of 3 • U:\WO\Projects\IRCOUNTY\IRC_Utility_MasterPlan\01 Proposals\ l . ] Proposals\PBSJ-Scope_FellsmereASA4. doc • Evaluate the selected water and wastewater alternatives based on technical feasibility, County preference , and capital cost. • Establish planning level routing corridors and sizing of pipelines for water and wastewater service for the selected alternatives . • Identify treatment facility expansion requirements to meet anticipated water demands and wastewater flows . Indian River County ' s water and wastewater system priorities that impact the development of the Fellsmere Option include : • Maintaining water and wastewater service . • Complying with regulatory requirements . • Serving current and projected IRC demands for service in addition to the Fellsmere/Pine Grove Development needs . • Providing capacity in accordance with the concurrency requirements of the County ' s Comprehensive Plan • Constructing and maintaining adequate infrastructure for the planning period (2025 ) . • Operating economically. PBS &J will rely upon population, demand, and flow projections provided in studies performed by others (Masteller & Moler, Inc . and Hartman & Associates , Inc . ) which will be provided by the County . These water demands and wastewater flows will be added to those developed in the Master Plan Update by PBS&J. Schedule Work will be completed within 30 days of notice to proceed by the COUNTY. Compensation Compensation for this task will be a Lump Sum Amount of $ 18 , 600 . 00 . Monthly invoices will be based upon estimates of percent complete . Page 2 of 3 PWJ U:\WO\Projects\IRCOUNTY\IRC_Utility_MasterPlan\OI Proposals\l . I Proposals\PBSJ-Scope_FellsmereASA4.doc THIS WORK AUTHORIZATION, made and entered into on this 11 day of octobpr 2004 , by and between Indian River County and Post, Buckley, Schuh, & Jernigan, Inc . (PBS &J) , pursuant to the Master Utility Plan Update Agreement dated September 4 , 2001 . IN WITNESS WHEREOF, the parties hereto have made and executed this Agreement as of the day and year first above written . OWNER : ENGINEER : Indian River County Post, Buckley, S h & Je , Inc . Caroline D . Ginn, Chairman? Ro ,eft A . Morrell, P . E . , DEE Board of County Commissioners Vice President Indian River County PBS&J Octb -9.2 • • 42 IM -7 . Date ' Date Atte: J T . at�ton ' Clerk a suit eourtk p p r o v e d b A y : By: Deputy Clerk ��� ?Co 'u'ntytyse h A . Baird Administrator Approved as to form & Legal Sufficiency : M ian E '. Fell , ;°" Assistant County Attorney Page 3 of 3 • U:\WO\ProjectsURCOUNTY\IRC_Utility_MasterPlan\01 Proposals\ LI Proposals\PBSJ-Scope_FellsmereASA4. doc