WORK AUTHORIZATION DIRECTIVE p p
No . 2001 -071
44`h Street Community Water System Rehab Project
DATE OF ISSUANCE : November 4 , 2003 EFFECTIVE DATE : November 4, 2003
OWNER: Indian River County
CONTRACTOR: George E . French
CONTRACT : WATER, SEWER AND RECLAIM WATER LINE REPLACEMENT / EXTENSIONS
AND MISCELLANEOUS LABOR CONTRACT, UCP #909 BID NO . 3032 RENEWED
APRIL 1 , 2003
PROJECT : 44`h Street Community Water System Rehab Project
COUNTY UTILITY PROJECT NO . : UCP #2380 CONTRACTOR ' S PROJECT NO . : N/A
COUNTY W . I.P . No . 471 - 169000 -02524
You are directed to proceed promptly with the following work:
Description :
Purpose of Work Authorization Directive :
The construction of 6 " water main, fire hydrant, sleeves, water services , meter boxes , filling, flushing,
disinfecting, testing, and any necessary restoration to place the system into County service
Attachments : (List documents supporting work)
(Construction Plans showing extent of work are on file in the Utilities Department)
Method of determining Contract Price :
❑x Unit Prices : Bid Items as established pursuant to Bid No . 3032 , and awarded by the Board of County
Commissioners on January 7 , 2001 to George E . French; Renewed April 1 , 2003
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below :
Estimated Labor Cost = $ 16,401 . 95 Estimated Contract Time : 60 days
Contingency at 10% = $ 1 , 640 . 20
Total Estimated Labor Costs= $ 18 , 042 . 15
ACCEPTED : R4CME JD : APPROV
B B By :
Georg ren Gordon E . SE . neth R. Nfacht
Labor Contractor Environmental Engineer COUNTY, CHAIRMAN
Date / o '� � '— � Date : �G� ' G' 7 5 Date : 11 - 04 - 2003
Attachment 3
F :\Utilities\UTILITY - ENGINEERMTrojects - Utility Construction Permits\IRC - 44th Street Community Water System Rehab UCP
#2380\Work Authorization No . 2001 -071 . doc9