HomeMy WebLinkAbout2003-283 O�tGt� t
WORK AUTHORIZATION DIRECTIVE
No . 2001 -070 s e 4 Q
4"' Street @ US 1 Water & Force Main Relocations to Avoid Conflicts with Proposed FDOT
Drainage Improvements
DATE OF ISSUANCE : October 21 , 2003 EFFECTIVE DATE : November 3 , 2003
OWNER: Indian River County
CONTRACTOR: George E . French
CONTRACT : WATER SEWER AND RECLAIM WATER LINE REPLACEMENT / EXTENSIONS
AND MISCELLANEOUS LABOR CONTRACT UCP #909 BID NO . 3032 RENEWED
APRIL 1 2003
PROJECT : US 1 water main & force main conflicts with proposed FDOT drainage improvements on US
1 near 0 Street
COUNTY UTILITY PROJECT NO . : UCP #2354 CONTRACTOR ' S PROJECT NO . : N/A
COUNTY W . I.P . No . 471 - 169000-02524
You are directed to proceed promptly with the following work:
Description:
Purpose of Work Authorization Directive :
The construction of widening and drainage improvements on US 1 north and south of 4 1 Street will cause conflicts
with existing County water and sewer mains that must be resolved prior to construction by the FDOT
Attachments : (List documents supporting work)
Attachment A Construction Plans showing extent of work (On file in Utilities Department)
Method of determining Contract Price :
[] Unit Prices : Bid Items as established pursuant to Bid No . 3032 , and awarded by the Board of County
Commissioners on January 7, 2001 to George E . French; Renewed April 1 , 2003
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below:
Estimated Labor Cost = $ 102 ,248 . 05 Estimated Contract Time : 60 days
Contingency at 10% = $ 10, 224 . 81
Total Estimated Labor Costs= $ 1125472 . 86
ACCEPTED : REAGordon
END APPROV
By: By.
eo rench E . Sparks, E . enneth R. Macht
Labor Contractor Environmental Engineer COUNTY, CHAIRMAN
Date : Jp _ g " vim Date : ,� - Jl 0 �e3 Date : 10 - 21 - 2003
Attachment 4
F :\Utilities\UTILITY - ENGINEERING\Projects - Utility Construction Permits\IRC - 4th Street @ US 1 Water-Sewer Main Conflicts with FDOT
Drainage UCP#2354\Work Authorization No. 2001 -070 , Attachment 4 .doc9