AMENDMENT NUMBER 1 TO WORK ORDER NUMBER 15
This Amendment 1 to Work Order Number 15 is entered into as of this 13th
day of October 2009 ( " Effective Date " ) pursuant to that certain Continuing
Contract Agreement for Professional Services entered into as of 10 August , 2004 , and
amended effective 1 August 2009 ( as so amended , the "Agreement" ) , by and between
Indian River County Solid Waste Disposal District , a dependent special district of Indian
River County , Florida , ( " District" ) and Geosyntec , Inc . ( " Consultant" ) .
1 . The District has selected the Consultant to perform the professional services
set forth in existing Work Order Number 15 , Effective Date 15 August 2008 ,
2 . The District and the Consultant desire to amend this Work Order as set forth
on Exhibit 1 attached to this Amendment and made part hereof by this reference , The
professional services will be performed by the Consultant for the fee schedule set forth in
Exhibit 1 and within the timeframe more particularly set forth in Exhibit 1 , all accordance
with the terms and provisions set forth in the Agreement .
3 . From and after the Effective Date of this Amendment , the above - referenced
Work Order is amended as set forth in this Amendment . Pursuant to paragraph 1 . 4 of
the Agreement , nothing contained in any Work Order shall conflict with the terms of the
Agreement and the terms of the Agreement shall be deemed to be incorporated in each
individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Amendment to
Work Order as of the date first written above .
CONSULTANT , INDIAN RIVER COUNTY SOLID
Geosyntec Consultants , Inc . WASTE DISPOS DISTRICT
By : wee zz
Thomas A . Peel , Ph . D , esl ey S . Davis , Chairman
Title : Vice President Attest : J . K . Barton , Clerk of Court
By : � - (s, ,..
Deputy Clerk
Approved :
� 2
seph Ai BairdCounty Administrator
it
A'pprove'd as to form and al sufficiency :
Mar a County Attorney
EXHIBIT 1
PROFESSIONAL SERVICES
130CA/ FR1545 AS "FDOC
cn iIn rs ( innOv; Itr � r5
Geospte & 5901 Broken Sound Parkway,
Suite 300
Boca Raton . Florida 33487
consultants P11 501 -995 -0900
FAX W -995 -0925
W \% " .geosvlllec .c(1111
18 September 2009
Mr . Himanshu Mehta
Managing Director
Solid Waste Disposal District
Indian River County
1325 74 "' Avenue Southwest
Vero Beach , Florida 32968
Subject : Budget Evaluation and Change Order Request No . I (Amendment No . 1 to Work
Order No . 15 )
Fuel Tank Relocation — From Former DOT Facility to Landfill
Geosyntec Project No . FR1545 ( IRC Work Authorization No . 15 )
Dear Mr . Mehta :
In response to your request for a current budget evaluation regarding the Indian River County
( IRC) Aboveground Storage Tank ( AST) project ( Work Order No . 15 ) , Geosyntec Consultants ,
Inc . (Geosyntec) has prepared this letter and cost table ( Table 1 ) in Attachment 1 . Attachment 1
includes an upAo - date listing of items not included in the original Work Order No . 15 and
assigns their individual costs within the requested change order budget . For clarification , an
itemized breakdown of the original proposal ' s Construction Contingency budget of $ 15 , 760
approved by IRC is shown in Attachment 1 . Items associated with the requested change order
budget include the following :
• Additional design , administration , and correspondence preparation effort required by
Geosyntec for the permitting process and project completion (see Items 2 , 4 , 5 , 15 , and
17 on attached Attachment 1 ) .
• Additional subcontractor costs associated with work/equipment not included in the
original scope and Geosyntec ' s effort regarding coordination , oversight , etc , associated
with the additional subcontractor scope costs ( see Items 6 through 14 , 16 , and 18 on
attached Attachment I ) .
130CA/FRI545 AST . DOC
I , i13, in � � l � i �, I 1 11111Oy , IImS
Himanshu Mehta , P . E . CreosynteC ''
18 September 2009 iMi 111i , iiii1 .
Page 2
Please note that Item 19 on Attachment 1 reflects a credit for IRC to the overall project budget,
which relates to the Gifford Road AST Sampling/ Relocation (Task 2) as indicated in Exhibit 2 of
IRC ' s Work Order No . 15 . Based on recent communications with Charles Vogt , IRC
Department of Health , the closure inspection for the MOT site is complete and we will not have
to complete the closure sampling as originally scoped . However, some type of reporting
document that will include observations and tank tightness testing documentation will still be
required for this Task . Therefore , we have estimated approximately $2 , 100 to be representative
of the effort and expenses associated with the sampling activities that are no longer required for
the project , which has been incorporated as a credit to IRC in the attached table .
SCHEDULE
To date , work associated with Phases 1 , 2 , 6 and 7 of Work Order No . 15 have been completed
,
except for limited reporting documentation preparation associated with Phase 2 (Gifford Road
Sampling Relocation ) . The limited reporting required for Phase 2 is expected to be prepared
within the same timeframe as the reporting required in Phase 5 ( IRC Landfill Closure Report ) .
Phase 3 ( IRC Landfill AST Construction and Installation) and Construction Contingency
activities included in Work Order No . 15 are mostly completed and AST startup activities are
expected to be initiated in early October 2009 . Once the AST relocated to the landfill is
operational , activities will be initiated for the remaining Work Order No . 15 scope items , which
include Phase 4 ( IRC Landfill Existing AST Closure) and Phase 5 ( IRC Landfill AST Closure
Report) . Please note that items in Change Order Request No . 1 include tasks that have been
completed to - date or tasks that are to be completed in conjunction with Phase 3 ( IRC Landfill
AST Construction and Installation ) .
130CA/ FRI 545 ASf . DOC
� it „ in � t3s ► ' , + illisi ► 1iw17 � � �; ift � r �,
Himanshu Mehta, P . E . GeOSyntec
18 September 2009
Page 3
CLOSURE
Geosyntec appreciates the opportunity to provide services to Indian River County . If you have
any questions regarding this correspondence , please feel free to contact me at ( 561 ) 995 - 0900 or
Jim Langenbach at (321 ) 269 - 5880 .
Sincerely ,
Dean Pinson , P . E .
Project Engineer
Jim Langenbach , P . E .
Associate
Attachment
130CA/ PR1545 AS 'T . DOC
1111 , 10 wcr1 " , t ii ' i1li `; { ", IllllOV � l � UrS
ATTACHMENT 1
COST PROPOSAL
BOCA / PR 1545 AS F DOC
Geosyntec Consultants
Table 1
Summary of Estimated Costs
Indian River County Solid Waste Disposal District
Change Order Request No. 1 for IRC Work Order No. 15
IRC AST Relocation Project
Propo, al Nu_ .rRUX051 Change Order
Existing Requested Change
Contingency Order Budget
Budget ( Geosyntec requests
( approved for use by for approval by
Item Item Description IRC on 12/2/20 (18) IRC )
I Sr . Resource Center Test Pits/NEPA/conference calls $4 , 200 NA
2 Permitting effort with IRC Community Development Division $967 $ 750
3 Subcontractor' s original clectrieal connection scope add-on as requested by IRC $ 10,593 NA
4 Additional electrical design effort required by IRC Building Division NA $ 1 ,250
5 Additional permitting effort required by IRC Building Division NA $ 1 ,450
Subcontractor's electrical connection scope change order for separate metal conduit required
6 for communication line NA $2 , 300
:]
7 K800 Hybrid card reader upgrade ( approved by IRC on 7/21 /2009) NA $ 1 ,495 . 86
8 Vac truck required for AST relocation at Gifford Road NA $6411
9 Vac truck required for existing landfill AST (less proposed drum sludge disposal ) NA $ 650
10 Repair of Gifford Rd AST components NA $ 1 ' 700
11 hour (4) additional bollards ( required by code) NA $ 750
12 ASrlq tightness testing (before and after relocation) NA $ 1 '37 (1
13 Suy
rveing ( required for Item 15 ) NA $ 540
Non -scope items for AS' f installation ( required by comments from IRC Building Division
and/or 18 .lune 2009 IRC Fire Division letter) , which include the purchase and installation of
NA $ 6 '4011
14 the following :
$ ,2, 920 - Two (2) emergency slop, electrical disconnect shunt t} pe requiring
in o step reset
52. 160 - Two (2) anti-siphon solenoid valve with manual override
5305 - 751, o ( ') anion top emergency sheer valves
$ 280 - Two (2) expansion release valves
$ 385 - Tn o (2) leak detector tees
$ 350 - fire exiinguisher and installations
15 As -built drawing and O& M manual preparation NA $ 1 . 8511
16 Painting of AST and
by IRC on 8/27/2009) NA $ 1 , 016 . 50
17 Design and oversight effort for additional 10' x 12 ' concrete fueling pads NA $ 7 (111
18 Subcontractor' s construction cost for two (2) additional 10' xlT concrete fueling pads NA $ 5 , 136
19 Credit to /RC fnr sampling not required fir Gifford Road AST relocate
N - $ 2. 100. 00
$ 159760 $259898.36
Total
Note : The currently authorized budget for Work Order No. 15 is $132,474.00 (including $ 15,760 contingency), which was
approved by IRC Board on 05 August 2008. The Change Order request listed above of $25,898.36 would bring the total
budget for this project to a grand total of $ 158,372.36.
1:I [ 1595 IRC AST Chance Ordcr( FINAL) sls