HomeMy WebLinkAbout2008-009 (3)SECTION 00632 - CONTRACTOR'S FINAL CERTIFICATION
OF THE WORK
r (TO ACCOMPANY CONTRACTOR'S FINAL APPLICATION FOR PAYMENT)
STATE OF _
COUNTY OF
Personally before me the undersigned officer, authorized by the laws of said state to
administer oaths, comes who on oath
Indian River County, Florida, a political
says: That he is the CONTRACTOR with whom
subdivision of said state, did on the day of
into a contract for the performance of certain work,
more
,20, enter
particularly described as follows:
CR 512, PHASE IV ROADWAY IMPROVEMENTS
r UNDER PENALTY OF PERJURY, affiant further says that said construction has
been completed and the Contract therefore fully performed and final payment is now due
and that all liens of all firms and individuals contracting directly with or directly employed by
�r such CONTRACTOR have been paid in full EXCEPT:
Name Description/Amount
r
who have not been paid and who are due the amount set forth.
Affiant further says that:
IN
CONTRACTOR has reviewed the Contract Documents.
r 2. CONTRACTOR has reviewed the Work for compliance with the Contract
Documents.
r 3. CONTRACTOR has completed the Work in accordance with the Contract
Documents.
r
4. All equipment and systems have been tested in the presence of the ENGINEER or
his representative and are fully operational with no defects or deficiencies except as
listed below.
5. The Work is complete and ready for final acceptance by the OWNER.
00632-1
F:1Engineering\Capital Projects\9611-CR 512 Widening19611 CR 512 PHASE MContract Documents100632 - Contractofs Final
Certification REV 04-07.doc
r
DATE OF ISSUANCE:
SECTION 00942 - Change Order Form
No.
EFFECTIVE DATE:
OWNER: Indian River County
CONTRACTOR
Bid Number:2008012
r Project: CR 512, PHASE IV ROADWAY IMPROVEMENTS
OWNER's Contract No. ENGINEER's Contract No. NIA
ENGINEER IRC
W
r
M
M
C
r
r
W
M
You are directed to make the following changes in the Contract Documents:
Description:
Reason for Change Order:
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE:
Descri tion
Amount
Original Contract Price
$
Net Increase (Decrease) from
$
previous Change Orders No.
Completion:
to
Final
Contract Price prior to this
$
Change Order:
Net increase (decrease) of this
$
Change Order:
Substantial
Contract Price with all approved
$
Change Orders:
Completion:
ACCEPTED
By:
CONTRACTOR (Signature)
r
Date:
CHANGE IN CONTRACT TIMES
Description
Time
Original Contract Time:
(days or dates)
Substantial
Completion:
_
Final
Completion:
Net change from previous Change
Orders No. _ to
(days)
Substantial
Completion:
Final
Completion:
Contract Time prior to
this Change
Order:
(days or dates)
Substantial
Completion:
Final
Completion:
Net increase (decrease) this
Change Order:
(days or dates)
Substantial
Completion:
_
Final
Completion:
Contract Time with all
approved
Change Orders:
(days or dates)
Substantial
Completion:
Final
Completion:
RECOMMENDED:
By:
By:
OWNER (Sig
Date:
00942 - Change Order Form REV 04-07.doo
00942-1
F:\Engineering\Cap@al Pro*ds\9611-CR 512 Widening19611 CR 512 PHASE INConvact Documents\00942 -Change Order Fonn REV 04-07 doc
M
0
IM
SECTION 00946 - Field Order Form
Field Change No.:
DATE OF ISSUANCE: EFFECTIVE DATE:
OWNER: Indian River County
CONTRACTOR
Bid Number: 2008012
Project: CR 512 PHASE IV ROADWAY IMPROVEMENTS
OWNER's Contract No. ENGINEER's Contract No. NIA
ENGINEER: IRC
Field Activity Description:
r
•
Reason for Change:
to
Recommended Disposition:
w
•r
Field Operations Officer/ Engineer (Signature) Date
• Disposition:
Contractor's Onsite Supervisor (Signature) Date
Distribution: Field Operations Officer Others as Required:
w On-site Supervisor
Project File
* * END OF SECTION * *
00946 - Field Order Forth REV 04-07.doc
F:\Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE IV\Contract Documents\00946 - Field Order Form
REV 04-07.doc
r -
DATE OF ISSUANCE:
SECTION 00948 - Work Change Directive
EFFECTIVE DATE:
No.
OWNER: Indian River County
CONTRACTOR:
Bid Number: 2008012
' Project: CR 512, Phase IV Roadway Improvements
OWNER's Contract No. ENGINEER'S Contract No. N/A
ENGINEER: IRC
r
You are directed to proceed promptly with the following changes:
Description:
to
Purpose of Work Change Directive:
177
Attachments: (List documents supporting change)
•
If OWNER or CONTRACTOR believe that the above change has affected Contract Price any
Claim for a Change Order based thereon will involve one or more of the following methods as
defined in the Contract Documents.
Method of determining change in
Contract Prices:
Unit Prices
w ❑ Lump Sum
❑ Other:_
❑ By Change Order:
Estimated increase (decrease) in Contract Price:
If the change involves an increase, the estimated
amount is not to be exceeded without further
authorization.
RECOM
By:
W
(Authorized
Method of determining change in
Contract Times
Q Contractor's Records
Q Engineer's Records
❑ Other:_
❑ By Change Order:
Estimated increase (decrease) in Contract Times:
Substantial Completion: days;
Ready for Final Completion: _ days.
If the change involves an increase, the estimated
time is not to be exceeded without further
authorization.
AUTHORIZED:
By:
* * END OF SECTION * *
Signature)
1r F:\Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE IV\Contmct Documents\00948 - Work Change
Directive REV 04-07.doc
r
r
r
r
m
LL
DIVISION 1
GENERAL REQUIREMENTS
DIVISION 1 GENERAL REQUIREMENTS
r TITLE SECTION NO.
r
SPECIAL PROVISIONS 01009
FORCE ACCOUNT 01024
r FIELD ENGINEERING AND LAYOUT 01050
r REFERENCE STANDARDS 01091
GENERAL QUALITY CONTROL 01215
PROGRESS MEETINGS 01220
,. CONSTRUCTION SCHEDULES 01310
SUBMITTAL OF SHOP DRAWINGS, PRODUCT
r DATA AND SAMPLES 01340
r
F.\Engineering\Capital Projects\9611.CR 512 Widening\9611 CR 512 PHASE MContrad DocumentsUVISION 1 GENERAL
REOUIREMENTS.doc
r
CONSTRUCTION FACILITIES AND TEMPORARY
r
CONTROLS
01520
PROTECTION OF THE WORK AND PROPERTY
01541
r
ACCESS ROADS, PARKINGS AREAS AND USE OF
PUBLIC STREETS
01550
r
TRANSPORTATION AND HANDLING OF MATERIALS
01610
AND EQUIPMENT
r
STORAGE OF MATERIAL AND EQUIPMENT
01611
SUBSTITUTIONS
01630
SITE CLEANUP AND RESTORATION
01710
r
RECORD DOCUMENTS
01720
r
F.\Engineering\Capital Projects\9611.CR 512 Widening\9611 CR 512 PHASE MContrad DocumentsUVISION 1 GENERAL
REOUIREMENTS.doc
r
go
r
SECTION 01009
SPECIAL PROVISIONS
r
1.1 GENERAL
A. Visits to the construction site may be made by representatives of permitting or
governing bodies. Submit details of all instructions from the above to the ENGINEER
immediately. The Work will not be accepted by the OWNER until final acceptance has
been received from the various Regulatory Agencies having jurisdiction.
B. Furnish sufficient labor, construction equipment and materials, and work such hours,
including night shifts and overtime operations, as may be necessary to insure the
prosecution of the work in accordance with the approved progress schedule. If, in the
opinion of the ENGINEER, the CONTRACTOR falls behind the progress schedule, take
such steps as may be necessary to improve progress, all without additional cost to the
OWNER. The ENGINEER shall be compensated for his overtime services in
.. accordance with the Supplementary Conditions, SC -6.02.
C. All salvageable material and equipment for which specific use, relocation or other
r disposal is not specifically noted, shall remain the property of the OWNER and shall be
delivered to the OWNER at the following location: 4550 41St Street, at the
CONTRACTOR's expense. All material and equipment not in salvageable condition, as
.. determined by the ENGINEER and the OWNER, shall be disposed of by the
CONTRACTOR, at the CONTRACTOR's expense.
+■ D. In addition to these Specifications all work must comply with the requirements of the
local governing agency, St. Johns River Water Management District, Department of
Environmental Protection, Corps of Engineers, Indian River Farms Water Control
District, and all other applicable State or Federal agencies' specifications and permits.
In the event of a conflict, the more stringent specification or requirement shall govern.
E. Before performing any work outside the designated limits of the work site, secure any
necessary permits and authorization from the applicable owner, or verify in writing that
such has been previously obtained. Follow all requirements of any said permits or
• authorization. Give the ENGINEER and appropriate owner ten (10) days minimum
notice before commencing construction operations outside the designated limits of the
work site. Adjacent property owners at time of bidding are listed below.
an
In
0
01009-1
01009 -Special Provisions
i F:\Engineering\Capital
Projects\9611-CR
512 Widening\9611
CR 512 PHASE
IV\Contract Documents\01009 - Special Provisions.doc
M SECTION 01024
r FORCE ACCOUNT
1.1 General
CONTRACTOR shall furnish all labor, materials, equipment and incidentals
r necessary to perform additional work not covered on the Contract Drawings.
The force Account is intended as a contingency for unforeseen work.
r 1.1 PAYMENT
A. Lump sum amount for force account work is included in the bid schedule.
.. The value of force account work will be determined in accordance with Article
12 of the General Conditions.
M
M
M
•
M
1
+ + END OF SECTION + +
01024- 1
F:\Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents\01024 - Force Account.doc
M SECTION 01050
FIELD ENGINEERING AND LAYOUT
am
1.1 GENERAL
• A.
The CONTRACTOR will furnish all construction staking for the project. All
Field
staking from control will be under the supervision of a Florida Registered Land
,.
Surveyor.
B.
Develop and make all detail surveys and measurements needed for
construction including but not limited to, slope stakes, batter boards, piling
layouts and all other working lines, elevations and cut sheets.
C.
Keep a transit and leveling instrument on the site at all times and a skilled
instrument man available whenever necessary for layout of the Work.
.. D.
Provide all material required for benchmarks, control points, batter boards,
grade stakes, and other items.
E.
Be solely responsible for all locations, dimensions and levels. No data other
r
than written orders of the ENGINEER shall justify departure from the
dimensions and levels required by the Drawings.
F.
Safeguard all points, stakes, grademarks, monuments and benchmarks made
•
or established on the Work, and reestablish same, if disturbed. Rectify all Work
improperly installed because of not maintaining, not protecting or removing
without authorization such established points, stakes, marks and monuments.
G.
When requested by the ENGINEER, provide such facilities and assistance as
may be necessary for the ENGINEER to check line and grade points placed by
the CONTRACTOR. Do no excavation or embankment work until all
cross -sectioning necessary for determining pay quantities has been completed
and checked by the ENGINEER.
H.
The cost of performing engineering and layout work described above shall be
included in the contract unit prices for the various items of work to which it is
incidental. No separate payment will be made for surveying or engineering.
1.2 SURVEY WORK AND QUALIFICATIONS OF SURVEYOR
A. Prior to commencing work, the CONTRACTOR shall satisfy himself as to the
accuracy of all survey and existing site information as indicated in the Contract
Documents. Immediately notify the ENGINEER upon discovery of any errors,
inaccuracies or omissions in the survey data. The commencing of any of the
work by the CONTRACTOR shall be held as the CONTRACTOR's acceptance
that all survey or existing site information is correct and accurate, without any
reasonably inferable errors, inaccuracies or omissions.
•
1=1
1050-1
01050
Field
Engineering
F.\Engineering\Capital Prcjec1s19611-CR 512 Widening19611
CR 512 PHASE MContmd Documents\01050 -
Field Engineeringg doc
1=1
W
I
B. The CONTRACTOR shall carefully preserve all control stakes, benchmarks,
reference points and property corners and will be responsible for any mistake or
loss of time caused by their unnecessary loss or disturbance. If the loss or
disturbance of the stakes or marks cause a delay in the Work, the
CONTRACTOR shall have no claim for damages or extension of time. Control
stakes, benchmarks, reference points and property corners disturbed by the
CONTRACTOR's work shall be replaced by a Florida Registered Land Surveyor
and Mapper, at the CONTRACTOR's expense. In the event the Owner must
provide the services of the Florida Registered Surveyor and Mapper to perform
this replacement work, the cost of the surveying services will be deducted from
,,. any sums due the CONTRACTOR for the work performed Under this Contract.
C. All survey work shall be performed under the guidance and direction of a Florida
up Registered Surveyor and Mapper.
D. All survey work for Record Drawings shall be performed by a Florida Registered
Surveyor and Mapper.
1_3 STATION BOARDS
A. CONTRACTOR shall erect and maintain white/black standard FDOT station
markers every 100 feet.
r
1.4 LAYOUT OF STRIPING
Establish by instrument, and mark the finished surface, the points necessary for
r striping finished roadway in conformance with Section 5-7 of FDOT Standard
Specifications.
r
M
+ + END OF SECTION + +
W
r^
of
1050-2 01050 Field Engineering
r F:1EngineeringlCapital PrgeG \9611 -CR 512 Widening19611 CR 512 PHASE J=ontract Documents\01050-Field Engineering.doc
No
7]
r
VA
M
r
M
r
r
M
r
W
C]
SECTION 01091
REFERENCE STANDARDS
1.1 GENERAL
A. Whenever reference is made to the furnishing of materials or testing
thereof to conform to the standards of any technical society, organization
or body, it shall be construed to mean the latest standard, code,
specification or tentative specification adopted and published at the date
of advertisement for bids, unless noted otherwise in the Technical
Specifications or on the Drawings. When a reference. standard is
specified, comply with requirements and recommendations stated in that
standard, except when they are modified by the Contract Documents, or
when applicable laws, ordinances, rules, regulations or codes establish
stricter standards. The list of specifications presented in Paragraph B is
hereby made a part of the Contract, the same as if repeated herein in full.
B. Reference to a technical society, organization, or body may be made in
the Specifications by abbreviations; in accordance with the following list:
AASHTO The American Association of State Highway and
Transportation Officials
ACI American Concrete Institute
AGA American Gas Association
AISC American Institute of Steel Construction
AISI American Iron and Steel Institute
ANSI American National Standards Institute
ASCE American Society of Civil Engineers
ASTM American Society for Testing and Materials
AWPAAmerican Wood Preservers Association
AWWA American Water Works Association
AWS American Welding Society
FED.SPEC. Federal Specifications
01091-1
01091 Reference
Standards
F:\Engineering\Capital
Projects\9611-CR 512 Widening\9611 CR
512 PHASE MConlracl Documents\01091 -Reference
Standards.doc
M
W
r�.
r
01091-2 01091 Reference Standards
P:\EngineeringSCapital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents101091 -Reference Standards. doc
CRSI
Concrete Reinforcing Steel Institute
FDEP/DEP
Florida Department of Environmental Protection
DNR
Department of Natural Resources
NCPI
National Clay Pipe Institute
NEMA
National Electrical Manufacturers Association
r
NEC
National Electric Code
•
NSPE
National Society of Professional Engineers
OSHA
Occupational Safety and Health Administration
•
PCI
Prestressed Concrete Institute
FDOT/DOT
Florida Department of Transportation
U. L., Inc.
Underwriter's Laboratories, Inc.
r
SSPC
Steel Structures Painting Council
`
SJRWMD
St. Johns River Water Management District
C. When no reference is made to a code, standard or specification, the
standard specifications of ASTM, FDOT, or ANSI shall govern.
D. In the event
of a conflict between the specifications prepared by the
ENGINEER
and the above referenced specifications and standards, or
any other regulatory
specification or standard, the more stringent
requirement
prevails.
+ + END OF SECTION + +
M
W
r�.
r
01091-2 01091 Reference Standards
P:\EngineeringSCapital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents101091 -Reference Standards. doc
No
n
W
•
SECTION 01215
GENERAL QUALITY CONTROL
• 1.1 DESCRIPTION OF REQUIREMENTS
A. Definitions: Specific quality control requirements for the work are indicated
t., throughout the Contract Documents. The requirements of this section are
primarily related to the performance of the work beyond the furnishing of
manufactured products. The term "Quality Control' includes, but is not
r necessarily limited to, inspection and testing and associat6d requirements.
This section does not specify or modify the OWNER and ENGINEER duties
relating to quality review and Contract surveillance.
•
1.2 RESPONSIBILITY FOR INSPECTIONS AND TESTS
+� A. Residual OWNER Responsibility: The OWNER will employ and pay for the
services of independent testing laboratories to perform those required
inspections and tests.
•
B. CONTRACTORS General Responsibility: No failure of test agencies, whether
engaged by the OWNER or CONTRACTOR, to perform adequate inspections
of tests or to properly analyze or report results, shall relieve the
CONTRACTOR of responsibility for the fulfillment of the requirements of the
Contract Documents. It is recognized that the required inspection and testing
• program is intended to assist the CONTRACTOR, OWNER, ENGINEER, and .
governing authorities in the nominal determination of probable compliance with
requirements for certain crucial elements of work. The program is not intended
• to limit the CONTRACTOR in his regular quality control program, as needed for
general assurance of compliance.
1.3 QUALITY ASSURANCE
A. General Workmanship Standards: It is a requirement that each category of
`r tradesman or installer performing the work be pre -qualified, to the extent of being
familiar with the applicable and recognized quality standards for his category of
• work, and being capable of workmanship complying with those standards.
1.4 PRODUCT DELIVERY -STORAGE -HANDLING
• Handle, store and protect materials and products, including fabricated components, by
methods and means which will prevent damage, deterioration and losses (and resulting
delays), thereby ensuring highest quality results as the performance of the work
progresses. Control delivery schedules so as to minimize unnecessary long-term
storage at the project site prior to installation.
r
01215-1 01215 General Quality Control
F9Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents\01215 General Quality.doc
J
1.5 PROJECT PHOTOGRAPHS/VIDEOS
A. The CONTRACTOR shall make provisions, at his expense, for video tapes of all
work areas just prior to construction, and for unusual conditions during construction.
The videos shall show pertinent physical features along the line of construction.
The purpose of the videos is to determine any damage to private or public property
during construction.
B. Pre -Construction Video:
1. Contractor shall provide the Owner with a video record and one copy of the
existing conditions prior to construction. This video shall be a standard VHS
cassette format, and shall be narrated.
.r 2. The video shall include, but not be limited to, the following items shown in a
clear manner:
W
W
LJ
W
W
CL
1) All existing features within the right-of-way.
2) All existing features within the temporary construction easement.
3) All existing features within permanent easements.
4) All existing features adjacent to any construction.
3. Detail of the video shall be such that the following examples shall be clear and
visible:
1) Cracks in walls.
2) Condition of fencing.
3) Condition of planted areas and types of vegetation.
4) Condition of sodded areas.
5) Conditions of sprinkler systems and associated controls and wiring.
6) Condition of signs.
7) Conditions of lighting and associated wiring.
8) Significant detail of any pre-existing damages physical features shall be
shown. The coverage of the video should include the limits of effects of
the use of vibratory rollers.
9) This video record shall be presented to the Owner within 30 days of the
Notice to Proceed. A copy shall be kept in the Contractor's field office.
10)Payment— No additional payment will be made for this work.
+ + END OF SECTION + +
01215-2 01215 General Quality Control
F:\Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents\01215 General Quality.doc
73
SECTION 01220
PROGRESS MEETINGS
• 1.1 SCOPE
A. Date and Time:
1. Regular Meetings: As mutually agreed upon by ENGINEER and
CONTRACTOR.
2. Other Meetings: On call.
• B. Place: CONTRACTOR'S office at Project site or other mutually agreed upon
location.
C. ENGINEER shall prepare agenda, preside at meetings, and,prepare and
distribute a transcript of proceedings to all parties.
D. CONTRACTOR shall provide data required and be prepared to discuss all items
on agenda.
•
1.2 MINIMUM ATTENDANCE
A. CONTRACTOR
B. SUBCONTRACTOR:
When needed for the discussion of a particular agenda item, CONTRACTOR
r shall require representatives of Subcontractors or suppliers to attend a meeting.
C. ENGINEER.
• D. OWNER'S representative, if required.
E. Utility Representatives
F. Others as appropriate.
G. Representatives present for each party shall be authorized to act on their behalf.
1.3 AGENDA
w
Agenda will include, but will not necessarily be limited to, the following:
1. Transcript of previous meeting.
2. Progress since last meeting.
3. Planned progress for next period.
4. Problems, conflicts and observations.
5. Change Orders.
6. Status of Shop Drawings.
7. Quality standards and control.
• 8. Schedules, including off-site fabrication and delivery schedules. Corrective
measures, if required.
9. Coordination between parties.
10. Safety concerns.
11. Other business.
+ + END OF SECTION + +
01220-1
01220 Progress Meetings
P:\Engineenng\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE I\AContract Documents\01220 - Progress Meetings. doc
r
SECTION 01310
CONSTRUCTION SCHEDULES
1.1 GENERAL REQUIREMENTS
A. No partial payments shall be approved by the ENGINEER until there is an
,. approved construction progress schedule on hand.
B. Designate an authorized representative who shall be responsible for
r development and maintenance of the schedule and of all progress and
payment reports. This representative shall have direct project control and
complete authority to act on behalf of the CONTRACTOR in fulfilling the
r commitments of the CONTRACTOR's schedules.
M
n
1.2 REVISIONS TO THE CONSTRUCTION SCHEDULES
When the ENGINEER requires the CONTRACTOR to submit revised (updated)
progress schedules on a monthly basis the CONTRACTOR shall:
A. Indicate the progress of each activity to the date of submission.
r B. Show changes occurring since the previous submission listing:
1. Major changes in scope.
2. Activities modified since the previous submission.
3. Revised projections of progress and completion.
4. Other identifiable changes.
" C. Provide a narrative report as needed to define:
1. Problem areas, anticipated delays, and the impact on the schedule.
2. Corrective action recommended and its effect.
3. The effect of changes on schedules of other prime contractors.
r
1.3 SUBMISSION OF THE CONSTRUCTION SCHEDULES
On or before the tenth day after the effective date of the Agreement, submit the
initial schedules to the ENGINEER. The ENGINEER will review the schedules
r and return a review copy to the CONTRACTOR within 21 days after receipt. If
required by the ENGINEER, resubmit revised schedules on or before the seventh
day after receipt of the review copy. If required by the ENGINEER, submit
revised monthly progress schedules with that month's application for payment.
17
01310-1 01310 Construction Schedule
F:\Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE IV\Contract Documents\01310 -Construction
r Schedule.doc
J
..
M
1.4 DISTRIBUTION OF THE CONSTRUCTION SCHEDULES
A. After receiving approval by the ENGINEER, distribute copies of the
approved initial schedule and all reviewed revisions (updated) to:
1. Job site file.
2. Subcontractors.
3. Other concerned parties.
4. OWNER (two copies).
5. ENGINEER
r B. In the cover letter, instruct recipients to report promptly to the
CONTRACTOR, in writing, any problems anticipated by the projections
shown in the schedules.
+ + END OF SECTION + +
F-
71
W
W
n
n
M
01310-2 01310 Construction Schedule
F:\Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE I\Acontract Documents101310 -Construction
Schedule.doc
M
or
771
01340 - Submittal of Shop Drawings.doc
Y 1.1 SCOPE
A. Submit shop drawings, product data and samples as required by or
inferred by the Drawings and Specifications. Submittals shall conform to
the requirements of Article 6.17 of the General Conditions, Section 00700,
and as described in this Section.
1.2 SHOP DRAWINGS
r A. Shop drawings are original drawings, prepared by the CONTRACTOR, a
subcontractor, supplier, or distributor, which illustrate some portion of the
work; showing fabrication, layout, setting, or erection details. Shop
.. drawings are further defined in Article 6.17, Section 00700.
B. Shop drawings shall be prepared by a qualified detailer and shall be
ow identified by reference to sheet and detail numbers on the Contract
Drawings.
W 1.3 PRODUCT DATA
A. Product data are manufacturer's standard schematic drawings and
r manufacturer's catalog sheets, brochures, diagrams, schedules,
performance charts, illustrations, and other standard descriptive data.
Product data are further defined in Article 6.17, Section 00700.
r
B. Modify standard drawings to delete information which is not applicable to
the project and supplement them to provide additional information
applicable to the project.
C. Clearly mark catalog sheets, brochures, etc., to identify pertinent
" materials, products, or models.
.r
1.4 SAMPLES
Samples are physical examples to illustrate materials, equipment, or
workmanship and to establish standards by which work is to be evaluated.
` Samples are further defined in Article 6.17, Section 00700.
M
01340 - Submittal of Shop Drawings.doc
01340-1
r F.\Engineenng\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE IV\Contract Documents\01340 -Submittal of Shop Drawings.doc
fm
r 01340 - Submittal of Shop Drawings.doc
1.5 CONTRACTOR'S RESPONSIBILITIES FOR SUBMITTAL OF SHOP
DRAWINGS, PRODUCT DATA AND SAMPLES
01340 -Submittal of Shop Drawings.doc
01340-2
r F9Engineering%Capital Pro)ects19611-CR 512 Wideningt9611 CR 512 PHASE IV1Contract Documents101340 - Submittal of Shop Drawings.doc
A. The CONTRACTOR's responsibilities for submittal of shop drawings,
product data, and samples are set forth in paragraph 6.17 of the General
Conditions and as further explained herein.
B. Prior to submission, thoroughly check shop drawings, product data, and
samples for completeness and for compliance with the Contract
Documents, verify all dimensions and field conditions, and coordinate the
shop drawings with the requirements for other related work. Also review
each shop drawing before submitting it to the ENGINEER to determine
that it is acceptable in terms of the means, methods, techniques,
r
sequences and operations of construction, safety precautions and
programs incidental thereto, all of which are the CONTRACTOR's
responsibility.
1. It is CONTRACTOR'S responsibility to review submittals made by
his suppliers and Subcontractors before transmitting them to
ENGINEER to assure proper coordination of the Work and to
determine that each submittal is in accordance with its desires and
that there is sufficient information about materials and equipment
for ENGINEER to determine compliance with the Contract
"
Documents.
2. Incomplete or inadequate submittals will be returned for revision
without review.
rt
C. The CONTRACTOR's responsibility for errors and omissions in submittals
is not relieved by the ENGINEER's review of submittals. The
CONTRACTOR shall approve the shop drawings based on his in -the -field
measurements, prior to submittal to the ENGINEER for his review.
D. Notify the ENGINEER, in writing at the time of submission, of deviations in
submittals from the requirements of the Contract Documents. The
CONTRACTOR's responsibility for deviations in submittals from the
'
requirements of the Contract Documents is not relieved by the
ENGINEER's review of submittals, unless the ENGINEER gives written
acceptance of specific deviations.
E. Begin no work, which requires submittals until return of submittals with the
ENGINEER's stamp and initials or signature indicating the submittal has
been reviewed.
01340 -Submittal of Shop Drawings.doc
01340-2
r F9Engineering%Capital Pro)ects19611-CR 512 Wideningt9611 CR 512 PHASE IV1Contract Documents101340 - Submittal of Shop Drawings.doc
W
01340 - Submittal of Shop Drawings.doc
A. Submit to:
Indian River County
Michael D. Nixon, P.E.
.. Engineering Division
1801 27th Street
Vero Beach, FL 32960
r
B. A letter of transmittal shall accompany each submittal. If data for more
than one Section of the Specifications is submitted, a separate transmittal
+■ letter shall accompany the data submitted for each Section.
C. At the beginning of each letter of transmittal, provide a reference heading
r indicating the following:
1. OWNER'S Name
2. Project Name
3. Contract Number
4. Transmittal Number
5. Section Number
r
D. All submittals shall have a title block with complete identifying information
satisfactory to the ENGINEER. The following is a sample Submittal Form
that the CONTRACTOR may use:
[The remainder of this page has been left blank intentionally]
W
as
W
W
01340 - Submittal of Shop Drawings.doc
01340-3
FAEngineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE IV\Contract Documents\01340 - Submittal of Shop Drawings.doc
F
77
W
mij
r
so
W
r
0
M
r
W
an
01340 - Submittal of Shop Drawinas.doc
01340 - Submittal of Shop Drawings.doc
01340-4
r F:\Engineering\Capital Projects19611-CR 512 Wdening19611 CR 512 PHASE MContract Documents\01340 - Submittal of Shop Drawmgs.doc
..r
CONTRACTOR SUBMITTALS
SUBMITTAL NO.
Contractor:
Date Sent to County
No. Copies Sent to County
❑ Original Submittal ❑ Re -Submittal
❑ Shop Drawing ❑
Cut Sheet ❑ Other
Description:
Sub -Contractor:
Remarks:
***********************************************************
Reviewing Agency: (As checked below)
Date Received Date Returned No. Copies Ret'd
❑ I R C Engineering Div.
❑ I R C Utilities Services
Remarks:
* * * * * * * * * * * * * * * * * * * *
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
IRC Engineering Division
Date Rec'd from Contractor
Michael D. Nixon, P.E.
Date Ret'd to Contractor
1801 27th Street
No. Copies Ret'd
Vero Beach, FI. 32960
Remarks:
Distribution of Copies:
IRC Engineering Division
Office File
Field Office File
01340 - Submittal of Shop Drawings.doc
01340-4
r F:\Engineering\Capital Projects19611-CR 512 Wdening19611 CR 512 PHASE MContract Documents\01340 - Submittal of Shop Drawmgs.doc
..r
•
01340 - Submittal of Shop Dmwings.doc
01340-5
_ F:\EngineerinMCapital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents101340 -Submittal of Shop Drawings.doc
01340 - Submittal of Shop Drawings.doc
E. All submittals shall bear the stamp of approval and signature of
CONTRACTOR as evidence that they have been reviewed by
CONTRACTOR. Submittals without this stamp of approval will not be
reviewed by the ENGINEER and will be returned to CONTRACTOR.
F. Assign a number to each submittal starting with No. 1 and thence
numbered consecutively. Identify resubmittals by the original submittal
number followed by the suffix "A" for the first resubmittal, the suffix "B" for
the second resubmittal, etc.
G. Initially submit to ENGINEER a minimum of six (6) copies of all submittals
that are on 11 -inch by 17 -inch or smaller sheets (no less than 8 1/2 -inch x
11 -inch), and one unfolded sepia and 2 prints made from that sepia for all
submittals on sheets larger than 11 -inch by 17 -inch.
H. After ENGINEER completes his review, Shop Drawings will be marked
with one of the following notations:
f.
1. Approved
2. Approved as Corrected
3. Approved as Corrected - Resubmit
•
4. Revise and Resubmit
5. Not Approved
I. If a submittal is acceptable, it will be marked "Approved" or "Approved as
Corrected". Three (3) prints or copies of the submittal will be returned to
CONTRACTOR.
J. Upon return of a submittal marked "Approved" or "Approved as
Corrected", CONTRACTOR may order, ship or fabricate the materials
included on the submittal, provided it is in accordance with the corrections
r
indicated.
K. If a Shop Drawing marked "Approved as Corrected" has extensive
"
corrections or corrections affecting other drawings or Work, ENGINEER
may require that CONTRACTOR make the corrections indicated thereon
and resubmit the Shop Drawings for record purposes. Such drawings will
`
have the notation, "Approved as Corrected - Resubmit."
L. If a submittal is unacceptable, three (3) copies will be returned to
•
CONTRACTOR with one of the following notations:
1. 'Revise and Resubmit'
2. "Not Approved"
•
01340 - Submittal of Shop Dmwings.doc
01340-5
_ F:\EngineerinMCapital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents101340 -Submittal of Shop Drawings.doc
01340 - Submittal of Shop Drawings.doc
M. Upon return of a submittal marked "Revise and Resubmit", make the
corrections indicated and repeat the initial approval procedure. The "Not
r Approved" notation is used to indicate material or equipment that is not
acceptable. Upon return of a submittal so marked, repeat the initial
r approval procedure utilizing acceptable_ material or equipment.
N. Any related Work performed or equipment installed without an "Approved"
or "Approved as Corrected" Shop Drawing will be at the sole responsibility
of the CONTRACTOR.
r O. Submit Sop Drawings well in advance of the need for'the material or
equipment for construction and with ample allowance for the time required
to make delivery of material or equipment after data covering such is
r approved. CONTRACTOR shall assume the risk for all materials or
equipment which is fabricated or delivered prior to the approval of Shop
Drawings. Materials or equipment will not be included in periodic progress
r., payments until approval thereof has been obtained in the specified
manner.
r P. ENGINEER will review and process all submittals promptly, but a
reasonable time should be allowed for this, for the Shop Drawings being
revised and resubmitted, and for time required to return the approved
r Shop Drawings to CONTRACTOR.
Q. Furnish required submittals with complete information and accuracy in
MP order to achieve required approval of an item within three submittals. All _
costs to ENGINEER involved with subsequent submittals of Shop
Drawings, Samples or other items requiring approval, will be back -charged
• to CONTRACTOR in accordance with the General Conditions and the
Supplementary Conditions. If the CONTRACTOR requests a substitution
for a previously approved item, all of ENGINEER'S costs in the reviewing
and approval of the substitution will be back -charged to CONTRACTOR
unless the need for such substitution is beyond the control of
CONTRACTOR.
r
+ + END OF SECTION + +
UP
W
a
01340 - Submittal of Shop Drawings.doc
01340-6
FAEngineeringZapitaI Projects19611-CR 512 Widening19611 CR 512 PHASE MContract Documenti;V340 -Submittal of Shop Drawings. doe
r
J
M
SECTION 01520
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
1.1 SCOPE
A. Provide all construction equipment and -facilities and temporary controls
required to satisfactorily complete the work represented on the Drawings
and described in the Specifications.
1.2 RESPONSIBILITY
r A. All construction facilities and temporary controls remain the property of the
Contractor establishing them and shall be maintained in a safe and useful
condition until removed from the construction site.
r
B. All false work, scaffolding, ladders, hoistways, braces, pumps, roadways,
sheeting, forms, barricades, drains, flumes, and the like, any of which may
be needed in construction of any part of the work and which are not herein
described or specified in detail, must be furnished, maintained and
removed by the CONTRACTOR, who is responsible for the safety and
efficiency of such work and for any damage that may result from their
failure or from their improper construction, maintenance or operation.
C. In accepting the Contract, the CONTRACTOR assumes full responsibility
for the sufficiency and safety of all hoists, cranes, temporary structures or
work and for any damage which may result from their failure or their
improper construction, maintenance or operation and will indemnify and
save harmless the OWNER and ENGINEER from all claims, suits or
actions and damages or costs of every description arising by reason of
failure to comply with the above provision.
1.3 TEMPORARY UTILITIES AND SERVICES
r
A. TEMPORARY WATER
1. Provide a temporary water service as required for all construction
purposes and pay for all water used.
2. Furnish potable drinking water in suitable dispensers and with cups
for use of all employees at the job.
3. Provide all temporary piping, hoses, etc., required to transport
water to the point of usage by all trades.
4. When temporary water service is no longer required, remove all
temporary water lines.
01520-1
FAEngineering\Capital Projects\9611-CR 512 Widening0611 CR 512 PHASE MContract Documents101520 -Construction
go Facilities.doc
r
"' SECTION 01520
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
r B. TEMPORARY SANITARY FACILITIES
1. Provide temporary toilet facilities separate from the job office.
Maintain these during the entire .period of construction under this
Contract for the use of all construction personnel on the job.
Provide enough chemical toilets to conveniently serve the needs of
., all personnel. Properly seclude toilet facilities from public
observation.
2. Chemical toilets and their maintenance shall meet the requirements
r of State and local health regulations and ordinances. Immediately
correct any facilities or maintenance methods failing to meet these
requirements. Upon completion of work, remove the facilities from
w the premises.
1.4 SECURITY
Full time watchmen will not be specifically, required as a part of the Contract, but
the CONTRACTOR shall provide inspection of work area daily and shall take
as whatever measures are necessary to protect the safety of the public, workmen,
and materials, and provide for the security of the site, both day and night.
W 1.5 TEMPORARY CONTROLS
Take all necessary precautions to control dust and mud associated with the work
of this Contract. In dry weather, spray dusty areas daily with water in order to
control dust. Take necessary steps to prevent the tracking of mud onto adjacent
streets and highways.
1.6 REMOVAL OF TEMPORARY CONSTRUCTION FACILITIES
Remove the various temporary facilities, services, and controls and legally
dispose of them as soon as the work is complete. The areas of the site used for
temporary facilities shall be properly reconditioned and restored to a condition
acceptable to the OWNER.
+ + END OF SECTION + +
0
01520-2
FAEngineering\Capital Projects\9611-CR 512 Widening\9617 CR 512 PHASE IV\Contract Documents\01520 -Construction
40 Facilities.doc
aw
so
1.1 GENERAL
SECTION 01541
PROTECTION OF THE WORK AND PROPERTY
• A. CONTRACTOR shall be responsible for taking all precautions, providing all
programs, and taking all actions necessary to protect the Work and all public and
private property and facilities from damage as specified in the General Condi-
tions and herein.
B. In
order to prevent damage, injury or loss, CONTRACTOR'S actions shall
include, but not be limited to, the following:
1.
Store apparatus, materials, supplies, and equipment in an orderly, safe
manner that will not unduly interfere with the progress of the Work or the
Work of any other Contractor or utility service company.
2.
Provide suitable storage facilities for all materials, which are subject to injury
by exposure to weather, theft, breakage, or otherwise.
` 3.
Place upon the Work or any part thereof, only such loads as are consistent
with the safety of that portion of the Work.
4.
Clean up frequently all refuse, rubbish, scrap materials, and debris caused
`
by construction operations, so that at all times, the site of the Work presents
a safe, orderly, and workmanlike appearance.
5.
Provide barricades and guard rails around openings, for scaffolding, for
`
temporary stairs and ramps, around excavations, elevated walkways and
other hazardous areas.
C. Except after written consent from proper parties, do not enter or occupy
privately -owned land with men, tools, materials or equipment, except on
easements provided herein.
D. Assume full responsibility for the preservation of all public and private property or
facility on or adjacent to the site. If any direct or indirect damage is done by or
on account of any act, omission, neglect or misconduct in the execution of the
Work by the CONTRACTOR, it shall be restored by the CONTRACTOR, at its
�. expense, to a condition equal to or better than that existing before the damage
was done.
M 1.2 BARRICADES AND WARNING SIGNALS
Where Work is performed on or adjacent to any roadway, right-of-way, or public
r place, provide barricades, fences, lights, warning signs, danger signals, and
watchmen, and take other precautionary measures for the protection of persons or
property and of the Work. Paint barricades so they are visible at night. From sunset
to sunrise, furnish and maintain at least one light at each barricade. Erect sufficient
barricades to keep vehicles from being driven on or into Work under construction.
Furnish watchmen in sufficient numbers to protect the Work. CONTRACTOR's
r responsibility for the maintenance of barricades, signs, lights, and for providing
watchmen shall continue until OWNER accepts the Project.
01541-1 F1Engineering\Capital Projects\9611-CR 512 WdeningV9611
+ CR 512 PHASE IV\Contract Documents\01541 - Protection of Property.doc
SECTION 01541
PROTECTION OF THE WORK AND PROPERTY
• 1.3 TREE AND PLANT PROTECTION
A. Protect existing trees, shrubs and plants on or adjacent to the site that are shown
• or designated to remain in place against unnecessary cutting, breaking or
skinning of trunk, branches, bark or roots.
• B. Do not store or park materials or equipment within the drip line.
C. Install temporary fences or barricades to protect trees and plants in areas subject
to traffic.
D. Fires shall not be permitted under or adjacent to trees and plants
r
E. Within the limits of the Work, water trees and plants that are to remain, in order
F9EngineedngZapital Projects19611-CR512 Widening49611
to maintain their health during construction operations.
PHASE
IVtContract DocumentsW1541
-Protection of Property.doc
F. Cover all exposed roots with burlap and keep it continuously wet. Cover all
exposed roots with earth as soon as possible. Protect root systems from
•
mechanical damage and damage by erosion, flooding, run-off or noxious
materials in solution.
•
G. If branches or trunks are damaged, prune branches immediately and protect the
cut or damaged areas with emulsified asphalt compounded specifically for
horticultural use.
•
H. Remove all damaged trees and plants that die or suffer permanent injury and
replace them with a specimen of equal or better quality.
r,
I. Coordinate Work in this Section with requirements of other sections herein.
•
1.4 PROTECTION OF IRRIGATION
The CONTRACTOR shall be responsible for maintaining in good condition all
•
irrigation systems within the easements, which could be damaged by
construction activities. The CONTRACTOR shall repair any irrigation systems
.,
damaged by construction activities within two (2) days. Irrigation systems
partially within the right-of-way of Kings Highway and all intersecting side streets
within project limits may be cut off and capped or connected to same system to
•
maintain functionality. The CONTRACTOR shall be responsible for maintaining
the functionality of the remaining portion of the system if it should fall outside of
the right-of-way.
•
r✓
1.5 PROTECTION OF EXISTING STRUCTURES
01541-2
F9EngineedngZapital Projects19611-CR512 Widening49611
CR 512
PHASE
IVtContract DocumentsW1541
-Protection of Property.doc
r
SECTION 01541
PROTECTION OF THE WORK AND PROPERTY
01541-3
A. Underground Structures:
r CR
1. Underground structures are defined to include, but not be limited to, all
..
sewer, water, gas, and other piping, and manholes, chambers, electrical
Documents\01541
conduits, tunnels and other existing subsurface work located within or adja-
of Property.doc
cent to the limits of the Work.
2. All underground structures known to ENGINEER except service connections
for water, sewer, electric, and telephone are shown. This information is
shown for the assistance of CONTRACTOR in accordance with the best
"
information available, but is not guaranteed to be correct or complete. The
existing utilities shown on the Contract Drawings are located according to
the information available to the ENGINEER at the time jhe Drawings were
prepared and have not been independently verified by the OWNER or the
ENGINEER. Guarantee is not made that all existing underground utilities
are shown or that the locations of those shown are accurate. The locations
shown are for bidding purposes only. Finding the actual location of any
existing utilities is the CONTRACTOR's responsibility and shall be done
before it commences any work in the vicinity. Furthermore, the
CONTRACTOR shall be fully responsible for any and all damages, which
might be occasioned by the CONTRACTOR's failure to exactly locate and
preserve any and all underground utilities. The OWNER or ENGINEER will
assume no liability for any damages sustained or costs incurred because of
the CONTRACTOR's operations in the vicinity of existing utilities or
structures, nor for temporary bracing and shoring of same. If it is necessary
to shore, brace, or swing a utility, contact the utility company or department
affected and obtain their permission regarding the method to use for such
work.
i
3. Contact the various utility companies which may have buried or aerial
utilities within or near the construction area before commencing work.
Provide 48 hours minimum notice to all utility companies prior to beginning
construction.
4. Schedule and execute all work involving existing utilities in order to minimize
r
necessary interruption of services. Whenever such interruption is necessary
for completion of the work, notify the ENGINEER and the appropriate utility
at least 48 hours in advance. Perform all work to repair/restore utility
..
service to the satisfaction of the appropriate utility. Include all costs related
to service maintenance, interruption, and restoration in the appropriate line
item in the Contract.
..
5. Where it is necessary to temporarily interrupt house or business services,
the CONTRACTOR shall notify the owner or occupant, both before the
interruption (24-hour minimum), and again immediately before service is
resumed. Before disconnecting and pipes or cables, the CONTRACTOR
shall obtain permission from their owner, or shall make suitable
arrangement for their disconnection by their owner.
•
6. Explore ahead of trenching and excavation work and uncover all obstructing
underground structures sufficiently to determine their location, to prevent
01541-3
F\Englneering\Capital Projects\9611-CR 512 Widening19611
r CR
512
PHASE
MContract
Documents\01541
- Protection
of Property.doc
n
0
r
M
SECTION 01541
PROTECTION OF THE WORK AND PROPERTY
damage to them and to prevent interruption of the services which such
structures provide. If CONTRACTOR damages an underground structure,
restore it to original condition at CONTRACTOR's expense.
7. Necessary changes in the location of the Work may be made by
ENGINEER, to avoid unanticipated underground structures.
8. If permanent relocation of an underground structure or other subsurface
facility is required and is not otherwise provided for in the Contract
Documents, ENGINEER will direct CONTRACTOR in writing to perform the
Work, which shall be paid for under the provisions of Article 11 of the
General Conditions.
B. Surface Structures:
Surface structures are defined as structures or facilities above the ground
surface. Included with such structures are their foundations and any
extension below the surface. Surface structures include, but are not limited
to, buildings, tanks, walls, bridges, roads, dams, channels, open drainage,
piping, poles, wires, posts, signs, markers, curbs, walks and all other facil-
ities that are visible above the ground surface.
M
M
1.6 DAMAGE TO EXISTING STRUCTURES AND UTILITIES
01541-4 F\Engineering\Capital Projects\9611-CR 512 Widening\9611
CR 512 PHASE MContract Documents\01541 - Protection of Property.doc
C. Protection of Underground and Surface Structures:
1. Sustain in their places and protect from direct or indirect injury, all
underground and surface structures located within or adjacent to the limits
of the Work. Such sustaining and supporting shall be done carefully, and as
required by the party owning or controlling such structure. Before
proceeding with the work of sustaining and supporting such structure, satisfy
the ENGINEER that the methods and procedures to be used have been
approved by the party owning same.
AV
2. Assume all risks attending the presence or proximity of all underground and -
surface structures within or adjacent to the limits of the Work.
CONTRACTOR shall be responsible for all damage and expense for direct
or indirect injury caused by its Work to any structure. CONTRACTOR shall
repair immediately all damage caused by his work, to the satisfaction of the
OWNER of the damaged structure.
W,
D. All other existing surface facilities, including but not limited to, guard rails, posts,
guard cables, signs, poles, markers, and curbs which are temporarily removed to
facilitate installation of the Work shall be replaced and restored to their original
condition at CONTRACTOR'S expense.
M
M
1.6 DAMAGE TO EXISTING STRUCTURES AND UTILITIES
01541-4 F\Engineering\Capital Projects\9611-CR 512 Widening\9611
CR 512 PHASE MContract Documents\01541 - Protection of Property.doc
r
SECTION 01541
PROTECTION OF THE WORK AND PROPERTY
.. A. The CONTRACTOR shall be responsible for and make good all damage to
pavement beyond the limits of this Contract, buildings, telephone or other cables,
water pipes, sanitary pipes, or other structures which may e encountered,
.r whether or not shown on the Drawings.
B. Information shown on the Drawings as to the location of existing utilities has
been prepared from the most reliable data available to the Engineer. This
information is not guaranteed, however, and it shall be this CONTRACTOR's
responsibility to determine the location, character and depth of any existing
utilities. He shall assist the utility companies, by every means possible to
determine said locations. Extreme caution shall be exercised to eliminate any
possibility of any damage to utilities resulting from his activities.
r
1.7 ADJUSTMENTS OF UTILITY CASTINGS, COVERS AND BOXES
A. All existing utility castings, including valve boxes, junction boxes, manholes, pull
boxes, inlets and similar structures in the areas of construction that are to remain
in service shall be adjusted by the CONTRACTOR to bring them flush with the
surface of the finished work.
B. The CONTRACTOR shall coordinate the utilities to ensure proper construction
` sequencing. CONTRACTOR shall make available survey reference markers to
the various utility companies.
•
ON
M
-1
+ + END OF SECTION + +
M
•
M
in
01541-5
F?Engineenng\Capital Projects0611-GR 512Widening\9611
T
CR 512
PHASE
IV\Contract
DocumentsV541
-Protection
of Property.doc
;J
GENERAL
SECTION 01550
ACCESS ROADS, PARKING AREAS
AND USE OF PUBLIC STREETS
A. Provide all temporary construction roads, walks and parking areas required
+. during construction and for use of emergency vehicles. Design and maintain
temporary roads and parking areas so they are fully usable in all weather
conditions.
r
B. Prevent interference with traffic and the OWNER's operations on existing roads.
Indemnify and save harmless the OWNER from any expenses caused by
CONTRACTOR's operations over these roads.
C. Roadways damaged by CONTRACTOR shall be restored to their original
condition by the CONTRACTOR subject to approval of the OWNER or
ENGINEER.
D. Remove temporary roads, walks and parking areas prior to final acceptance and
return the ground to its original condition, unless otherwise required by the
Contract Documents.
1.2 USE OF PUBLIC STREETS
The use of public streets and alleys shall be such as to provide a minimum of
inconvenience to the public and to other traffic. Any earth or other excavated
material spilled from trucks shall be removed immediately by the CONTRACTOR
and the streets cleaned to the satisfaction of the Owner.
r
1.3 USE OF PUBLIC STREETS FOR HAUL ROADS
A. Prior to construction, the CONTRACTOR shall designate all proposed haul
roads to be used during the life of the project. Any earth or other materials
spilled from trucks shall be removed by the CONTRACTOR and streets
cleaned to the satisfaction of the Owner. He further shall be responsible for
repairs to any damages caused by his operations, prior to final payment.
01550 Access Roads
01550-1
F:\Engineering\CapitalProjects\9611-CR512W-idening\9611 CR 512 PHASE MContract Documents\01550 - Access Roads.doc
r=
M
SECTION 01550
ACCESS ROADS, PARKING AREAS
r AND USE OF PUBLIC STREETS
B. All trucks carrying earth shall be covered while moving with an appropriate
tarpaulin. Should trucks hauling earth fail to cover their loads, the
,., CONTRACTOR will be given two (2) written warnings, after which the
CONTRACTOR shall pay a fine of $50 per uncovered truck to the Owner
when invoked by the Owner to Owner's Engineer. All cleanup shall be the
responsibility of the CONTRACTOR.
C. All trucks/moving equipment shall have backup warning horns in proper
r working order while on the job site.
r
++ END OF SECTION ++
W
M
W
M
r7l
01550 Access Roads
01550-2
F:\Enginee6ng\Cap1ta1 Projects\9611-CR 512 Widening\9611 CR 512 PHASE IV\Contrac[ Documents\01550 - Access Roads.doc
M
W
M
r SECTION 01610
TRANSPORTATION AND HANDLING OF MATERIALS AND EQUIPMENT
r
1.1 GENERAL
•
A. Make all arrangements for transportation, delivery and handling of equipment
and materials required for prosecution and completion of the Work.
r
B. Shipments of materials to CONTRACTOR or Subcontractors shall be delivered
to the site only during regular working hours. Shipments shall be addressed and
r consigned to the proper party giving name of Project, street number and city.
Shipments shall not be delivered to OWNER except where otherwise directed.
r C. If necessary to move stored materials and equipment during construction,
CONTRACTOR shall move or cause to be moved materials and equipment
without any additional compensation.
1.2 DELIVERY
• A. Arrange deliveries of products in accord with construction schedules and in
ample time to facilitate inspection prior to installation.
• B. Coordinate deliveries to avoid conflict with Work and conditions at site and to
accommodate the following:
1. Work of other contractors, or OWNER.
• 2. Limitations of storage space.
3. Availability of equipment and personnel for handling products.
4. OWNER'S use of premises.
r
C. Do not have products delivered to project site until related Shop Drawings have
been approved by the ENGINEER.
r
D. Do not have products delivered to site until required storage facilities have been
r
provided.
E. Have products delivered to site in manufacturer's original, unopened, labeled
• containers. Keep ENGINEER informed of delivery of all equipment to be
incorporated in the Work.
01610-1
F:\Engineering\Capital Projects\9611-CR 512 Widening\9611 CR 512 PHASE MContract Documents\01610 - Transportation and
r Handling of Materials and Equipment.doc
VW
W
r SECTION 01610
TRANSPORTATION AND HANDLING OF MATERIALS AND EQUIPMENT
0
F. Partial deliveries of component parts of equipment shall be clearly marked to
I, identify the equipment, to permit easy accumulation of parts, and to facilitate
assembly.
r G. Immediately on delivery, inspect shipment to assure:
1. Product complies with requirements of Contract Documents and reviewed
submittals.
.r 2. Quantities are correct.
3. Containers and packages are intact, labels are legible.
4. Products are properly protected and undamaged.
i
1.3 PRODUCT HANDLING
•r A. Provide equipment and personnel necessary to handle products, including
those provided by OWNER, by methods to prevent soiling or damage to
products or packaging.
r
B. Provide additional protection during handling as necessary to prevent scraping,
marring or otherwise damaging products or surrounding surfaces.
C. Handle products by methods to prevent bending or overstressing.
D. Lift heavy components only at designated lifting points.
E. Materials and equipment shall at all times be handled in a safe manner and as
recommended by manufacturer or supplier so that no damage will occur to
them. Do not drop, roll or skid products off delivery vehicles. Hand carry or use
r
suitable materials handling equipment.
+ + END OF SECTION + +
r
J
01610-2
FAEngineeringSCapital Projects19611-CR 512 Widening\9611 CR 512 PHASE I\AContract Documents\01610 - Transportation and
i Handling of Materials and Equipment.doc
W
M SECTION 01611
_ STORAGE OF MATERIAL AND EQUIPMENT
1.1 GENERAL
A. Store and protect materials and equipment in accordance with manufacturer's
recommendations and requirements of Specifications.
B. Make all arrangements and provisions necessary for the storage of materials
and equipment. Place all excavated materials, construction equipment, and
materials and equipment to be incorporated into the Work, 'so as not to injure
any part of the Work or existing facilities, and so that free access can be had at
all times to all parts of the Work and to all public utility installations in the vicinity
,. of the Work. Keep materials and equipment neatly and compactly stored in
locations that will cause a minimum of inconvenience to other contractors,
public travel, adjoining owners, tenants and occupants. Arrange storage in a
• manner to provide easy access for inspection.
C. Areas available on the construction site for storage of material and equipment
.. shall be as shown or approved by the ENGINEER.
D. Store materials and equipment which are to become the property of the
r• OWNER to facilitate their inspection and insure preservation of the quality and
fitness of the Work, including proper protection against damage by extreme
temperatures and moisture.
E. Do not use lawns, grass plots or other private property for storage purposes
without written permission of the OWNER or other person in possession or
control of such premises.
F. CONTRACTOR shall be fully responsible for loss or damage to stored materials
• and equipment.
G. Do not open manufacturers containers until time of installation unless
recommended by the manufacturer or otherwise specified.
H. When appropriate store materials on wood blocking so there is no contact with
the ground.
+ + END OF SECTION + +
n
01611-1 01611—Storage of Material
F:1Engineering\Capital Projects19611-CR512Widening19611 CR512 PHASE NAContract Documents\01611 -Storage of Materials.doc
ft
r
SECTION 01630
SUBSTITUTIONS
1.1 GENERAL
• A. Requests for review of a substitution shall conform to the requirements of
Article 6.05, "Substitutes and Or -Equals," of the General Conditions, and shall
contain complete data substantiating compliance of the proposed substitution
with the Contract Documents.
1.2 CONTRACTOR'S OPTIONS
r
A. For materials or equipment (hereinafter products) specified only by reference
standard, select product meeting that standard by any manufacturer, fabricator,
r supplier or distributor (hereinafter manufacturer). To the maximum extent
possible, provide products of the same generic kind from a single source.
r B. For products specified by naming several products or manufacturers, select any
one of the products or manufacturers named which complies with Specifications.
C. For products specified by naming one or more products or manufacturers and
stating "or equivalent," submit a request for a substitution for any product or
manufacturer which is not specifically named.
D. For products specified by naming only one product or manufacturer and followed
by words indicating that no substitution is permitted, there is no option and no
r
substitution will be allowed.
E. Where more than one choice is available as a CONTRACTOR's option, select
product which is compatible with other products already selected or specified.
1.3 SUBSTITUTIONS
A. During a period of 15 days after date of commencement of Contract Time,
ENGINEER will consider written requests from CONTRACTOR for substitution of
products or manufacturers, and construction methods (if specified).
1. After end of specified period, requests will be considered only in case of
unavailability of product or other conditions beyond control of
CONTRACTOR.
B. Submit 5 copies of Request for Substitution. Submit a separate request for each
substitution. In addition to requirements set forth in Article 6.7 of General Condi-
tions, include in the request the following:
1. For products or manufacturers:
a. Product identification, including manufacturer's name and address.
b. Manufacturer's literature with product description, performance and
test data, and reference standards.
r
01630-1
01630 Substitutions
FAEngineering\Capital
Projects\9611-CR
512 Widening\9611
CR 512 PHASE
IV\Contract Documents\01630 - Substitutions.doc
r
c. Samples, if appropriate.
d. Name and address of similar projects on which product was used,
and date of installation.
2. For construction methods (if specified):
` a. Detailed description of proposed method.
b. Drawings illustrating method.
3. Such other data as the ENGINEER may require to establish that the
proposed substitution is equal to the product, manufacturer or method
specified.
C. In making Request for Substitution, CONTRACTOR represents that:
1. CONTRACTOR has investigated proposed substitution, and determined
do that it is equal to or superior in all respects to the product, manufacturer
or method specified.
2. CONTRACTOR will provide the same or better guarantees or
warranties for proposed substitution as for product, manufacturer, or
method specified.
3. CONTRACTOR waives all claims for additional costs or extension of
.. time related to a proposed substitution that subsequently may become
apparent.
.. D. A proposed substitution will not be accepted if:
1. Acceptance will require changes in the design concept or a substantial
revision of the Contract Documents.
2. It will delay completion of the Work, or the work of other contractors.
3. It is indicated or implied on a Shop Drawing and is not accompanied by
a formal Request for Substitution from CONTRACTOR.
E. If the ENGINEER determines that a proposed substitute is not equal to that
specified, furnish the product, manufacturer, or method specified at no additional
cost to OWNER.
F. Approval of a substitution will not relieve CONTRACTOR from the requirement
for submission of Shop Drawings as set forth in the Contract Documents.
G. The procedure for review by Engineer will include the following:
1. Requests for review of substitute items of material and equipment will
not be accepted by Engineer from anyone other than CONTRACTOR.
2. Upon receipt of an application for review of a substitution, Engineer will
determine whether the review will be more extensive than a normal shop
drawing review for the specified item.
3. If the substitution will not require a more extensive review, Engineer will
proceed with the review without additional cost to CONTRACTOR.
M
E7
M
01630-2
01630 Substitutions
FAEngineering\Capital
Projects19611-CR
512 Widening\9611
CR 512 PHASE
MContract Documents\01630 - Substitutions.doc
E7
M
4. If the substitution requires a more extensive review, Engineer will
proceed with the review only after CONTRACTOR has agreed to
reimburse Owner for the review cost.
5. Engineer may require CONTRACTOR to furnish at CONTRACTOR's
expense additional data about the proposed substitute.
H. Any redesign of structural members shall be performed by, and the plans signed
and sealed by, a Professional Engineer registered in the State of Florida. The
redesign shall be at the CONTRACTOR's expense. Any redesign will require an
extensive review by the Engineer. The CONTRACTOR must agree to reimburse
the Owner for the review cost prior to the Owner's Engineer proceeding with the
design review. The ENGINEER's hourly rate for review is $125 per hour. The
ENGINEER's estimated cost of review shall be provided to the CONTRACTOR
prior to proceeding with the review to allow the CONTRACTOR the opportunity to
rescind the request.
1. Engineer will be allowed a reasonable time within which to evaluate each
proposed substitution. Engineer will be the sole judge of acceptability and shall
have the right to deny use of any proposed substitution. The CONTRACTOR
shall not order, install, or utilize any substitution without either an executed
Change Order or Engineer's notation on the reviewed shop drawing. Owner may
.. require CONTRACTOR to furnish at CONTRACTOR's expense a special
manufacturer's performance guarantee(s) or other surety with respect to any
substitute and an indemnification by the CONTRACTOR. ENGINEER will record
�• time required by Engineer and Engineer's consultants in evaluating substitutions
proposed by CONTRACTOR and in making changes in the Contract Documents
occasioned thereby. Whether or not a proposed substitute is sued,
+� CONTRACTOR shall reimburse Owner for the charges of Engineer and
Engineer's consultants for evaluating each proposed substitute
• J. Substitute materials or equipment may be proposed for acceptance in
accordance with this Section. In the event that substitute materials or equipment
are used and are less costly than the originally specified material or equipment,
than the net difference in cost shall benefit the Owner and CONTRACTOR in
equal proportions. This cost difference shall not be reduced by any failure of the
CONTRACTOR to base his bid on the named materials or equipment.
+ + END OF SECTION + +
M
•
01630-3
01630 Substitutions
F:\Engineering\Capital
Projects\9611-CR
512
Widening\9611
CR 512
PHASE
MContract
Documents\01630 - Substitutions.doc
r
r
1.1 SCOPE
r
•
SECTION 01710
SITE CLEANUP AND RESTORATION
Furnish all labor, equipment, appliances, and materials required or necessary to
clean up and restore the site after the construction is completed.
1.2 REQUIREMENTS
A. During the progress of the project, keep the work and, the adjacent areas
affected thereby in a neat and orderly condition. Remove all rubbish,
surplus materials, and unused construction equipment. Repair all damage
so that the public and property owners will be inconvenienced as little as
possible.
B. Provide onsite containers for the collection of waste materials, debris, and
rubbish and empty such containers in a legal manner when they become
full.
C. Where material or debris has been deposited in watercourses, ditches,
gutters, drains, or catch -basins as a result of the CONTRACTOR's
operations, such material or debris shall be entirely removed and
satisfactorily disposed of during the progress of the work, and the ditches,
channels, drains, etc., shall be kept clean and open at all times.
D. Before the completion of the project, unless otherwise especially directed
or permitted in writing:
1. Tear down and remove all temporary buildings and structures;
2. Remove all temporary works, tools, and machinery, or other
construction equipment furnished;
3. Remove all rubbish from any grounds occupied; and
4. Leave the roads, all parts of the premises, and adjacent property
affected by construction operations, in a neat and satisfactory
,,. condition.
E. Restore or replace any public or private property damaged by construction
r. work, equipment, or employees, to a condition at least equal to that
existing immediately prior to the beginning of the operations. To this end,
the CONTRACTOR shall restore all highway, roadside, and landscaping
• work within any right-of-way, platted or prescriptive. Acceptable materials,
equipment,and methods shall be used for such restoration.
• F. Thoroughly clean all materials and equipment installed and on completion
of the work, deliver the facilities undamaged and in fresh and new -
appearing condition.
01710 Site Cleanup
01710-1
F \Engineering\Capital Projects\9611-CR 512 Widenin9\9611 CR 512 PHASE MContract Documents\01710 - Site Cleanup.doc
r G. It is the intent of the Specifications to place the responsibility on the
CONTRACTOR to restore to their original condition all items disturbed,
destroyed, or damaged during construction. Particular attention will be
r placed on restoration of canals to equal or better condition than prior to
construction.
H. When finished surfaces require cleaning with cleaning materials, use only
those cleaning materials which will not create hazards to health or
property and which will not damage the surfaces. Use cleaning materials
r only on those surfaces recommended by the manufacturer. Follow the
manufacturer's directions and recommendations at all times.
r I. Keep the amount of dust produced during construction activities to a
minimum. At CONTRACTOR's expense, spray water or other dust control
agents over the areas, which are producing the dust. Schedule
construction operations so that dust and other contaminants will not fall on
wet or newly coated surfaces.
IN 1.3 SITE CLEANUP AND RESTORATION
Prior to final completion, the OWNER, ENGINEER, INDIAN RIVER FARMS
WATER CONTROL DISTRICT, and CONTRACTOR shall review the site with
regards to site cleanup and restoration. Clean and/or restore all items
r
determined to be unsatisfactory by the OWNER or ENGINEER, at no additional
expense.
+ + END OF SECTION + +
r
W
r
r
M
01710 Site Cleanup
M 01710-2
FAEngineering\Capital Projects19611-CR 512 Widening\9611 CR 512 PHASE IV\Contract Documents\01710-Site Cleanup. doc
r
r
r
0
w
r
r
r
r
0
r
r
M
r
r
DIVISION 2
TECHNICAL PROVISIONS
m
m DIVISION 2 TECHNICAL PROVISIONS
r Section No. Title
#.
ROADWAY
1
STANDARD SPECIFICATIONS
101
MOBILIZATION
..
102
MAINTENANCE OF TRAFFIC
104
EROSION AND WATER POLLUTION CONTROL
109
FIELD OFFICE
110
CLEARING AND GRUBBING
120
EXCAVATION AND EMBANKMENT
160
STABILIZING
285
OPTIONAL BASE COURSE
286
TURNOUT CONSTRUCTION
300
PRIME AND TACK COATS
r
327
MILLING EXISTING ASPHALT PAVING
334
SUPERPAVE ASPHALTIC CONCRETE
r
400
CONCRETE STRUCTURES
+r
425
INLETS, MANHOLES AND JUNCTION BOXES
430
PIPE CULVERTS AND STORM SEWERS
520
CONCRETE GUTTER, CURB ELEMENTS & TRAFFIC SEPARATOR
522
CONCRETE SIDEWALK
550
FENCING
yr
570
GRASSING (BY SEEDING)
"'
575
SODDING
F:\Engineering\Capital
Projects\9611-CR 512 Widening\9611 CR 512 PHASE IV1Contmct Documents\DIVISION 2 TECHNICAL PROVISIONS Table of
r•
Contents.doc
580 LANDSCAPE INSTALLATION
630 CONDUIT
• 635 PULL AND JUNCTION BOXES
700 SIGNING AND PAVEMENT MARKING
r
706 RAISED RETRO -REFLECTIVE PAVEMENT MARKERS AND
BITUMINOUS ADHESIVE
r
711 THERMOPLASTIC TRAFFIC STRIPES AND MARKINGS
r 1000 WATER AND SEWER UTILITIES
LANDSCAPING & IRRIGATION (MEDIANS)
See Specifications for Landscape and Irrigation
TRAFFIC SIGNALIZATION
See Signalization Plans CR 512, # SG108.dgn
r
' 1-95 SIDEWALK
r See CR 512 Specifications
�J
r
F:tEngineering\Capital Projects19611-CR 512 Widening\9611 CR 512 PHASE RAContract DommentsVIVISION 2 TECHNICAL PROVISIONS Table of
No Contents.doc
M
so
s
TECHNICAL SPECIFICATIONS
SECTION —1
STANDARD SPECIFICATIONS
A. All work of this Contract shall conform to the applicable technical specifications of Florida
Department of Transportation Standard Specifications for Road and Bridge Construction,
Special Provisions and addenda thereto, except as modified and supplemented
hereinafter. Reference to Article numbers hereinafter apply to the FDOT Standard
.. Specifications, and reference in FDOT Standard Specifications to Department shall be
taken as the Owner or its appointed Representative. Wherever the Specifications,
Supplementals, etc. may refer to the "Owner," "Department," "State of Florida
Department of Transportation," or words relating to offices of State Government, such
words shall be taken as meaning Owner or Indian River County, Florida. Wherever the
word "Owner's Engineer," "District Engineer," "Engineer," "Project Engineer," etc., it shall
be taken to mean the Registered Professional Project Engineer of the firm of Masteller &
Moler, Inc. as an agent of Indian River County, Florida, acting directly or through duly
authorized representatives. Wherever the word Resident Engineer appears, it shall be
taken to mean an authorized representative of the Owner's Engineer on the Project
(Resident Construction Inspector) who will act as an agent for Indian River County,
assigned to observe the progress quantity and quality of the work.
W
SECTION —101
r MOBILIZATION
1.01-1 Description
r
The work specified in this section shall conform to Section 101 of the FDOT Standard
Specifications.
` 1.01-2 Basis of Payment
Work and incidental costs specified as being covered under this Section will be paid for in partial
payments, in accordance with Section 101-25DOT Standard Specifications, for the item of
Mobilization.
UV Payment shall be made under:
Item No. 101-1 Mobilization Partial Payments
r-:
s
r
In
SECTION 102
MAINTENANCE OF TRAFFIC
A. General: Work under this section consists of maintaining traffic within the limits of the
project for the duration of construction in accordance with the U.S. Department of
Transportation's Manual on Uniform Traffic Control Devices (MUTCD) 2003 Edition, FDOT
Index 600 Series and FDOT Standard Specification Section 102. The purpose of the Traffic
r Control Plan, presented in the roadway construction plans, is to depict the concept of
feasible construction sequencing and maintenance of traffic. The Contractor may submit to
the Engineer an alternate plan for review and approval, one week prior to the pre -
construction conference. The Traffic Control Plan indicates typical signing, marking and
barricade locations and types. Additional details are found in the MUTCD, FDOT Index
(600 Series) and Standard Specifications. The Contractor shall install only new TCP signs
and shall be Engineer quality.
B. Quantities: The Contractor is hereby notified that the Engineer's estimate of quantities,
which appears on the summary of quantities sheet, is provided only for the Contractor's
information. The Contractor is to determine the actual quantities and items to be used for
maintenance of traffic.
s C. Off-duty police or sheriff deputies shall be used during various maintenance of traffic
operations including: signalization adjustments and installations and lane closures of
duration greater than 10 minutes.
D. Compensation: All compensation for maintenance of traffic includes: barricades (Type ll),
Barricades (Type III), Temporary Pavement along CR 512 and variable message sign, shall
r be lump sum. This shall include all items and services necessary for the safe maintenance
of traffic within the project limits. This shall include, but not be limited to, flaggers, off-duty
police or sheriff deputy, construction and advisory signing, detours, temporary retaining
r systems, striping, maintenance of pavement, asphaltic concrete curb, temporary barrier
wall, stormwater removal, temporary drainage structures and pipe, pumps, commercial
material for driveway maintenance, flashing arrow boards, high intensity flashing lights,
removable and temporary pavement markings, and temporary reflective pavement markers,
temporary pavement, for maintenance of traffic.
Item No. 102-1 - Maintenance of Traffic — Lump Sum
E. Non -Compliance: Should the Owner or Engineer determine that traffic within the project is
not being maintained in accordance with the approved traffic control plan or presents a
public safety concern, the Contractor shall have until the end of the working day, in which
notification is given, to take action to modify the maintenance of traffic. Should the
Contractor fail to make such modification the Owner shall have the option to fine the
•r Contractor $450 per day until remedied.
W
M
M
No
SECTION 104
r EROSION AND WATER POLLUTION CONTROL
The Contractor shall install erosion and water pollution methods in accordance with FDOT Index
Wo 1003 102, 103 and 104, Standard Specifications Section 104, and all permit requirements. The
Contractor is responsible for meeting appropriate federal, state, and local regulations and water
quality standards, such as turbidity. All disturbed areas will be replanted with approved
1W vegetation cover (either final or temporary) within 30 days of final grading.
A. NPDES Permit: Contractor is responsible for preparing, submitting and obtaining the
r NPDES Permit. Erosion Control Plans included in the construction plans are for suggestive
purposes only and are not considered to be a complete Erosion Control Plan. Contractor is
responsible for any preparing any additional plans/information that will be required in order
to to obtain the NPDES Permit.
B. Pre -construction Conference: At the pre -construction conference the Contractor shall
present, in written form, his plans and schedules for prevention, control, and abatement of
erosion and water pollution.
C. Ditches. Streams and Canals: Staked and floating turbidity barriers shall be installed in all
permanent water courses in a manner so as not to act as a dam. Barriers shall be located
at distances of no greater than 25' downstream from the last point of construction.
D. Silt Fences: Silt fences shall be installed to prevent silt and erosion from leaving the
project limits particularly adjacent to wetlands, roadside ditches or existing bodies of water.
E. Storm Sewer System: The Contractor shall protect the storm sewer system from erosion
and sedimentation during construction. This may include the use of baled hay, silt fences
or any other method approved by the Engineer. Should any constructed item be damaged
r due to erosion or sedimentation, the Contractor shall repair or replace the item with no
additional compensation. All new and existing (where called for) storm sewer pipes shall
be clean and free from silt prior to final acceptance.
r
F. Mowing: Mowing shall be based upon a minimum of one (1) cutting per month for mowing
within right-of-way, including all ditches and side streets within limits of construction.
s
G. Compensation: All payment for the above items shall be made under Item
_ Item No. 104-4 Mowing Per Acre
Item No. 104-10 Baled Hay or Straw Per Each
Item No. 104-13 Silt Fence (Type III) Per Linear Foot
rr
71
W
W
M
to
FIELD OFFICE
SECTION 109
W Item of Payment
Payment shall be made under:
rr
Item No. 109-71 Field Office (Contractor) (Lump Sum)
.a
The Specifications for Field Office (Contractor) shall include furnishing and installing a
Construction Field Office at or near the Project Limits in accordance with these Specifications.
+�
The Contractor shall provide and maintain, in good condition, for the exclusive use of the
Engineer, one or more of the hereinafter described construction field offices at a location or
locations to be approved by the Engineer.
r
The office shall be of weatherproof construction having a floor space of no less than 228 SF,
located on or in the immediate vicinity of the Project. The office shall be provided with sufficient
natural and artificial light and shall be adequately cooled and/or heated. Doors and windows
shall be equipped with adequate locks, and all keys shall be in the possession of the Engineer.
Suitable sanitary conveniences for the use of the Engineer, shall be provided in or adjoining the
field office or offices which shall be maintained clean and in good working condition, and shall
'
be stocked with lavatory and sanitary supplies at all times during the period of the Contract.
The office shall be equipped with tables and chairs for the use of four (4) people and shall have
sufficient drawers for the standard size plans, either attached to the tables or in cabinet form,
one (1) rough plan rack, one (1) supply cabinet, a minimum of five (5) gallons of potable water
maintained by the Contractor, one (1) dual cassette telephone answering machine, one (1) fax
machine, and one (1) fire-resistant (2) drawer legal size file cabinet meeting fire underwriters'
approval for no less than a 1 -hour test. The room also shall be provided with a desk and chair.
Parking spaces for two (2) full-size vehicles shall also be provided within the immediate vicinity
of the office.
The Contractor will provide for the installation of telephone facilities in the field offices.
However, only the minimum monthly service charge and work related toll charges will be paid by
the Contractor.
In lieu of the field office or offices specified above, the Contractor may provide equivalent office
space, equipment and facilities subject to approval of the Engineer.
The field office shall be ready for use later than ten (10) calendar days after the date of mailing
the fully executed Contract and before any other work is started, and shall be maintained by the
r'
Contractor until one (1) month after final acceptance of the Project by the Engineer and Owner,
and then shall be removed.
W Item of Payment
Payment shall be made under:
rr
Item No. 109-71 Field Office (Contractor) (Lump Sum)
.a
771
..
_ SECTION 110
CLEARING AND GRUBBING
A. Payment for Clearing and Grubbing shall include compensation for: the removal and
disposal of asphaltic (existing flexible pavement, excluding existing public roadways which
is paid for under Pay Item 110-4) and existing concrete pavement, concrete, sidewalks,
curbing, abandoned utilities (including pipes, cables, conduit and structures), existing walls,
riprap, various types of fences, septic tanks, drain fields, pump stations, motor boxes,
pumps, irrigation apparatus, base material, trimming of trees and shrubs, drainage
r structures, pipe, backfilling the removal excavations, plus all other items necessary to be
removed to construct the project. All non -salvageable materials removed shall remain
property of the Contractor unless otherwise directed by the Engineer or Owner. All
unwanted materials shall be removed and suitably disposed of by the Contractor outside
the project limits. Any salvage value received from the removed materials shall be
reflected in the Contractor's proposal.
B. Existing and temporary asphaltic pavement and excess subsoil shall be disposed of outside
the project by the Contractor, at a location and in a manner approved by the Engineer.
C. Removal of existing pavement includes all removal and disposal of the asphalt within the
limit shown on the plans for CR 512 and the intersecting side streets. A 3" layer of topsoil
is include in this work for the removed asphalt along CR 512 and paid for in this item.
•
D. Existing artesian and non -artesian water wells located within the limits of the proposed
roadway improvements shall be grouted and sealed in accordance with St. Johns River
r Water Management District Chapter 40C-3, F.A.C.
Payment shall be made under:
r
Item No. 110-1-1 Clearing and Grubbing Lump Sum
V
no
wr
r
J
W
LJ
SECTION 120
W
-73
EXCAVATION AND EMBANKMENT
A. Earthwork, including earthwork for drives and retention ponds outside the right-of-way
limits, shall be paid for as regular excavation. Any excavation to the proposed bottom
elevation of the select fill shall be paid for as regular excavation. Cost shall include all work
specified in this Section and Section 120 of the Standard Specifications. The quantity of
regular excavation is provided due to the evaluation that excavated material will not meet
the specifications for roadway embankment. Any excavated material that does not meet
r
the specifications for roadway embankment shall be disposed of by the Contractor with no
additional compensation. Such price and payment shall specifically include all cost of any
roadway, lateral ditch or canal, and final dressing operations in accordance with Section
4W
120-13.3.
B. Earthwork quantities shall be considered as in-place material with no shrinkage or
expansion factors.
C. Subsoil Excavation — Any excavation below the proposed bottom elevation of the select fill,
isolated swale bottom locations, isolated locations for pipe installations, and as approved by
4W
the Engineer, shall be paid for as subsoil excavation. Approximately 2.5 ft of subsoil
excavation is required in sublateral canals and ditches located under proposed roadway
and drainage culvert improvements. Cost of replacement embankment shall be included in
w
cost of subsoil excavation. Contractor to coordinate with County representative prior to any
subsoil excavation.
..
D. Embankment: General Requirements for Embankment Materials:
Roadway Design Standard Index No. 505, Embankment Utilization Details is modified by
the addition of the following:
Embankment Select Material (A-1, A-3, A-2-4) shall not contain more than 12% passing the
U.S. No. 200 sieve.
•
Fill materials shall be placed at or slightly dry of their optimum moisture content for
compaction as determined by AASHTO T-180. Fill soils will be dried prior to placement in
"
the embankment.
Any stratum or stockpile or soil which contains obvious pockets of highly organic material
•
may be designated as muck or unsuitable for construction of subgrade by the Owner.
Backfill material containing more than 2.0% by weight of organic material, as determined by
�.
FM 1-T267 and by averaging the test results for three randomly selected samples from
each stratum or stockpile of a particular material, shall not be used in construction of the
reinforced volume. If an individual test value of the three samples exceeds 3.0%, the
stratum or stockpile will not be suitable for construction of the reinforced volume.
1,
W
-73
J
or
No A-8 material permitted in embankment either inside or outside of sidewalk location.
~ Payment shall be made under:
Item No. 120-1 Regular Excavation Per Cubic Yard
Item No. 120-4 Subsoil Excavation Per Cubic Yard
Item No. 120-6 Embankment Per Cubic Yard
SECTION 160
r
STABILIZING
Sub Article 160-3 is modified by the addition of the following:
"The stabilization thickness indicated on plans shall be considered a minimum thickness.
r Thickness will vary to conform to the lines, and grades shown in the plans." Minimum L.B.R. _
40 — No under -tolerance.
Payment shall be made under:
Item
No.
160-4-1
Type B
Stabilization
(12")
Per
Square
Yard
Item
No.
160-4-2
Type B
Stabilization
(8")
Per
Square
Yard
SECTION 285
•
OPTIONAL BASE COURSE
., Sub Article 285-4 is modified by the addition of the following:
A. Base material, thickness and requirements are described in the construction plans. Only
one type of alternate base material shall be used through the project limits. The soil
cement option will not be permitted.
Item of Payment
Payment shall be made under:
"' Item No. 285-7-09
Item No. 285-7-16
W
W
to
op
Base
Group 9
Per
Square
Yard
Base
Group 16
Per
Square
Yard
771
W
SECTION 286
TURNOUT CONSTRUCTION
Specifications for turnout construction shall conform to the applicable portions of Section 286 of
the Florida Department of Transportation Standard Specifications for Road and Bridge
Construction (2007 Edition).
• Item of Payment
aj
r
Payment shall be made under:
Item No. 286-1-1 Turnout Construction Asphalt Per Square Yard
SECTION 300
PRIME AND TACK COATS
All prime and tack materials as identified in the 2007 FDOT Road and Bridge Specifications may
be used. Article 300-9 Basis of Payment is deleted and the following substituted: The
quantities to be paid for under this Section shall be included in the cost of the following contract
items:
A. Prime Coat — included in 'Base" Pay Item
B. Tack Coat — included in "Superpave Asphaltic Concrete" Pay Item
C. Bituminous Material (Plant Mix) (asph. cem. 20/30) — to be included in Superpave
Asphaltic Concrete.
4W
SECTION 327
'W MILLING EXISTING ASPHALT PAVING
•
Item of Payment:
Payment shall be made under:
*m Item No. 327-70-1
Item No. 327-73
W
El
W
40
Milling Existing Asphalt Paving Per Square Yard
Milling & Resurfacing (1" depth,
Type SP9.5, Level C) Per Square Yard
•
• SECTION 334
SUPERPAVE ASPHALTIC CONCRETE
r
Subarticle 334-7 is modified by the addition of the following:
Payment shall be made under:
Item No. 334-1 Superpave Asphaltic Concrete Type SP 9.5 (1") - Per Square Yard
•
Item No. 334-2 Superpave Asphaltic Concrete Type SP 12.5 (1-1/2") Per Square Yard
• Included in this payment will be tack coat and bituminous materials (Plant Mix). No separate
payment will be made for bituminous materials. No additional payment will be made for
asphaltic thickness in excess of the specified thickness.
•
'w SECTION 400
CONCRETE STRUCTURES
Specifications for concrete structures shall conform to the applicable portions of Section 400 of
the Florida Department of Transportation Standard Specifications for Road and Bridge
Construction (2007 Edition).
Payment shall be made under:
r Item No. 400-1-2 Class I Concrete Endwalls Per Cubic Yard
• SECTION 425
ON
INLETS MANHOLES AND JUNCTION BOXES
A. Inlet
(Curb Inlet
P5
and J5): Structure bottoms
shall
be
constructed as per FDOT Index
200.
Inlet tops shall
be constructed as per FDOT
Index
211.
•
Payment shall be made under:
• Item No. 425-1-351 Inlet (Curb Type P-5)(<10') Per Each
�r B. Inlet (Curb Inlet P6 and J6): Structure bottoms shall be constructed as per FDOT Index
200. Inlet top shall be constructed as per FDOT Index 211.
Payment shall be made under:
r
Item No. 425-1-361 Inlet (Curb Type P-6)(<10') Per Each
•
u
WMI
r
C. Inlet (DT Bottom Type C D Modified E. and H Modified): Structures shall be constructed
as per FDOT Index 232.
Payment
shall be made
under:
r Item
No.
425-1-521
Inlet
(DT
Bottom
Type
C)(<10')
Per
Each
Item
No.
425-1-542
Inlet
(DT
Bottom
Type
D)(<10')
Per
Each
Item
No.
425-1-549
Inlet
(DT
Bottom
Type
D Modified)(<10')
Per
Each
Item
No.
425-1-571
Inlet
(DT
Bottom
Type
G)(<10')
Per
Each
Item
No.
425-1-573
Inlet
(DT
Bottom
Type
G Modified)(<10')
Per
Each
D. Manholes: Price shall include all work associated with constructing and installing manholes
and covers. The covers shall have raised letters, cast in the cover stating "STORM
SEWER."
Payment shall be made under:
r Item No. 425-2-041 Manhole (Type P-8) (<10') Per Each
Item No. 425-2-042 Manhole (Type P-7) (>10') Per Each
E. Adiust Manholes: Price shall include all work associated with adjusting existing manhole
ring and cover to proposed grades as depicted on the Engineering Plans.
r
Payment shall be made under:
r Item No. 425-5 Adjusting Manholes Per Each
Item No. 425-5-1 Adjusting Manholes (Utilities) Per Each
r SECTION 430
r
PIPE CULVERTS AND STORM SEWERS
A. Concrete Pipe Culvert (Class III) RCP/Corrugated Aluminum Culvert & Mitered End
Section: The concrete pipe culvert, Class III, shall be constructed in accordance with
• Designation C-76, Class III, Wall B. Corrugated aluminum culvert & mitered end section
shall be Group 12. Any select bedding needed to stabilize pipe to be #57 or #4 rock.
Select bedding will be included in the cost of the pipe. Minimum bedding depth to be 18"
• and minimum width to be diameter of pipe. Cost of removal of unsuitable material beneath
18" bedding shall be paid for as subsoil excavation Item No. 120-4.
r The work under this Section shall include all materials, excavation, backfilling, tamping and
disposal of surplus material. All required sheeting is to be included in the cost of pipe.
Such price and payment shall be full compensation for all work in this Section.
r
on
a
r
Payment shall be made under:
r
Item No. 430-11-325
Concrete Pipe Culvert, Storm Sewers Class III, 18" dia.
Per LF
Item No. 430-11-329
Concrete Pipe Culvert, Storm Sewers Class III, 24" dia.
Per LF
Item No. 430-11-333
Concrete Pipe Culvert, Storm Sewers Class 111, 30" dia.
Per LF
Item No. 430-11-338
Concrete Pipe Culvert, Storm Sewers Class 111, 36" dia.
Per LF
Item No. 430-11-340
Concrete Pipe Culvert, Storm Sewers Class Ill, 42" dia.
Per LF
Item No. 430-11-341
Concrete Pipe Culvert, Storm Sewers Class 111, 48" dia.
Per LF
Item No. 430-81-225
Corrugated Aluminum Pipe Culvert, 18" dia.-16 gauge
Per LF
Item No. 430-81-229
Corrugated Aluminum Pipe Culvert, 24" dia.-16 gauge
Per LF
•
Item No. 430-81-233
Corrugated Aluminum Pipe Culvert, 30" dia.-14 gauge
Per LF
Item No. 430-81-238
Corrugated Aluminum Pipe Culvert, 36" dia.-14 gauge
Per LF
Item No. 430-81-240
Corrugated Aluminum Pipe Culvert, 42" dia.-12 gauge
Per LF
Item No. 430-81-243
Corrugated Aluminum Pipe Culvert, 60" dia.-10 gauge
Per LF
�.
Item No. 430-141-102
Elliptical Concrete Pipe Culvert, Storm Sewer
HE 111, 14" x 23"
Per LF
r
Item No. 430-141-103
Elliptical Concrete Pipe Culvert, Storm Sewer
HE Ill, 19" x 30"
Per LF
Item No. 430-141-104
Elliptical Concrete Pipe Culvert, Storm Sewer
HE 111, 24" x 38"
Per LF
Item No. 430-984-402
ADS Storm Culvert, 30" diameter
Per LF
r
Item No. 430-984-225
Mitered End Section, Side Drain, 18" dia. RCP
Per EA
Item No. 430-982-229-1
Mitered End Section, Side Drain, 24" dia. RCP(Dbl)
Per EA
r
Item No. 430-984-233-1
Mitered End Section, Side Drain, 30" dia. RCP(Dbl)
Per EA
Item No. 430-984-338
Mitered End Section, Side Drain, 36" dia. Corrugated Pipe Per EA
Item No. 430-984-402
Mitered End Section, Side Drain, 14"x 23" ERCP
Per EA
Item No. 430-984-403
Mitered End Section, Side Drain, 19"x 30" ERCP
Per EA
ow
Item No. 430-984-403-1
Mitered End Section, Side Drain, 19"x 30" ERCP(Dbl)
Per EA
Item No. 430-984-404
Mitered End Section, Side Drain, 24"x 38" ERCP
Per EA
r
B. Concrete Pipe Joints:
Subarticle 430-7.1.is modified by the addition of the following: In
addition to the rubber gaskets ail round and elliptical concrete pipe other than side drains
r
shall have wrapped filter fabric jacket joints. The joint between the pipe and the
structure
shall also have a filter fabric jacket. These joints shall conform to INDEX 280 and have a
minimum wrapping width of 1' on both sides of the exposed joint. The fabric must be long
r
enough to overlap the
outer circumference of the pipe joint by a minimum of
one foot.
Metal strapping will be
used on both sides of the circumference of the pipe joint
to secure
the fabric. Other methods
which will secure the fabric against the wall until the
backfill is
r
compacted will be considered
for approval by the Engineer. The filter fabric shall be in
accordance with Section
985, and/or as modified by these special provision, for subsurface
drainage. Payment shall be made under the unit price for concrete pipe.
r
C. Pipe Culverts and Storm Sewers: Subarticle 430-12.1. The text is deleted
and the
following substituted:
r
•
"The quantities of pipe culvert to be paid for under this Section shall be the plan quantity in
feet of concrete Pipe Culvert and Corrugated Aluminum Pipe Culvert subject the provisions
of 9-3.2. Any additions or deletions thereto, as authorized by the Engineer, shall be
•
determined by plan dimensions, final measurement, or any combination thereof, as
measured along the centerline of the completed and accepted pipe."
•
Lifting holes on pipe culverts shall be grounds for rejection of pipe. ASTM Specification C-
76 -85A and AASTM Specification M170-89 are modified by the following:
"
"The exposure of the ends of the longitudinal stirrups or spaces that have been used to
position the cages during the placement of the concrete may be a cause for rejection by the
Project Engineer.
During construction, the Contractor is to maintain the storm sewer void of any silting
material. Prior to final acceptance the Contractor or Engineer shall inspect and certify that
•
the storm sewer is free of any construction material or debris and operates in a functional
manner. Contractor shall remove silt and other material from sewer at no cost to Owner.
Compensation shall be included in the maintenance of traffic lump sum item.
•
D. Aluminum Oil Skimmers: Aluminum Oil Skimmers shall be used where indicated in the
plans and shall conform to the following provisions:
The Work consists of the fabrication, cutting, bending, furnishing and installing oil skimmers
on drainage structures as detailed on the Plans. The Contractor shall use all new materials
for the posts and facing materials for the oil skimmer. The Contractor is responsible for the
•
use of materials and methods necessary for the long term maintainability of the units.
Oil skimmers shall be constructed of corrugated aluminum. They shall be constructed to
•
the liens and grades as shown on the Plans. The skimmers include all labor and materials
including mounting fasteners, brackets, posts bonding adhesives, Class III concrete for
posts and all other items necessary for the construction of the completed skimmer.
•
Material
•
The skimmers shall be constructed of 12 gauge 2-2/3" x'/:" corrugated aluminum.
r
Basis of Payment
The compensation for the furnishing, bending, fabrication and installation of materials as well as
the labor involved for placement are considered incidental to the contract drainage items as
shall be included in the unit price for the associated drainage structure.
r
•
•
C
M SECTION 520
CONCRETE GUTTER CURB ELEMENTS & TRAFFIC SEPARATOR
Specifications for concrete gutter, curb elements and traffic separator shall conform to the
applicable portions of Section 520 of the Florida Department of Transportation Standard
Specifications for Road and Bridge Construction, (2007 Edition).
Payment shall be made under:
Item No. 520-1-10 Concrete Curb & Gutter, Type "F". Per LF
r
Item No. 520-5-42 Concrete Traffic Separator, Type IV,
6 ft. wide Per LF
+r
SECTION 522
r
CONCRETE SIDEWALK
M Specifications for concrete sidewalk shall conform to the applicable portion of Section 522 of the
Florida Department of Transportation Standard Specifications for Road and Bridge
Construction, (2007 Edition).
•r
Payment shall be made under:
.• Item No. 522-1 Concrete Sidewalk (4° thick) — 6' wide Per Square Yard
Item No. 522-2 Concrete Sidewalk (6" thick) — 8' wide Per Square Yard
AW
W
Li
10
1W
SECTION 550
M FENCING
A. All
6' Type
B chain
link fencing, posts,
and
gates shall
have a green vinyl coating. The cost
of
the vinyl
coating
shall be included in
the
cost of the
fence.
B. Relocation of existing fence gate shall include all appurtenances and labor to construct.
�+ Relocated fence gate shall be equal or better condition than existing.
Payment
shall be made
under:
i
Item
No.
550-1
Livestock Fence, Type A (5' height)
Per
lineal Foot
Item
No.
550-2
Fencing, Type B (Std. 6')
Per
lineal Foot
Item
No.
550-3-1
Corner Post Assembly (Type A Fence)
Per
Each
Item
No.
550-3-2
Corner Post Assembly (Type B Fence)
Per
Each
Item
No.
550-4-1
Pull Post Assembly (Type A Fence)
Per
Each
Item
No.
550-5-1
Pull Post Assembly (Type B Fence)
Per
Each
Item
No.
550-76-242 Fence Gate, Double 24' opening (Type B Fence)
Per
Each
i
r
ED
0
40
LJ
-�l
SECTION 570
GRASSING (BY SEEDING)
•
570-1 Description.
Establish.a stand of grass on slopes, shoulders and specified other areas, by seeding or by
seeding and mulching. Perform seeding and mulching, fertilizing, and wildflower seed
•
application as required, and maintain the grassed areas until the completion of the project.
The Engineer may eliminate at his discretion, any of the items of work covered by this
Section.
570-2 Materials.
Meet the following requirements:
•
Grass Seed
....................................................................981-1
Wildflower Seed981-1
..........................................................
Mulch........................................................................... 981-3
Fertilizer, Type I .................................................Section 982
Water...................................................................Section 983
Compost..............................................................Section 987
•
Prior to planting, furnish the Engineer a certification from the grower stating the age of
.all seed.
•
570-3 Construction Methods.
570-3.1 General: Do not seed or mulch when wind velocities exceed 15 mph. Sow seed
only when the soil is moist. Do not perform any seeding when the ground is frozen, unduly wet
or otherwise not in a tillable condition.
Whenever a suitable length of roadway slopes or adjacent areas has been graded,
prepare the area and perform grassing in accordance with the Contract Documents. Incorporate
grassing into the project at the earliest practical time.
Complete all grassing on shoulder areas prior to the placement of the friction
course on adjacent pavement, unless the friction course is to be placed directly on a non -asphalt
r
base.
570-3.2 Sequence of Operations: Perform the operations in the following sequence:
Apply finish soil layer materials in accordance with Section 162, prepare the area to be seeded,
seed, spread and cut -in mulch and fertilize.
In preparing the ground for sowing of seeds, disk -harrow and thoroughly
pulverize the soil to an average depth of 6 inches. Make the soil true to grade, not compacted and
free of large clods, roots, and other material which will interfere with the work or subsequent
mowing and maintenance operations. Do not begin subsequent operations until the Engineer has
approved the condition of the prepared areas.
570-3.3 Seeding: While the soil is still loose, scatter the seed uniformly over the grassing
area and immediately mix it into the seed bed to a depth of 1/4 inch using the specified seed.
r.
Thoroughly dry -mix the separate types of seed immediately before sowing. Do
not use wet seed.
The Engineer will allow the wildflower seed to be included in the grassing
•
operation or performed separately from the grass seeding operation in areas shown in the plans.
W
771
570-5 Method of Measurement.
570-5.1 General: The quantities to be paid for will be for the following items, completed
and accepted:
(1) The area, in square feet, of seeding.
(2) The area, in square feet, of seeding and mulching.
(3) The weight, in pounds, of grass seed.
M.
W
Ensure that the wildflower seed is uniformly planted by drilling or placing the
seed into the soil at an average depth of 1/8 inch, but not exceeding 1/4 inch into the designated
area at the specified rate.
570-3.4 Mulching: When areas require mulch, as shown on the plans, apply
approximately 2 inches, loose thickness, of the mulch material uniformly over the seeded area,
and cut the mulch material into the soil to produce a loose mulched thickness of 3 to 4 inches. Do
n,.
not use harrows. The Contractor may use compost meeting the requirements of Section 987 in
lieu of mulch.
When mulching on steep slopes, where the use of a machine for the cutting -in
+
process is not practicable, secure the mulch after the seeding operation by either using an erosion
control fabric, or; spread a string net over the mulch using stakes driven flush with the top of the
mulch at 6 foot centers and string parallel and perpendicular with diagonals in both directions.
570-3.5 Rolling: Immediately after seeding, roll the entire grassed or mulched area with
a cultipacker, traffic roller or a horticultural roller. Make at least two passes over the entire area.
570-3.6 Watering: Provide a vehicle for applying water to the grassed areas equipped
+�
with either a calibrated tank or an approved metering device installed at such point on the vehicle
to measure the water at time of application. Do not water newly seeded areas to force the seed
germination. Do not apply more than 1 inch of water per week for sustaining the grass growth.
Use water only on vegetated areas when permitted by the Engineer.
570-3.7 Fertilizing: Spread the fertilizer over the grassed area four to five weeks after
the grass seed germinates in one or more applications as specified below:
•
Spread an initial application of 265 lbs/acre of 16-4-8.
If the project has not reached final acceptance in accordance with Article 5-11,
spread subsequent applications of 135 lbs/acre of 16-4-8 approximately 60 calendar days after
the initial application without mixing into the soil.
The Contractor may spread the fertilizer by hand on steep slopes or other areas
where machine -spreading may not be practicable.
r
570-4 Maintenance.
Maintain the planted areas as an acceptable stand of grass until final acceptance of the
project at no expense to the Department. Include in such maintenance the filling, leveling, and
repairing of any washed or eroded areas, as may be necessary.
An acceptable stand of grass is defined as a 1 by 1 foot area containing a minimum of 16
live, viable, healthy wildflower and/or grass seedlings.
The Department will pay for replanting as necessary due to factors determined to he
beyond control of the Contractor.
Mow the planted grass areas to a height of 6 inches when competing vegetation height
exceeds 20 inches in height. Do not mow wildflower areas until at least three weeks after the
peak of the bloom period and do not mow lower than 6 inches. Do not use selective herbicides in
wildflower areas.
570-5 Method of Measurement.
570-5.1 General: The quantities to be paid for will be for the following items, completed
and accepted:
(1) The area, in square feet, of seeding.
(2) The area, in square feet, of seeding and mulching.
(3) The weight, in pounds, of grass seed.
M.
W
r (4) The weight, in tons, of mulch material.
(5) The weight, in tons, of fertilizer.
(6) The volume, in thousand gallons, of water.
(7) The weight, in pounds, of wildflower seed.
(8) The area, in acres, of mowing.
570-5.2 Area Quantities: For the quantities paid for on a square foot basis, no
r deductions will be made for the areas occupied by turnouts in rural sections.
570-5.3 Seed: The quantity of grass or wildflower seed will be determined from
packaged weights or by other appropriate methods.
570-5.4 Mulch Material: The quantity will be determined by weighing on truck scales,
or by other appropriate methods. The Contractor shall advise the Engineer of the time and place
r
of such weighing. Weighing will be done in the general vicinity of the project.
Item No. 570- 2- Seeding and Mulching - per square yard.
0
r.
W
r
570-6 Basis of Payment.
570-6.1 General: Prices and payments will be full compensation for all work and
materials specified in this Section.
570-6.2 Seeding: When mulching is not specified, price and payment will be full
compensation for all work and materials not specifically included in the items of separate
payment shown below. The item of Seeding will include specifically all preparations of the
ground, the application of the seed, the rolling, tilling or other specified work.
570-63 Seeding and Mulching: When mulching is specified, price and payment will be
full compensation for everything specified in 570-6.2 and, in addition, will include the cost of
applying, cutting -in, rolling, and anchoring, where required, of the mulch material, but will not
include the furnishing of the mulch material.
570-6.4 Seed: Price and payment for Grass Seed (Permanent Type) and, Grass Seed
(Quick -Growing Type) will be full compensation for the furnishing of the seed, at the site of its
use. Price and payment for Wildflower Seed will include furnishing, applying, and mixing the
seed into the seed bed.
570-6.5 Mulch Material:
570-6.5.1 General: Price and payment will be full compensation for the
furnishing and spreading of the mulch material, at the site of its use.
570-6.6 Water: The quantity of water, ordered at the specific time of its being applied
and which is actually used, determined by the specific metering device or by calibrated tank, will
be paid for at the Contract price per thousand gallons of Water for Grassing. Such quantity will
include all water authorized by the Engineer, which is used until the time of acceptance of the
work.
570-6.7 Payment Items: Payment will be made under:
Item No. 570- 2- Seeding and Mulching - per square yard.
0
r.
W
r
M
M
SECTION 575
SODDING
A. Description: Sod for the project shall be of the variety that is common to the area and of a
variety approved by the Engineer. Where sodding an area in which previously had
` established grass the new sod shall be of the same variety as existing (Argentia Bahia or
St. Augustine). All sodding associated with Landscaping as proposed in Landscape Plans
shall be St. Augustine. This work shall also include mowing in accordance with Section
104-7.2 to be mowed at 6" height with a mulching mower.
B. Work included: Scope of Work: The work specified in this section consists of the
+■ establishing of a stand of grass, within the project, right-of-way, easements, and other
areas indicated on the Drawings, by furnishing and placing grass sod. Also included are
fertilizing, watering and maintenance as required to assure a healthy stand of grass. Two
applications of fertilizer will be required with the initial application being fertilized and the
second application being "weed and feed."
C. Guarantee: All sodded areas shall be guaranteed for three months after date of final
acceptance.
Replacement of Defective Sod: Any dead sod or sod showing (less than 95% of a square)
` indication of probable non -survival or lack of heath and vigor, or which do not exhibit the
characteristics to meet specifications, shall be replaced within two weeks of notice from
Owner or Engineer. All replacement sod shall be furnished/installed at no additional cost to
the Owner and shall be guaranteed for three months. All replacement shall meet original
specifications.
The Contractor shall notify the Owner and Engineer ten days prior to the end of the
guarantee period and such guarantee shall be extended until notification is received.
r„ At the end of the guarantee period, all sod that is dead or in unsatisfactory growth shall be
replaced within two weeks.
` D. Fertilizer: Commercial fertilizers shall comply with the state fertilizer laws.
The numerical designations for fertilizer indicate the minimum percentages (respectively) of
(1) total nitrogen, (2) available phosphoric acid and (3) water-soluble potash contained in
` the fertilizer.
The chemical designation of the fertilizer shall be 16-4-8. Fertilizer shall include iron, minor
nutrients and trace elements. At least 50% of the nitrogen shall be derived from organic
sources. At least 50% of the phosphoric acid shall be from normal super phosphate or an
equivalent source which will provide a minimum of two units of sulfur. The amount of sulfur
shall be indicated on the quantative analysis card attached to each bag or other container.
Contractor shall ensure one (1) pound of nitrogen per 1,000 square feet.
M
M
an
LJ
r
E. Water for Grassing: Contractor shall provide the water used in the sodding operations as
necessary to meet the requirements of Article 570-3.
r
F. Preparation of Ground: The area over which the sod is to be placed shall be scarified or
loosened to a depth and then raked smooth and free from debris. Where the soil is
`
sufficiently loose and clean, the Owner, at his discretion, may authorize the elimination of
ground preparation.
•
G. Application of Fertilizer: Before applying fertilizer, the soil pH shall be brought to a range of
6.0-7.0.
r
Contractor shall apply two (2) applications. The initial shall be fertilizer and the second
application shall be "weed and feed."
r
The fertilizer shall be spread uniformly over the sodded area at the rate of 436 pounds per
acre, or 10 pounds per 1,000 square feet, by a spreading device capable of uniformly
distributing the material at the specified rate.
Contractor shall apply applications a per manufacturer's specification. All tickets from bags
shall be handed over to the County Inspector.
`
On steep slopes, where the use of a machine for spreading or mixing is not practicable, the
fertilizer shall be spread by hand and raked in and thoroughly mixed with the soil to a depth
of approximately 2 inches.
r
H. Placing Sod: The sod shall be placed on the prepared surface, with edges in close contact
and shall be firmly and smoothly embedded by light tamping with appropriate tools.
r
Where sodding is used in drainage ditches, the setting of the pieces shall be staggered so
as to avoid a continuous seam along the line of flow. Along the edges of such staggered
areas, the offsets of individual strips shall not exceed 6 inches. In order to prevent erosion
caused by vertical edges at the outer limits, the outer pieces of sod shall be tamped so as
to produce a feathered edge effect.
s
Where sodding is placed abutting paved shoulder, the Contractor is to ensure that the
finished sod elevation is 1-1/2" below paved shoulder.
`
On slopes greater than 3:1, the Contractor shall prevent the sod from sliding by means of
wooden pegs driven through the sod blocks into firm earth, at suitable intervals.
r'
Sodding shall not be performed when weather and soil conditions are, in the Engineer's
opinion, unsuitable for proper results.
■►
I. Watering: The areas on which the sod is to be placed shall contain sufficient moisture, as
determined by the Engineer, for optimum results. After being placed, the sod shall be kept
in a moist condition to the full depth of the rooting zone for at least two (2) weeks.
a
Thereafter, the Contractor shall apply water as needed until the sod roots and starts to
grow for a minimum of 60 days (or until final acceptance, whichever is latest).
M
r
J. Maintenance: The Contractor shall, at his expense, maintain the sodded areas in a
r satisfactory condition until final acceptance of the project. Such maintenance shall include
repairing of any damaged areas and replacing areas in which the establishment of the
grass stand does not appear to be developing satisfactorily.
Replanting or repair necessary due to the Contractor's negligence, carelessness or failure
to provide routine maintenance shall be at the Contractor's expense.
+" The Contractor shall mow the sodded area up to the final acceptance date as directed by
the Engineer.
r K. Article 575-5he first three paragraphs under this Article are deleted and the following
substituted:
The contract unit price for sodding shall include the costs of sod, fertilizer (2 applications),
sidewalk sweeping after mowing, mowing, disposal of clippings, water, tools, equipment,
labor and all other incidentals necessary.
r
Payment shall be made under:
Item No. 575-1-1 Sodding (Bahia) Includes Watering & Fertilizer Per SY
Item No. 575-1-4 Sodding (St. Augustine) Includes Watering & Fertilizer Per SY
Item No. MLS -14 Sodding Floratom Per SY
r
r
so
ZI
r
W
V
10
SECTION 580
LANDSCAPE INSTALLATION
r
580-1 Description.
Install, establish and maintain landscaping as indicated on Sheets L -I through L-3
r (Landscape Plans) in the Construction Plans.
580-2 Materials.
580-2.1 Plants:
580-2.1.1 Grade Standards and Conformity with Type and Species: Only use
nursery grown plant materials purchased from Florida based Nurseryman Stock that comply with
r, all required inspection, grading standards, and plant regulations in accordance with the latest
edition of the Florida Department of Agriculture's "Grades and Standards for Nursery Plants."
Unless otherwise specified, minimum grade for all plants is Florida No. 1
or better. All plants must be the specified size and grade at the time of delivery to the site and the
minimum grade maintained throughout the project construction period and plant establishment
period.
s Use only plants that are true to type and species and ensure that the plants
not specifically covered by Florida Department of Agriculture's "Grades and Standards for
Nursery Plants" conform in type and species with the standards and designations in general
r acceptance by Florida nurseries. Prior to planting, furnish certification to the Engineer that all
plant materials have been purchased from Florida based Nurseryman Stock.
A minimum of two plants of each species on each shipment must be
shipped with tags stating the botanical nomenclature and common name of the plant. Should
discrepancies between botanical nomenclature and common name arise, the botanical name will
take precedence.
580-2.1.2 Inspection and Transporting: Move nursery stock in accordance with
all federal and state regulations and accompany each shipment with the required inspection
certificates for filing with the Engineer.
580-2.2 Water: Meet the requirements of Section 983.
580-2.3 Mulching: Use of Cypress Mulch prohibited.
580-3 Planting Requirements.
580-3.1 Delivery: All materials must be available for inspection before installation and
will be subject to approval or rejection.
580-3.2 Layout: Mark proposed planting beds and individual locations of trees and
palms as shown in the Contract Documents for Engineer's review, prior to excavation or
planting. The Engineer may request to review all proposed construction and maintenance
practices before the start of the operations.
Make no changes to the layout, materials or any variations of plant materials from
the Contract Documents without the Engineer's written approval.
w 580-3.3 Soil Drainage: All planting holes and beds must drain sufficiently prior to
installing any plants. Immediately notify the Engineer of drainage or percolation problems before
plant installation.
580-3.4 Installation of Plants: For installation of the plants as identified in the Contract
Documents, comply with the requirements of the Design Standards, Index No. 544.
M
W
r 5804 Disposal of Surplus Materials and Debris.
Remove from the jobsite any surplus excavated material from plant holes unless
otherwise directed by the Engineer. Surplus is defined as material not needed after installation of
r
Personnel performing these services are under the sole responsibility and
supervision of the Contractor and must be competent, experienced, and skilled in all aspects of
the required landscape installation and establishment practices.
r
580-3.5 Contractor's Responsibility for Condition of the Plantings: Begin
maintenance of all plants immediately after each planting.
Keep all plants watered, fertilized, mulched, pruned, and staked and guyed as
r
necessary to assure specified minimum grade of Florida No. 1 throughout the duration of the
project construction period and establishment period. During the establishment period, keep the
individual planting locations and planting beds free of litter and undesirable vegetation. Ensure
r
that the plants are maintained so that they are healthy, vigorous, and undamaged throughout the
duration of the project construction period and establishment period. For the duration of the
establishment period, operate and maintain in good operating condition, all components of any
irrigation system installed in compliance with the Contract Documents.
During the establishment period, replace any plants that fall below specified
minimum grade. Use replacement plants of the same species, size and planting medium as the
plant being replaced and as specified in the Contract Documents.
580-3.6 Inspection Requirements. Certify monthly on a form provided by the
Department that the plants have been installed and are being maintained per Contract
°i
Documents. A Registered Landscape Architect acting as the Contractor's Landscape Quality
Control representative will oversee the establishment period.
The Contractor's Landscape Quality Control representative must perform
r
quarterly inspections of planting areas and submit findings in report form to the Department.
Information to be included in inspection report from the Contractor's Quality Control
representative must include as a minimum the following:
Date of inspection
Description of project
Location of inspection
r
Weather conditions
Condition of plants — identify by species, location, and number of plants
that are no longer the specified minimum.
r
Condition of planting beds (including mulching, mowing, weeding,
fertilizing, watering, and staking and guying), if applicable
Other comments
M
Signature and seal of Contractor's Landscape QC representative
Submit the certified inspection report to the Engineer within seven calendar days
after performing the inspection. Any corrections to the inspection report must be
revised/corrected and resubmitted within three calendar days after notification by the Engineer.
Any deficiencies noted on the inspection report must be corrected within ten days of notification
..
from the Department.
Periodic, random verifications will be performed by the Department to ensure the
quality of the plants and correctness of the certified landscape inspection report. Any unresolved
+.�
disputes that arise between the QC reporting and the verifications performed by the Department
will be referred to the Statewide Disputes Review Board.
r 5804 Disposal of Surplus Materials and Debris.
Remove from the jobsite any surplus excavated material from plant holes unless
otherwise directed by the Engineer. Surplus is defined as material not needed after installation of
r
U9
„w
plants per Contract Documents. Upon commencement of the plant installation, remove daily all
landscape installation debris from the landscape locations described in the Contract Documents.
Remove all excess staking and guying materials from the jobsite.
r
580-5 Plant Establishment Period and Contractor's Warranty.
Take responsibility for the proper maintenance, survival and condition of all plants for a
,.
period of one year after final acceptance in accordance with 5-11. Notify the Engineer upon
completion of installation of all plants.
Mowing as part of the landscape work will be identified in the Contract Documents.
r
Continue any mowing of the landscape areas specified in the Contract Documents throughout the
establishment period.
Provide a Warranty/Maintenance Bond to the Department in the amount of the total sums
bid for all landscape items as evidence of warranty during this plant establishment period. The
cost of the bond will not be paid separately, but will be included in the costs of other bid items.
In addition to satisfying the provisions of Section 287.0935, Florida Statutes, the bonding
w
company is required to have an A.M. Best rating of "A" or better. If the bonding company drops
below the "A" rating during the Warranty/Maimenance Bond period, provide a new
Warranty/Maintenance Bond for the balance of the establishment period from a bonding
company with an "A" or better rating. In such event, all costs of the premium for the new
Warranty/Maintenance Bond will be at the Contractor's expense.
The Engineer may conduct interim inspections of all landscape items during the plant
"'
establishment period, as well as at the end of the plant establishment period. As part of the
warranty to the Department, and at no cost to the Department, replace all plants found not to
meet minimum specifications as shown in 580-2.1.1 and 580-3.5 within ten days after each
r'
inspection.
Prior to the end of the establishment period, remove all staking and guying from the
project.
At the end of the establishment period, the Engineer will release the Contractor from
further warranty work and responsibility provided all plants are established and all previous
warranty and remedial work, if any, has been completed to the satisfaction of the Engineer.
r
580-6 Method of Measurement.
The quantifies to be paid will be the items shown in the Contract Documents, completed
and accepted.
580-7 Basis of Payment.
Prices and payments will be full compensation for all work and materials specified in this
Section.
•.
M
or
OW
r—:
SECTION 630
CONDUIT
ar
630-1 Description.
Install conduit for traffic signals and other electrically powered or operated traffic control
r devices as shown in the plans and Design Standards, Index No. 17721.
630-2 Materials.
r
Use materials meeting the requirements of Section A630 of the current Minimum
Specifications for Traffic Control Signal Devices (MSTCSD), except as provided in 603-2.2.
No
630-3 Installation Requirements.
630-3.1 General: Consider the locations of conduit as shown on the plans as
approximate. Construct conduit runs as straight as possible, and obtain the Engineer's approval
w
of all major deviations in conduit locations from those shown on the plans.
Do not place more than the equivalent of four quarter bends or 360 degree of
bends, including the termination bends, between the two points of termination in the conduit,
r
without a pullbox. Obtain the Engineer's approval to use corrugated flexible conduits for short
runs 6 feet or less.
Use only intermediate metal conduit, rigid galvanized conduit, rigid aluminum
it
conduit or PVC coated intermediate metal conduit for above -ground or underground electrical
power service installations. Meet the requirements of Section 562 for coating all field cut and
threaded galvanized pipe.
r
Use either schedule 80 PVC or fiberglass reinforced epoxy conduit for
installations on bridge decks.
Use either schedule 40 PVC or fiberglass reinforced epoxy, conduit for
r
underground and under pavement installations, except for electrical power service.
When the installation of a conduit requires jacking under paved surfaces,
railroads, etc., use an intermediate metal conduit as the sleeve for the underground conduit.
r.
Install the underground conduit as shown in the Design Standards, Index No. 17721.
When a conduit installation changes from underground to above -ground, make
the change a minimum of 6 inches below finished grade.
r
Install a No. 12 AWG pull wire or polypropylene cord the full length of all
conduits that are designated for future use. Ensure that a minimum of 24 inches of pull line
approved by the Engineer is accessible at each conduit termination.
w
Install an expansion fitting when conduit crosses an expansion joint of a structure.
Use couplings and expansion joints made of the same material as the conduit.
Ensure that all joints are made as specified by the manufacturer and are
waterproof.
For installations not specifically shown, install the conduit in accordance with
NEC and/or National Electrical Safety Code requirements.
When earth backfill and tamping is required, place backfill material as per
Section 120 in layers approximately 12 inches thick, and tamp each layer to a density equal to or
greater than the adjacent soil.
+'
When trenching, saw cut and repair all pavement and sidewalks encountered.
rr
When backfilling trenches in existing pavement, use a commercially available
sand -cement (approximately 10:1 mix ratio).
Provide a standard clearance between underground control cable and electrical
w
service cable or another parallel underground electrical service cable that meets National
Electrical Safety Code requirements.
630-3.1.1 Fiber Optic Cable Conduit: Prevent the ingress of water, dirt, sand,
and other foreign materials into the conduit prior to, during and after construction. Exclude water
and debris from buried conduit and from the top riser assembly of aboveground conduit using a
foam -sealing material, rubber plug, or other device designed for this application and approved by
`
the Engineer. Use a UV -rated flexible conduit to protect the cable from the top of the conduit
riser to the span messenger where the cable is to be lashed.
Ensure that the conduit fill ratio (outer cable diameter to inner
conduit/duct diameter) does not exceed 50%.
Install the conduit system so the fiber optic cable maintains a minimum
bend radius of 20 times the cable diameter.
Install the conduit as shown in the plans. Provide all fittings and incidental
materials necessary to construct a complete installation. Use approved methods for connecting
w
inner duct or conduit within or between plowed portions, trenched portions, and bored portions.
Submit the conduit manufacturer's coupling method and material to the Department's Project
Manager for approval.
aw
630-3.1.2 Fiber Optic Cable Locate Wire: Bury locate wire along the centerline
of the top outer surface of installed conduit, as shown in the plans, or as directed by the
Engineer. Install locate wire in the trench or bore with all underground conduits to provide
r
end-to-end electrical continuity for electronically locating the underground conduit system. Do
not install locate wire in a conduit with fiber optic cable.
Do not run locate wires into field cabinets. Terminate locate wires at the
r
first and last pull boxes in the conduit run or as shown in the plans. Ensure that wire termination
occurs only at the top of a pull box.
In a trenching operation, install the locate wire no more than 3 inches
above the conduit. Ensure that the locate wire enters all pull boxes and splice boxes, and that a
minimum of 10 feet of slack locate wire is coiled and neatly stored in each box.
In a boring operation, install the locate wire in an encasement.
Drill a hole in the pull box or splice box for wire entry as shown in the
plans. Fill any gaps between the locate wire and the hole it passes through with nonshrink grout
or a similar sealant suitable for the application and approved by the Engineer.
Perform continuity tests and insulation resistance tests on all locate wires.
Provide the Engineer with all test results. Replace or repair defective locate wire at no additional
cost.
Make locate wire splices in a flush grade -level box. Ensure that locate
wire splices are waterproof and suitable for direct burial. Ensure that locate wire splices at the
pull box meet NEC requirements. Ensure that locate wire splices include a mechanical crimp
connection with a butt sleeve, an oxide -preventing aerosol lacquer, mastic electrical splicing
tape, and standard electrical tape using methods and materials approved by the Engineer. At the
�.
completion of the installation, provide the Engineer with as -built drawings that document all
splice locations.
r
M
Li
630-3.2 Conduit Sizes: Size the conduit to be used on all installations, unless otherwise
shown in the Contract Documents. Use conduit of sufficient size to allow the conductor to be
installed without any damage and meeting NEC requirements. Use conduit that is at least 1 inch
a. in diameter, except for the conduit protecting the ground wire on the side of a pole, use conduit
that is at least 1/2 inch in diameter.
630-3.3 Conduit Joints: Make conduit joints using materials as specified by the
• manufacturer. As an exception to the threaded coupling for intermediate metal conduit, at
locations where it is not possible to screw the threaded coupling properly, the Contractor may
use a waterproof slip -joint coupling approved by the Engineer. Secure the joint, and tighten
threaded connections.
Prior to insertion into the coupling, clean, prime and coat the ends of PVC conduit
with a solvent -type cement as specified by the manufacturer.
1'
630-3.4 PVC Coating: Apply the PVC coating to the entire surface of the conduit,
except for the threads, to attain a nominal thickness of 40 mils. Ensure that the coating is free of
sags and/or drips. Ensure that the bond between the PVC coating and the conduit is greater than
the tensile strength of the PVC coating.
Attach the coupling to the conduit prior to the application of the coating for
conduit
of 1 inch diameter or less.
Use a coupling with sleeve extensions on conduit larger than 1 inch. Ensure that
the sleeve extensions on all threaded female openings have a length equal to the diameter of the
conduit up to and including size number 53.
630-3.5 Conduit Terminations: Fit the terminating ends of all metal conduit and metal
conduit sleeves with an appropriate bushing.
For conduit to be encased in concrete, wrap with tape or otherwise protect all
terminations to prevent the entrance of concrete.
Connect new underground conduit(s) to existing underground conduit(s) with a
,r
pull box.
Install conduit terminating in a concrete strain pole through the cable entry hole
and up the center of the pole to a location approximately 6 inches below the handhole.
r
Seal conduits terminating in a controller base, pole, pull box, junction box, or
pedestal base with Appleton Duct Seal, Permagum Duct Seal, GB Duct Seal, or an equivalent
moisture resistant sealant approved by the Engineer.
+�
For a controller base, pole or pedestal base, and junction boxes, terminate conduit
runs into the center of the base or box at least 2 inches above the surface of the base.
630-3.6 Existing Underground Facilities: Coordinate with any potential conflicting
underground utilities prior to starting all excavating or jacking operations at the project site.
630-3.7 Restoration of Trench Areas: Restore the conduit trench construction area to
an acceptable condition. Such work includes replacement of all pavement areas, sidewalks,
curbs, structures, or grass areas disturbed by the conduit trench.
630-3.8 Jacking Conduit: Use either intermediate metal conduit or rigid galvanized
conduit as the sleeve when installation of a conduit requires jacking under paved surfaces,
railroads, etc., with either polyvinyl chloride or fiberglass reinforced epoxy conduit installed in
the jacked sleeve. Do not disturb any pavement without the approval of the Engineer.
630-3.9 Above -Ground Installation: Securely attach above -ground conduit installations
to the surface of the supporting structure using conduit straps. As a minimum, use conduit straps
located
on 5 feet centers. Use galvanized metal
conduit straps when
installing
intermediate
metal
conduit, fiberglass reinforced epoxy conduit, rigid galvanized conduit, rigid aluminum conduit or
PVC coated intermediate metal conduit above ground.
Use the same PVC coating for the metal straps as the conduit, when using PVC
coated intermediate metal conduit.
630-3.10 Elbows: Use only preformed or field constructed conduit elbows. The radius of
curvature of the inner edge of any bend shall not be less than shown below:
r
W
W
W
•r
630-4 Method of Measurement.
630-4.1 General: Measurement for payment will be in accordance with the following
work tasks.
630-4.2 Furnish and Install: The Contract unit price per foot of conduit, furnished and
installed, will include famishing all hardware and materials as specified in the Contract
Documents, and all labor, trenching, backfilling, and restoration materials necessary for a
complete and accepted installation.
OW Payment for conduit placed in the ground or used on bridge decks will be based
on the horizontal path of the installed conduit as measured in a straight line between the centers
of pull boxes, cabinets, poles, etc. No allowance will be made for sweeps or vertical distances
y above or below the ground or the bridge deck.
Due to conditions which may exist on the project site, the Contractor may furnish
conduit in variable lengths.
• Furnishing and installing the locate wire is included in the cost of the conduit.
Conduit used for fiber optic cable includes the cost of furnishing and installing
the locate wire and the cost of conducting the continuity test and the insulation resistance test.
• 6304.3 Furnish: The Contract unit price per foot of Conduit, furnished, will include the
cost of materials, and hardware as specified in the Contract Documents, plus all shipping and
handling cost involved in delivery as specified in the Contract Documents.
r' The Contractor shall furnish conduit in 20 foot sections with one coupling per
section.
630-4.4 Install: The Contract unit price per foot of conduit, installed, will include all
miscellaneous hardware and materials, labor, trenching, backfilling, and restoration materials
necessary for a complete and accepted installation.
r
M
Size
Standard Radius
1/2 inch
4 inches
3/4 inch
4 1/2 inches
1 inch
5 1/2 inches
1
1/4 inches
7 1/4 inches
1
1/2 inches
8 1/4 inches
2 inches
9 1/2 inches
2
1/2 inches
10 1/2 inches
3 inches
13 inches
3
1/2 inches
15 inches
4 inches
16 inches
5 inches
24 inches
6 inches
30 inches
630-4 Method of Measurement.
630-4.1 General: Measurement for payment will be in accordance with the following
work tasks.
630-4.2 Furnish and Install: The Contract unit price per foot of conduit, furnished and
installed, will include famishing all hardware and materials as specified in the Contract
Documents, and all labor, trenching, backfilling, and restoration materials necessary for a
complete and accepted installation.
OW Payment for conduit placed in the ground or used on bridge decks will be based
on the horizontal path of the installed conduit as measured in a straight line between the centers
of pull boxes, cabinets, poles, etc. No allowance will be made for sweeps or vertical distances
y above or below the ground or the bridge deck.
Due to conditions which may exist on the project site, the Contractor may furnish
conduit in variable lengths.
• Furnishing and installing the locate wire is included in the cost of the conduit.
Conduit used for fiber optic cable includes the cost of furnishing and installing
the locate wire and the cost of conducting the continuity test and the insulation resistance test.
• 6304.3 Furnish: The Contract unit price per foot of Conduit, furnished, will include the
cost of materials, and hardware as specified in the Contract Documents, plus all shipping and
handling cost involved in delivery as specified in the Contract Documents.
r' The Contractor shall furnish conduit in 20 foot sections with one coupling per
section.
630-4.4 Install: The Contract unit price per foot of conduit, installed, will include all
miscellaneous hardware and materials, labor, trenching, backfilling, and restoration materials
necessary for a complete and accepted installation.
r
M
W
r7
The Engineer will supply conduit in sections with one coupling per section and
elbows as required.
Payment for conduit placed in the ground or used on bridge decks will be based
on the horizontal path of the installed conduit as measured in a straight line between the centers
of pull boxes, cabinets, poles, etc. No allowance will be made for sweeps or vertical distances
above or below the ground or the bridge deck.
Installing the locate wire is included in the cost of the conduit. Conduit used for
fiber optic cable includes the cost of installing the locate wire and the cost of conducting the
w, continuity test and the insulation resistance test.
630-5 Basis of Payment.
Price and payment will be full compensation for all work specified in this Section.
Payment will be made under:
Item No. 630- 1-2 Conduit - per foot.
M
•
M
•
n
M
•
on
AW
M
M
or
r.
W
r
0
SECTION 635
PULL AND JUNCTION BOXES
635-1 Description.
Install pull and junction boxes for traffic signals.
635-2 Materials.
Use Pull and Junction Boxes listed on the Department's Approved Product List (APL).
.. Ensure that all Pull and Junction Boxes are marked in accordance with Section 603 and the
markings are visible after installation.
635-3 Pull Boxes Installation.
Install pull boxes in accordance with the Design Standards, Index No. 17721. Ensure that
the pull box cover is flush with the finished grade or sidewalk. Do not install pull boxes in
ru roadways, driveways, parking areas, ditches or public sidewalk curb ramps.
635-4 Junction Boxes Installation.
635-4.1 Aerial Junction Boxes: Install aerial junction boxes in accordance with the
Design Standards, Index No. 17733.
635-4.2 Mounted Junction Boxes: Install mounted junction boxes in accordance with
the Design Standards, Index No. 17841. Ensure that the bottom surface of pole mounted junction
boxes is a minimum of 4 feet above the finished grade.
635-4.3 Cable Terminations: Make cable terminations in junction boxes in accordance
i, with Section 632. Rout and form the cable to allow access to the terminal screws. Do not cover
the terminal identification numbers with the cable.
635-5 General. Requirements.
Do not pull signal or interconnect cable through a pull box used for loop termination. Use
separate pull boxes for signal and interconnect cables.
r, Use embedded junction boxes that include junction boxes, conduit, conduit expansion
couplings, and miscellaneous hardware to make a complete and accepted installation -
Ground all metal covers in accordance with Section 620.
r When specified in the Contract Documents, disregard the grounding requirements for
metal covers for pull and junction boxes powered strictly by battery or a combination of battery
and solar energy or used exclusively for vehicle loop wires where signal or 120V interconnect
power is not present.
635-6 Method of Measurement.
635-6.1 General: Measurement for payment will be in accordance with the following
work tasks:
635-6.2 Furnish and Install: The Contract unit price each for Pull and Junction Boxes,
furnished and installed, will consist of the pull and junction boxes including all required
hardware for the type of box and location as specified in the Contract Documents, and all labor
and materials necessary for a complete and accepted installation.
,. 635-6.3 Furnish: The Contract unit price each for Pull and Junction Box, furnished, will
include the cost of the pull and junction box including covers, doors, locks and keys, and any
to
r
L
r necessary miscellaneous hardware specified in the Contract Documents, plus all shipping and
handling costs involved in delivery as specified in the Contract Documents
635-6.4 Install: The Contract unit price each for Pull and Junction Box, installed, will
include the cost of all labor, equipment, miscellaneous hardware and materials necessary to make
a complete and accepted installation of the type box and at locations as shown on the plans. The
Engineer will supply a complete box as specified in the Contract Documents.
635-7 Basis of Payment.
Price and payment will be full compensation for all work specified in this Section, except
~ grounding. Payment for embedded junction boxes will not be made separately.
The Contractor shall include the cost of embedded junction boxes in the Contract unit
price for the concrete substructure or superstructure items_
Payment will be made under:
Item No. 635- 1-11 Pull and Junction Boxes - per each
w Item No. 635- 1-15 Slack/Splice Boxes - per each.
W
W
W
L:J
40
"7
C
i
SECTION 700
so SIGNING AND PAVEMENT MARKING
A. Signing and pavement marking for traffic control shall conform to the requirements of the
• Standard Specifications (2003) Manual on Uniform Traffic Control Devices, Supplemental
Specifications, Roadway and Traffic Design Standards, manufacturers specifications.
B. Traffic Signs: All existing signs which are the property of the Owner shall be transported to
the Indian River County Road and Bridge Maintenance Yard by the Contractor during
construction if they are within the construction limits. Care shall be e)iercised by the
Contractor during removal, storage and relocation so as not to damage the signs. If any
• damage occurs, as determined by the Owner's Engineer or Resident Construction
Inspector, the sign shall be replaced by the Contractor with no compensation.
• C. Article 700-11: The following is added to this Article:
Payment shall be made under.
Item No. 700-40-1
Item No. 700-46-21
• Item No. 700-46-11
Sign Single Post
Sign Existing (Relocate) (Single Post)
Sign Existing (Remove)
SECTION 706
Per Each
Per Each
Per Each
RAISED RETRO -REFLECTIVE PAVEMENT MARKERS AND BITUMINOUS ADHESIVE
Specifications for Reflective Pavement Markers shall conform to the applicable portion so
Section 706 of the Florida Department of Transportation Standard Specifications for Road and
it Bridge Construction, (2007 Edition).
773
A. All reflective pavement markers shall be 4" x 4".
Basis of Payment
to The work listed under this Item shall include the furnishing and installation of all materials
necessary to complete the installation of Reflective Pavement Markers in accordance with
the details shown in the Construction Plans.
to Payment shall be made under.
Item No. 706-3 Reflective Pavement Markers Per Each
J
•
40
r
SECTION 711
• THERMOPLASTIC TRAFFIC STRIPES AND MARKINGS
Specifications for Thermoplastic Traffic Stripes and Markings shall conform to the applicable
portion so Section 711 of the Florida Department of Transportation Standard Specifications for
Road and Bridge Construction, (2007 Edition).
• Basis of Payment
The work listed under this Item shall included all painting, all cleaning and preparing of
r surfaces, furnishing of all materials, including paints and spheres; the application, curing
and protection of all paints; the protection of traffic; the furnishing of all tools, machines, and
all other necessary equipment; and the furnishing of all incidentals necessary to complete
the work.
Payment shall be made under:
Item
No.
711-3
Directional Arrows
Item
No.
711-4
Skip Traffic Stripe
Item
No.
711-33
Skip Traffic Stripe
Item
No.
711-34
Solid Traffic Stripe
Item
No.
711-35-61
Solid Traffic Stripe
Item
No.
711-35-121
Solid Traffic Stripe
Item
No.
711-35-181
Solid Traffic Stripe
Item
No.
711-35-241
Solid Traffic Stripe
Item
No.
711-36-61
Solid Traffic Stripe
.. Item
No.
711-36-61
•
or
W
Pavement Messages (Thermo)
Per
Each
Directional Arrows
(Thermo)
Per
Each
Skip Traffic Stripe
(Thermo)(White)
Per
LF
Skip Traffic Stripe
(Thermo)(Yellow)
Per
LF
Solid Traffic Stripe
(Thermo)(6"White)
Per
LF
Solid Traffic Stripe
(Thermo)(12"White)
Per
LF
Solid Traffic Stripe
(Thermo)(1 8White)
Per
LF
Solid Traffic Stripe
(Thermo)(24"White)
Per
LF
Solid Traffic Stripe
(Thermo)(6"Yellow)
Per
LF
Solid Traffic Stripe
(Thermo)(6"Yellow)
Per
LF