Loading...
HomeMy WebLinkAbout2008-009 (5)r. Chapter 4 - Hest. .Management. Practices for Erosion. and.:Sediment.Gontrol. Good timing is essential to fill construction. The filling operation should be completed as quickly as possible and the permanent slope protection measures and slope stabilization measures installed as soon after completion as possible: With quick and proper construction, the developer or contractor will save both time and money in building, repairing and stabilizing the fill area. The longer the time period for construction and stabilization, the more prone the fill operation is to damages by erosion. Repairing the damages adds additional time and expense to the project. ` Design Criteria M No formal design is required. The following criteria shall be met: Drainage Area ` The maximum allowable drainage area is 5 acres (2 ha). r Height • The minimum height of the supporting. ridge shall be 9 inches (23 cm). (See Plate 4.16a). Grade The channel shall have a positive grade to a stabilized outlet. Outlet The diverted runoff should be released through a stabilized outlet, slope drain or sediment trapping measure. Construction Specifications 1. The diversion shall be constructed at the top of the fill at the end of each work day as needed. 2. The diversion shall be located at least 2 feet (60 cm) inside the top edge of the fill. (See Plate 4.16a). 3. The supporting ridge of the lower side shall be constructed with a uniform height ` along its entire length. Maintenance Since the practice is temporary and under most situations will be covered the next work day, the maintenance required should be low. If the practice is to remain in use for more than one day, an inspection will be made at the end of each work day and repairs made to the measure if needed. The contractor should avoid the placement of any material over the structure white it is in use. Construction traffic should not be permitted to cross the diversion. Florida Erosion and -Sediment Control Inspector's Manual This page left intentionally blank 4-62 AW Chapter 4,: -,Best Man agement. Practices_for Erosion and Sediment. Control • 4.17 TEMPORARY RIGHT-OF-WAY DIVERSION • (ES BMP 1.17) Definition • A ridge of compacted soil or loose rock or gravel constructed across disturbed rights-of-way and similar sloping areas. Purpose �. To shorten the flow length within a long sloping right-of-way, thereby reducing the erosion potential by diverting storm runoff to a stabilized outlet or sediment trapping device. r Conditions Where Practice Apniles: . Generally, earthen diversions are- applicable where there will be little or no construction • traffic within the right-of-way. Gravel structures are. more ap"piicable to roads and other rights-of-way which accommodate vehicular traffic: • Planning Considerations Construction of utility lines and: roads often requires the clearing of long strips of .. right-of-way over sloping terrain. The volume.and velocity of stormwater runoff tend to increase in these. cleared strips and the potential for erosion is much greater since the vegetative cover is diminished or removed. To compensate forthe loss of vegetation, itis usually a good practice to break up the flow length within the cleared strip so that runoff does not have a chance to concentrate and cause erosion. At proper spacing intervals, Temporary Right -of -Way Diversions can significantly reduce the amount of erosion which ,. will occur until the area is permanently stabilized. Design Criteria • No formalAesign is required. The following criteria shall be met: ,. Drainage Area Less than 5 acres (2 he). For larger drainage areas use a DIVERSION. -Section 5.18 (ES • BMP 1.18). Dimensions The minimum allowable height measured from the upslope side of the diversion is 18 inches (45 cm). The minimum top width shall be 2 feet (60 cm) and the base width • minimum is 6 feet (1.8 m). (See Plate 4.17a) Side Slopes 3:1 or flatter to allow the passage of construction traffic. Florida Erosion and Sediment Control Inspector's Manual Width The measure should be constructed completely across the disturbed portion of the right-of-way. Plate 4.17a Temporary Right-of-way Diversions Source: Virginia OSWC Chapter4- Best Management rraottces Tor erosion r Spacing The following table will be used to determine.the spacing of right-of-way diversions: % Slope 'Spacing in feet(m). Less than 5% 300 (90 m) Between 5% and 10% 200 (60 m) Greater than 10% 100 (30 m) Grade r Positive drainage, With less than 2% slope, should be provided to a stabilized outlet or sediment trapping facility. Outlet Interceptor dikes must have an outletwhich is not subject to erosion. The on-site location may need to be adjusted to meet field conditions in order to utilize the most suitable outlet. Concentrated flows should spread over the widest possible area after release. Flows with r high sediment concentrations should pass through a sediment trapping measure. (See Plate 4.17b) Construction Specifications 1. The diversion shall be installed as soon as the right-of-way has been cleared and/or graded. 2. All earthen diversions shall be machine- or hand -compacted in 8 -inch (20 cm) lifts. it 3. The outlet of the diversion shall be located on an undisturbed and stabilized area when at all possible. The field location should be adjusted as needed to utilize a ,r stabilized outlet. Sediment laden flows shall be conveyed.to a sediment trapping device. 4. Earthen diversions which will not be subject to construction traffic should be stabilized in accordance with TEMPORARY SEEDNG - Section 6.65 (ES BMP .65). • Maintenance The practice shall be inspected after every rainfall and repairs made if necessary. Approximately once every week, whether a storm has occurred or not, the measure, shall be inspected and repairs made if needed. Diversions which are subject to damage by ,,,, vehicular traffic should be reshaped at the end of each working day. Florida Erosion and. Sediment Control Inspector's Manual t, �raly- 2:i SIDE 5LOMS - 3i I MAX I— FFOOR Yee' illrRE G7smc, SLOM q '::�'_'_• law MIN. .I SECTION Plate 4.17b Rolling Dip and Water Bar Source: Erosion Draw 4-66 a .. - Rest M.anaaement Practices.for.Eroslon and r 4.25 TEMPORARY SEDIMENT TRAP (ES BMP 1.25) Definition r A small temporary ponding area formed by excavation and/or an embankment across a draihageway. r Purpose .. To detain sediment -laden runoff from small disturbed areas long enough to allow most of the sediment to settle out thereby protecting drainageways, properties, and rights-of-way from sedimentation. r Conditions WherePractice Apolies r 1'. A sediment trap is usually installed in a drainageway, at a storm drain inlet or at other points of discharge from a disturbed area. ., 2. Below drainage areas of 5 acres (2 ha) or less. 3. Where the sediment trap will be used less than 18 months. r 4. The sediment trap may be constructed either independently or in conjunction with a TEMPORARY DIVERSION DIKE - Section 4.15 (ES BMP 1.15). Plannirrg Considerations The sediment trap should be located to obtain the maximum storage benefit from the terrain, for ease of clean out and disposal of the trapped sediment and to minimize interference with construction activities. r Sediment traps should be used only for small drainage areas. If the contributing drainage area is greater than 5 acres (2 ha), refer to SEDIMENT BASINS - Section 4.26 (ES BMP ,. 1.26). Sediment must be periodically removed from the trap. Plans should detail how this ., sediment is to be disposed of, such as by use in fill areas on site or removal to an approved off-site dump. r Sediment traps, along with other perimeter controls, shall be installed before any land disturbance takes place in the drainage area. L-1 10 Florida Erosion and Sediment Control Inspector's Manual Dike if Required to Divert Water to Trap � :;::!: f::g Section A A Excavated Earth Outlet SedimentTrap Excavate, if Necessary, for Storage Flow Embankment,X-4'0 21 or Flatter Width (ft) 6 x Drainage Area (Ac.) Outlet Section Embankment Earth Outlet Sediment Trap Construction o if ations 1. Area under embankment shall be cleared, grubbed and stripped of any vegetation and root mat The pool area shall be cleared. 2. The fill material for the embankment shall be free of roots or other woody vegetation as well as over- sized stones, rocks, organic material, or other objectionable matsdai.The embankment shall be compacted by traversing with equipment while it is being constructed a. Sediment shall be removed and trap restored to its original dimensions when the sediment has accumulated to 112 the design depth of the trap. Removed sediment shall be deposited in a suitable area and in such a manner that it will not erode. 4. The structure shall be inspected after each rain and repairs made as needed. 5. Construction operations shall be carried out in such a manner that erosion and water pollution are minimized. S. Tile structure shall be removed and area stabilized when the drainage area has been properly stabirized. 7. All out and fill slopes shall be 2:1 or flatter. S. Outlet crest elevation shall be at least one foci below the top of the embankment Plate 4.25a Earth Outlet Sediment Trap Source: NRCS Chapte .r Design Criteria Trap Capacity Erosion and The sediment trap must have an initial storage volume of 134 cubic yards, or 3600 cubic feet per acre ( 252 m3/ha) of drainage area, measured from the low point of the ground to the crest of the gravel outlet. Sediment should be removed from the basin when the volume is reduced by one-half. r For a natural basin, the volume may be approximated. as follows: • V=0.4xAxD where: V = the storage volume in ft.3 • A = the surface area of the flood area at the crest of the outlet, in ft.Z D = the maximum depth, measured from low point in trap to crest of outlet, in ft. Excavation If excavation is necessary to attain the required storage volume, side slopes should be no steeper than 2:1. • Embankment Cross -Section The maximum height of the sediment trap embankment shall be 5 feet (1.5 m) as • measured from the low point. Minimum top widths (W) and outlet heights (Ho) for various embankment heights (H) are shown in Table 4.25a. Side slopes of the embankment shall be 2:1 or flatter. • Table 4.25a7 MINIMUM TOP WIDTH (W) AND OUTLET HEIGHT (Ho) REQUIRED FOR SEDIMENT TRAP EMBANKMENT ACCORDING TO HEIGHT OF EMBANKMENT (feet) W H: Ho W 2.0 1.0 2.0 .. 2.5 1.5 2.5 3.0 2.0 2.5 3.5 2.5 3.0 4.0 3.0 3.0 4.5. 3.5 4.0' 5.0 4.0 4.5 Florida Erosion and Sediment Control Inspector's Manual Earth Embankment . Nutlet Protection All Slopes 2:1 or Flatter Excavate, if Necessary, for Storage Flow Lam•. 4' �.�. ;1^-6' Min. 5' Max. Welded All Around Embankment SectionThru Fuser Construction Specifications Perforated Riser 1. Area under embankment shall be cleared, grubbed and stripped of any vegetation and root mat. The pool area shall be cleared 2. The fill material for the embankment shall be free of roots.or other woody vegetation as well as over- sized stones, rocks, organic material, or other objectionable material.The embankment shall be compacted by traversing with equipment while it is being constructed. 3. Sediment shall be removed and trap restored to its original dimensions when the sediment has accumulated to 1/2 the design depth of the trap. Removed sediment shall be.deposhed in a suitable area and in such a manner that it will not erode. 4. The structure shall be Inspected after each rain and repairs made as needed. 5. Construction operations shall be carried out in such a manner that erosion and water polluflon are minimized. 6. Tile structure shall be removed and area stabilized when the drainage area has been properly stabilized. 7. All cut and fill slopes shall be 2.1 or flatter. B. All pipe connections shall be watertight 9. At least the top 213 of the riser shall be perforated with 112 -inch diameter holes spaced a inches vertically and 10 -12 inches horizontally. 10. Fig matertail around pipe spillway shall be hand compacted in 4 -Inch layers. A minimum of two feet of hand -compacted backtlll shall be placed over the pipe spillway before crossing If with construction equip- , ment. Plate 4.25b Pipe Outlet Sediment Trap Source: NRCS M w ;.-, L7 r u r r 7 7 r Chapter 4 - Best Management Practices for Erosion and. Sediment Control ORIGINAL GROUND ELEV. Ill VARIABLE 67 CU. YD./ACRE — T (EXCAVATED) V QAX' FILTER CLOTH ORIGINAL GROUND ELEV. COARSE AGGREGATE CLASS I WRAP Crass -Section of outlet CLASS I RIRRAP LENGTH (IN FEET) H X DRAINAGE AREA I lip (LN AC.) �.- ONERSION DIKE' Z MM COARSE AGGREGATE4 ME f f EXCAVATED FILTER CL F/par_! AREA CGARSE AGlic(CijAtC SF:`Ai.t SE rTOT y3, X357 OR. #5 Outlet (Perspective View) Plate 4.25c Slone Outlet Sediment Trap Source: NRCS r 441 TOE OF U KEY BALE INTO BANKAT BOTH: ENDS OF, BARRIER It �-EMBED STRAW. BALE 4' MIN, U INTO SOIL SECTION A - A STRAW BALES TIGHTLY ABUTTING. . 3 it . • Y 0 WOODEN STAKE OR REBAR DRIVEN T1qROV6H. SALE. .. TYP. :Z= PER BALE' .. TA A,yviy. VIEW LOOKING UPSTREAM NOTES, I. PLACE BALES PERPENDICULAR .. - TO PLOW. 2. £t*15EP THE BALE 4' INTO THE SOIL AND 'KEY' THE END SALES INTO THE CHANNEL' - BAHKS. S. BALES PLACED IN A ROW WITH ENDS TI6HnLY ABUTTING. USE STRAW, ROCKS OR FILTER FABRIC TO PILL ANY 6AP5 BBTreEm BALES AND TAMP SACKFILL MATERIALS TO FFMTV Mr EROSION OR FLOYV AROUND THE SALES. 4. POINT 'A' SHAH BE HIGHH¢ THAN POINT 'B'. 5. SPILLWAY SHALL NOT EXCE= 241. Plate 4.25d Semi -pervious Straw Bale Sediment Barrier Source: Erosion Draw 4-72 Chapter 4---7 Best -Managements Practices for Erosion and. Sediment uontrot r Outlet The outlets shall be designed, constructed and maintained so that sediment does not leave the trap and that erosion of the outlet does not occur. A trap may have several different outlets: with each outlet conveying part of the flow based on the criteria below. The combined outlet capacity shall be sufficient for the drainage area. Foe. example, a 12 foot (3.6 m),earth outlet, adequate for 2 acres (0.8 ha), and a 12 inch (30 cm) pipe outlet, adequate for 1 acre (0.4 ha), could be used for a three acre (1.2 ha) drainage area. There are four types of outlets for sediment traps. Each sediment trap is named according r to the type of outlet that it has. Each type has different design criteria and will be discussed separately. 1. An Earth Outlet Sediment Trap consists of a basin formed by excavation andloran embankment. The trap has a discharge point overor cut into natural ground. The outlet width (feet) shall be equal to 6 times the drainage area (acres). If an embankment is used the outlet crest shall be at least one foot (30 cm) below the top of the embankment. The outlet shall be free of any restriction to flow. The earthen embankment shall be seeded with temporary or permanent vegetation (see Sections 6.65. and 6.66) within 15 days of construction: (See Plate 4.25a) 2. A Pipe Outlet Sediment Trap consists of a basin. formed by an embankment, or an r excavation and 'an embankment. The outlet for the trap is though`a perforated riser and a. pipe through the embankment. The outlet pipe and riser shall be made of corrugated metal. The riser diameter shall- be of the same or larger diameter than the pipe. The top of the embankment shall be at least 1.5 feet (45 cm) above the crest of the riser. At least the top 2/3 of the riser shall be perforated with 1/2 inch (13 mm) diameter holesspaced 8 inches (20 cm) vertically and 10-12 inches (25 30 cm) horizontally. All pipe connections shall be watertight (See Plate 4.25b). us Select pipe diameter from the following table: 4W 12 (30 cm) 1(0.8 18 (45 cm) ha)` 21 (53 cm) 3 (1.2 ha) 24 (60 cm) 4 (1.6 ha) 30 (75 cm) 5 (2.0 ha) 3. A Stone Outlet Sediment Trap consists of a basin formed by an embankment or excavation and an embankment. The outlet for the sediment trap shall consist of a crushed stone section of the embankment located at the low point in the basin. The f t1L� s L..❑ 5... t' 4 '- h r 9 r minimum length o. ti le outlet shaft be 6 feet thanes the acreage of a talnage area (4.5 m times hectares). The crest of the outlet must be at least lfoot (30 cm) below the top of the embankment, to insure that the flow wilt travel over the stone and not the embankment. The outlet shall be constructed of FDOT No. 1 size crushed stone. (See Plate 4.25c) Avery temporary alternate trap can be constructed from straw bales with a stone outlet. (See Plate 4.25d) Straw bales shall be installed per Section 4.05 STRAW BALE BARRIER (ES BMP 1.05). A.71 and. Sediment Control Inspectors Manual. 4. A Storm Inlet Sediment Trap consists of a basin formed by excavation or natural ground that discharges through an opening in a storm drain inlet structure. This opening, can either be the inlet opening or a temporary opening made by omitting bricks or blocks in the inlet. The trap shall be between 1' and 2'(30 - 60 cm) deep measured from the low point of the inlet. A yard drain inlet or an inlet in the median strip of a dual highway would use the inlet opening for an outlet. (See Plate 4.25e) A curb inlet would require a temporary opening. (See Plate 4.25f) The trap should be out of the roadway to.avoid interference with constriction. Placing the trap on the opposite side of the opening and diverting water from the roadway to the trap is one means of accomplishing this. 5. Other applications Attimes a small trap may be constructed in a drainage channel using the culvert for a road crossing. Straw bales or gravel filled bags maybe used provided that there are no gaps in the installation. (See Plate 4.25g) In larger traps baffles may be required to insure adequate flow length and prevent short- circuiting: (See Plate 4.25h) Construction Specifications The area under the embankment shall be cleared, grubbed; and stripped of any vegetation and root mat. To facilitate cleanout, the pool area should be cleared. 2. Fill material for the embankment shall be free of roots or other woody vegetation, organic material, large stones, and other objectionable material. The embankment should be compacted in 8 inch. (20 cm) layers by traversing with construction equipment. - - . 3. The earthen embankment shall be seeded with temporary or pe rmanent vegetation (see Sections -6.65 and 6.66) within 15 days of construction. 4. Construction operations shall be carried out so that erosion and water pollution are minimized. 5. The structure shall be removed and the area stabilized when the upslope drainage area has been stabilized: Maintenance Sediment shall be removed and the trap restored to its original dimensions when the sediment has accumulated to 112 the design volume of the trap: Sedimeni removed from the basin shall be deposited in a suitable area and in such a manner that it will not erode. 2. The structure should be checked regularly to insure that it is structurally sound and has not been damaged by erosion or construction equipment. The height of the outlet should be checked to ensure that its center is at least one foot (30 cm) below the top of the embankment. 4-74 an Chapter 4 - Best Mans a t Practices for Erosion and Sediment MAX. SLOPE 2 STORM WATER WITH LaROER PARTICLES". REMOVED DRAIN INLET FLOW 7�' 1 r FLOW FLgR DEPTH BELOW TOP OF INLET: MIN. I'— MA%. Z , WEEP HOLES 1111.�f 11 - s FOR DEWA7ERING _ _.... I[-1f=tf—ll—/-11-1 '=if=►f�f=fl=lr=ao=u=n. TH!S METHOD OF INLET PROTECTION IS APPLICABLE WHERE HE"YY FLOWS ARE EXPECTED AND WHERE AN OVERFLCW CAPAStLITY AND EASE OF MAINTENANCE ARE DESIRABLE, Plate 4.25e Excavated Drop Inlet Sediment Trap Source: Michigan Sol Erosion and Sedimentation Control Guidebook i Florida Erosion and Sediment Control Inspector's Manual Row• is - ROW ' l•,,i �\� `\:�-`-'. + 1. t j•L•i .; �'t,♦ .l jA`• !C' fop � � ori'}-+•�• /'�^ Row' Flow . - S`�•<� - As Required —7 21 or Flatter Cross -Section Yard Drain Block Inlet with Plywood and Sandbags, as Necessary, to Prevent Water from Entering? Flow � er L., I K\1�49 y .. 11it ' A Remove Bricks or::-1�-�•: Blocks for outlet I - Trap may be Placed Behind or at End of Inlet ff 2.1 or ��Fla��ttt�er . 7r/V_,IiYLiIYrtlY11111iielr 4v 1 Min f' Section A -A Curb Drain . NOTE Where curb is in place, provide a 1 foot wide opening in the curb or use a sandbag dam to force water over the curb to the trap. Construction Soecifications 1. Sediment shall be removed and trap restored to its original dimensions when the sediment has accumulated to 1/2 the design depth of the trap. Removed sediment shall be deposited in a suitable area and in.such a manner that it will not erode. 2.The structure shall be inspected after each rain and repairs made as needed. 3. Construction operations shall be carried out in such a manner that erosion and water pollution shall be minimized. 4. The sediment trap shall be removed and area stabilized when the remaining drainage area has been properly stabilized. S. All cut and fill slopes shall be 2:1 or flatter. Plate 4.25f Storm Inlet Sediment Trap Source; NRCS M W- a. W W W for Erosion and Sediment Control RemoVai removedSedime nt traps must be shou d show how the site of the sedi{ment trap Iso be graded anstabilized, d stabilized after removal. c_. a 1 M. - -..m ._ ra a- a �vm SIDE VIEV MW Meko MR EA em PM4TS -A' MST BE Hla-e l,,m aim LITE Fmw •B' A B. A N2 rteS AF E m BE ermexr FRONT VIEV (NO SCALE) FRONT VIEV (ALTERNATIVE) TDP VIEV GRAVEL CiMAII�ED IN PERVIOUS4BURLAP BAGSEiLR syorE i IC NET BAGS (1/6 -INCH MESH AND BE APPK-7l XW1 iELY. 24 INO-ES LONG. 12 INCES VIDE PND 6 INCFES Rich to Plate 4.26g Small Sediment Trap Located within a Stormwater Conveyance Channel Source: HydroDynamics, Inc. 4-77 z Florida Erosion and Sediment Control Inspectors Manual. SEDIMENT TRAP GUIDELINES lot H (FT] I 20 aS 3.0 35 5A 4.5 5.0 v rF n eo as as ao 3:0 4 0 4s 104SWC'QdT. SIM SLD'ES ARE NiT TO M STEEPER TK" a SP3LLVAY MS136ED To PASS 10 -YR. 24 -FR PEAK FLDVS l WER EMlNATF9 VD_L!E' . ru n. aTW gY SE9II T DJTET PIPE mrn To STMAC8 EIIZYTZ - CaJVe! anTL NS i0RE Dag , a/, U%cs DETENTION PCIND_ SEDIMENT TRAP/BASIN OVER :'�. a,E .. . seam - .'a._ a a- -a HISTERIC FLOW LENGTH DETAIL = UP Wpnx My ix FL.W LiNGT}i . r BAFFLE DETAIL ELEVAT104 Cr RISER CRESTS CZVATZ:N or naawn an-mn Plate 4.25h Sediment Trap and Basin Guide Source: HydroDynamics, Inc. 70 3 M" 4-78 nt Practices for -Erosion and Sediment Control Chapter 4 -Best Mana eme 4.26 TEMPORARY SEDIMENT BASIL (ES BMP 1.26) Definitlon A temporary basin with a controlled stormwater release structure, formed by constructing an embankment of compacted soil across a drainageway. ` Pur ose To detain sediment-laden runoff from disturbed areas long enough for most of the ` sediment to settle out. Conditions Where Practice Acolles Below disturbed areas greater than 5 acres (2 ha). There"must be sufficient space and appropriate topography for the construction of a temporary impoundment. Thesestructures ` are limited to a useful life of 18 months unless they are designed as permanent ponds by a qualified professional engineer. ` Planning Considerations Effectiveness Sediment basins are at best only 70-80% effective in trapping sediment which flows into them. Therefore, they should be used together with erosion control practices such as temporary seeding, mulching, diversion dikes, etc. to reduce the amount of sediment flowing into the basin. ` Location To improve the effectiveness of the basin, it should be located so as to intercept the largest possible amount of runoff from the disturbed area. The best locations are generally low areas and natural drainageways below disturbed areas. Drainage into the basin can be improved by the use of diversion dikes and ditches. The basin must not bnters the strea e located in live stream but should be located to trap sediment=laden runoff before it eam. The basin should not be located where its failure would result in the loss of life, damage to r adjacent properties, or interruption of the use of public utilities or roads. Multiple Sediment basins may be designed as permanent structures to remain in place after construction is completed. The Stormwater Rule (Ch. 62-25, F.A.C.) makes the use of these structures desirable for stormwater detention purposes. Always leave the bottom of r the sediment basin 6" -12" higher than the eventual bottom of a retention basin. This will ensure removal of accumulated fine sediments which could prematurely clog the retention basin. Wherever these structures are to become permanent, or if they exceed the size limitations of the design criteria, they must be designed as permanent ponds by a qualified professional engineer. Permanent ponds are beyond the scope of this BMP - 4 -79 Florida Erosion and Sediment Control Inspector's Manual Design Criteria Maximum Drainage Area Unless the structure is, designed as a permanent pond by a qualified professional engineer, the maximum allowable drainage area.into the basin shall be 150 acres (61 ha). Basin Capacity The design capacity of the basin must be at least -134 cubic yards or 3600 cubic feet per acre (252 m3/ha) of drainage area measured from the bottom of the basin to the crest of the principal spillway (riser pipe). Sediment should be removed from the basin when the volume of the basin has been reduced to 55 cubic yards per acre (104 m3/ha) of drainage area. The elevation of the sediment clean out level. should be calculated and clearly marked on the riser. In no case shall the sediment clean out level be higher than one foot (30 cm) below the top of the riser. (See Plate 4.26a). Basin Shape To improve sediment trapping efficiency of the basin, the effective flow length must be twice the effective flow width. This basin shape may be attained by properly selecting the site of the basin, by excavation, or by the use of baffles. See Appendix 1.26A for design details. Plate 4.26a Sediment Basin Storage Volumes Source: Virginia DSWC 67 C.Y. AC." DRY STORAGE DEWATERING DEVICE 67 C.Y./ AC. - . " WEr " STORAGE _ SEDIMENT CLEANOUT POINT {"E 3 STORAGE DUCED E- TO4 C.Y.f ACRE) Plate 4.26a Sediment Basin Storage Volumes Source: Virginia DSWC Practices for Erosion. and Sediment Control. Embankment Cross -Section The embankment must have aminimum top width of a feet (2.5 m). The side slopes must be 2:1 or flatter. The embankment may have a maximum height of 10 feet (3 m) if the side slopes are 2:1. If the side slopes are 2.5:1 or flatter, the embankment may have a .. maximum height of 15 feet (4.5 m). Sgil U Design The outlets for the basin may consist .of a combination of principal and emergency spillways or a principal' spillway alone. In either case, the outlet(s) must pass the peak runoff expected from the drainage area for. a 1t0 year storm without damage to the embankment of the basin. Runoff computations shall be based upon the soil cover conditions which are expected to prevail during the life of the basin. Refer to Chapter 3 of • this manual for calculation of the peak rate of -runoff, The spillways designed by the procedures contained in this BMP will not necessarily result +. in any reduction in the peak rate of runoff. If a reduction in peak runoff is needed; the appropriate hydrographs should be generated to choose the basin and outlet sizes. n. To increase the efficiency of the basin, the spillway(s) must be designed to maintain a permanent pool of water between storm events. .. Principal Spillway The principal spillway shall consist of a solid (non -perforated), vertical pipe or box of r corrugated metal or reinforced concrete joined by a watertight connection to a horizontal pipe (barrel) extending through the embankment and outletting beyond the downstream toe of the fill. If the principal spillway is used in conjunction with an emergency spillway, the .. ve a minimum capacity of 0.2 cfs per acre (0.015 m3 /sec. per ha) principal spillway shall ha of drainage area when the water surface is at the crest of the emergency spillway. If no emergency spillway is used, the principal spillway, must be designed to pass the entire w peak flow expected from a 10 -year storm.. See Appendix 1.26A of The Florida Development Manualfor design details. w Design Elevations If the principal spillway is used together with an emergencyy spillway, the crest of the principal spillway shall be a minimum of one foot (30 cm) below the crest of the emergency spillway. if no emergency spillway is used, the crest of the principal spillway shall be a minimum of 3 feet (90 cm) below the top of the embankment. (See Plate 4.26b.) In either r case, a minimum freeboard of one foot (30 cm) shall be provided between the design high water and the top of the embankment. 77 up Florida Erosion and. Sediment Control Inspector's Manua! HIGH WATER STORM ELEV.) O.S CREST OF EMERGENCY i SPILLWAY f RISER CREST 67 C.Y./ AC. :•; !: DEWATERING DRY " STORAGE ..... .... .'r _ DEVICE 67 C.Y./ AC. " WET " STORAGE (CLFANOUT POINT �� STORAGE REDUCED TO 34 C.Y./ ACRE) Design Elevations with Emergency Spillway DESIGN HIGH WATER U2,O6 (25-YR. STORM E1EV:), MINMIN .jr 0. MIN. 1.0' L_ 67 C.Y./ AC. - DRY ' STORAGE 67 C.Y./ AC. - " WET " STORAGE SEDIMENT CLEANOUT • . RISER CREST DEWATERING DEVICE Design Elevations without Emergency Spillway (Riser Passes 26 -Year Event) Plate 4.26b Sediment Basin Schematic Elevations Source: Virginia DSWC 4-82 ►_,z Anti -vortex device and trash rack for Erosion and Sediment Control An anti -vortex device and trash rack shall be attached to the top of the principal spillway to improve the flow of water into the spillway and prevent floating debris from being carried out of the basin. The anti -vortex device shall be of the concentric type. (See Plate 4.26c). See Appendix 1.26A of The Florida Development Manual for design procedures for the anti -vortex device and trash rack. Dewatering: Shall be done in a way that removes the relatively clean waterwithout removing any of the .. sediment that has settled out and without removing any appreciable quantities of floating debris. As a minimum, provisions shall be made to dewater the basin down to the sediment cleanout elevation. This can be accomplishedby providing a hole at the r maximum sediment retention elevation (See. Plate 4.26b). The dewatering hole shall be no larger than 4 inches (10 cm) in diameter. Other means of automatic dewatering are detailed in Appendix 1.26A of The Florida Development Manual. It is also advantageous (but not required). to provide for dewatering. of trapped sediment before clean out. Basin underdrains are generally installed for this purpose. Appendix .. 1.26A contains details for the design of an underdrain system. Base r The base of the principal spillway must be firmly, anchored to prevent: its floating. If the riser of the spillway is greater than 10 feet (3 m) in height, computations must be made to �., determine the anchoring requirements.' As a minimum, a factor of safety of 1.25 shall be used (downward forces = 1.25 x upward forces). ,. For risers 10 feet (3 m) or less in height, the anchoring may be done in one of the two following ways: op 1. A concrete base I's inches (45 cm) thick and twice the width of riser diameter shall be used and. the riser embedded. 6 inches (15 cm) into the concrete. (See Plate 4.26d and Appendix 1.264 ofi The. Florida Development Manual for design details). 2. A square steel piste, a minimum of 114 inch (6.5 mm) thick and having a width equal to twice the diameter of.the. riser..shall be welded to the base of the riser. •The plate �. shall then be covered with 2.5 feet (76: cm) of stone, gravel, or compacted soil to prevent floatation. (See Plate 4.26d and Appendix 1.26A for design details). r. Barrel The barrel of the principal spillway, which extends through the embankment, shall be designed to cavy the flow provided by the riser of the principal spillway with the water level at the crest of the emergency spillway. The connection between the riser and the barrel must be watertight. The outlet of the barrel must be protected to prevent erosion or scour of downstream areas. See Appendix 1.26A for design details. Florida Erosion and Sediment Control Inspector's Manual Plate 4.26c Anti -vortex Device Design Source: NRCS 4-84 Chapter 4 Best, Management Practices for. Erosion. and Sediment Control Plate 4.26e Location of Anti -seep Coilars Source: Virginia CSWC • 4-85 Florida Erosion and Sediment Control Inspector's Manual Plate 4.26f 'Emergency Spillway Source: Virginia DSWC 4-86 Practices for. Erosion and Sediment Control Anti -seep collars Anti -seep collars shall be used. on the barrel of the principal spillway within the normal saturation zone of the embankment to Increase the seepage length by at least 10%, if either of the following two conditions is met: 1. The settled. height of the embankment exceeds 10 feet (3 m). 2. The embankment has a low silt -clay content (Unified Soil Classes SM or GM) and the barrel is greater than 10 inches (25 cm) in diameter. The anti -seep collars shall be installed within the saturated zone. The maximum spacing 4 times the projection of the collar above the barrel. Collars shall between collars shall be 1 o cm) to a pipe joint. Collars ssufficiently not be closer than 2 feet 4 should be placed suciently far apart to allow space for hauling and compacting equipment. Connections between the collars and the barrel shall be watertight. See Plate 4.26e and Appendix 1.26A for design procedure and details. Emergency Spillway The emergency spillway shall consist of an open channel constructed next to the embankment over undisturbed material or properly compacted fill. The spillway shall have a control section at least 20 feet (6 m) in length. The control section is a level portion of the spillway channel at the highest elevation in the channel. (See Appendix 1.26A and plate 4.26f). The primary spillway and the emergency spillway shall both discharge to stabilized outlets. (See Plate 4.26g).. Ca acif The emergeneyspillway shall be designed to carry the. peak rate of runoff expected from a 10 -year storm, less any reduction due to the flow through the principal spillway. See Appendix 1.26A for: design details. r Design elevations " The design high water through the emergency spillway shall be at least one foot (30 cm) below the top of the embankment. The crest of the emergency spillway channel shall be at least one foot (30 cm) above the crest of the principal spillway. s Location an The emergency spillway channel shall be located to avoid fill material. if consucted on fill, the fiilwill be properly compacted in lifts. The channel shall be located so as to avoid sharp turns or bends. The channel shall return the flow of water to a defined channel an downstream from the embankment. 4-8 Florida Erosion and Sediment Control Inspector's Manual SEDIMENT RISER KITH _ 15A51 TRASH RACK STABILIZED OUTLET PLAN `-TRASH RACK STABILIZE T C�R� cmaRGENGY SPILLFNAY KITH VEGETATION % 1 FT .,,. FRE=BOARD T i �ENGMESZED _ - SPILLMNY FT 7 1 SELEGTID FILL BARREL I Imo,` �`i`"AG STI STABILIZED DRAINAG` ANi f - COLLAR 7YP. of 3 SECTION NOTES. 1. THE T'M'ORARY IMENT 5ASIN, D5516NED BY A WALIFiED PROF�551aNAL, IS REaUIRi=D FDR DISTURBED AREAS GREATER T+JAN 5 A4,RE5 NITHIN A DRAINAGE AREA LESS THAN 100 ACAS. • 2. THE �5EWIMENT BASIN SHILL BE REMOVE17 K17H- IN 3 TEARS. Plate 4.26g Sediment Basin Source; Erosion Draw 488 Best Erosio Maximum velocities The maximum allowable velocity in the emergency spillway channel will depend upon the type of lining used. For vegetated linings, allowable velocities are listed in Table 5.35a (STORMWATER CONVEYANCE CHANNEL - Section 5.35 - ES SMP 1.35), For non -erodible linings, such as concrete or asphalt paving and riprap, design velocities may be increased. However, the emergency spillway channel shall return the flow to the natural channel at a non -eroding velocity. See Appendix 1.26A for design details. Stabilization of the Embankment and Basin r The embankment of the sediment basin shall be temporarily seeded within completion as perTEMPORARY SEEDING -Section 6.65 (ES BMP 1.65) r required in the basin, side slopes should not be steeper than 2:1. 15 days after ifs if excavation is Cleanout r Sediment shall be removed from the basin when the capacity is reduced to 55 cubic yards per acre (104 m'lha) of drainage area. This elevation should be clearly marked; preferably r sin shalt state the methods for disposing of on the riser. Plans for the sediment. ba sediment removed from the basin. Possible alternatives are the use of the material in fill areas on-site or removal to an approved off-site dump. Finaremoval r. Sediment basin plans shall show the final disposition of the sediment basin after the upstream drainage area is stabilized. The plans shall specify methods for the removal of excess water lying over the sediment, stabilization of the basin site, and the disposal of any excess material. Sediment shall not be flushed into the stream or drainageway. Safe VE Sediment basins are attractive to children and can be very dangerous. Therefore, they should be fenced or otherwise made inaccessible to persons or animals unless this is ,. deemed unnecessary due to the remoteness of the site or other circumstances. Strategically placed signs around the impoundment reading "DANGER -QUICKSAND" should also be installed. In any case, local ordinances and regulations regarding health r and safety must be adhered to. Construction Specifications r Site Pry an Areas under the embankment and any structural works shall be cleared, grubbed, and stripped of topsoil to remove trees, vegetation, roots, or other objectionable material. In order to facilitate cleanout and restoration, the pool area (measured at the top of the +� principal spillway) will be cleared of all brush and trees. INFLOW D D 2 Florida Erosion and. Sediment Control NO SCALE w 7' spector's Manual L = TOTAL DISTANCE FROM THE POINT OF INFLOW AROUND THE BAFFLE TO THE RISER. SHEETS OF V x as X 1/T' EXTERIOR PLYWOOD OR EOUIVALENT RISER CREST ELEVATION 4�SQUAE MIN, ORSo ROUND. SET AT LEAST 34 INTO THE CROUNO. e' I Plate 4.26h Example Plan Views of Baffle Locations in Sediment Basins Source: NRCS t Practices for! Sediment Contro Chapter 4 -Best Managemenl . r cutoff Trench For earth fill embankments, a cutoff trench shall be excavated along the centerline of the dam. The minimum depth shall be 2 feet (60 cm): The cutoff trench shall extend up both abutments to the riser crest elevation. The minimum bottom width shall be 4 feet (1.2 m), " but wide enough to allow operation of compaction equipment. The side slopes shall be no steeper. than 111. Compaction requirements shall be the same as those for the embankment. The trench shall be drained during the backfilling -compacting operations. Embankment The fill material shall be taken from approved borrow areas. It shall -be clean mineral soil, free of roots, woodymegetation, oversized stones, rocks, or other objectionable material: Areas on which fill is to be placed shall be scarified prior to placement. of fill. The fill material should contain sufficient moisture so that it can be formed by hand into a bail without crumbling. if water can be squeezed out of the ball, it is too wet for proper compaction. Fill material will be placed in 6 to 8 inch (15 to 20 cm) continuous layers over the entire length of the fill. Compaction shall be obtained by routing the hauling equipment over the fill so that the entire surface of the fill is traversed by at least one wheel or tread track of the equipment, or by using a compactor. The embankment shall be constructed to an elevation 10% higher than the design height to allow for settlement if compaction is obtained'with hauling. equipment. If compactors are used for compaction, the overbuild may be reduced to not les s 't an Principal Spillway The riser of the principal spillway shall be securely attached to the barrel by a watertight connection. The barrel and riser shall be placed on a firm compacted soil foundation. The base of the riser shall be firmly anchored according to design criteria to prevent its floating. Pervious material such as sand, gravel or crushed stone shall not be used as backfill around the barrel or anti -seep collars. Fill material shall be placed around the pipe in 4 inch (10 cm) layers and compacted by hand at least to the same density as the " embankment. A minimum of two feet (60 cm) of fill shall be hand -compacted over the barrel before crossing it with construction equipment. Emergency Spillwa The emergency spillway should not be constructed over fill material. Design elevations, widths, entrance and exit channel slopes are critical to the successful operation of the spillway and should be adhered to closely during construction. to Vegetative Stabilization in The embank ment on within nd 15cdaysllofay of the sediment ompletioIn of the bas nshall perTEMPORARY stabilized with to temporary 9 SEEDING - Section 6.65 (ES BMP 1.65). Florida Erosion and Sediment Control Inspector's Manual EMERGENCY SPILLWAY CREST DESIGN HIGH WATER h r--1 ANTI—SEEP ANTI—VORTEX COLLARS DEVICE or y RISER - BARREL: x �D CONCRETE BASE L H = HEAD ON PIPE THROUGH EMBANKMENT h _ HEAD OVER RISER CREST L = LENGTH OF PIPE THROUGH EMBANKMENT DP= DIAMETER OF PIPE THROUGH EMBANKMENT D,= DIAMETER OF RISER Plate 4.261 Principal Spillway Design Source: Virginia DSWC 4-92 O .. _. .. _. Chapter -Best lvlana ementPractioes' .ot rosion,an - Erosion and Sediment Control The construction of the sediment basin shall be carried out in a manner such that erosion and water pollution are minimized downstream. w Final Disposal When tem ora structures have served their intehded purpose and the contributing drainage area has been properly stabilized, the embankment and resulting sediment deposits are to be leveled or otherwise disposed of according to the approved pollution control plan. Maintenance ` The embankment of the basin should be checked regularly to ensure that it is structurally sound and has not been damaged by erosion or construction equipment. The emergency spillway should be checked regularly to ensure that its lining is well established and erosion -resistant. The basin should be checked after each runoff -producing rainfall for sediment cleanout: When the sediment reaches the cleanout level mark, it shall be r. removed and properly disposed of. Information to be Submitted for Approval Sediment Basin designs and construction plans submitted for review.to the appropriate regulatory agency shall include: ` 1. Specific location of the dam. 2. Plan view of dam, storage basin and emergency spillway. 3. Cross-sections and profiles of dam, principal spillway and emergency spillway. 4_ Details of pipe connections, riser to pipe connection, riser base, anti -seep collars, trash rack;. and anti -vortex device. M 5. Runoff calculations for 10 -year frequency storm. g. Storage Computations a. Total required b. Total available rr c, Level of sediment at which cleanout shall be required; to be stated as a distance from the riser crest to the sediment surface. 7. Calculations showing design of pipe and emergency spillway. Florida Erosion and Sediment Control Inspector's Manual LEVEL PORTION CREST AND CONTROL SECTION — FLOW _� 0 Em EMBANKMENT T Plan View LEVEL I LEVET. OR I GREATER APPROACH C14ANNE L Profile Along Centerline EXIT SECTOR NOTE NEITHER THE LOCATION NOR AUONMENT OF THE CONTROL SECTION HAS . TO COINCIDE WITH THE CENTERLINE OF THE DAM. X— LENGTH OF EXIT CHANNEL WT SECTOR Cross -Section at Control Section Plate 4.26j Excavated Earth Spillway Source: NRCS 494 4:- Best. Management Practices for Erosion: and -Sediment Control... . Concrete Base for Embankment 10' or Less in Height %s Ss Steel Basefor Embankment 1o' or Less in r+eig"L Plate 4.26k Riser Pipe Base Conditions for. Embankments Less than 10 Feet High Source: Virginia DSWC Florida Erosion and Sediment Control Inspector's Manual kR 10 al Or. 1 e. GAGE AS THE WK N w R IS WEO PAIRS, 9.OREO HOLM AT r GG SECTION 8=3 ELEVATION OF UNASSEMBLED COLLAR Y MIN DETAIL Corrugated Metal SIZE AND SPACING OF SLOTTED OPENINGS SHALL BE THE SAME AS SHOWN FOR CM COLLAR. USE RODS AND LUGS TO CLAMP BANDS SECURELY TO PIPE. 1Y tRNA I MAO OF 2 NaICV. PWS I1 Thor .E l 9101 " ORAWIIr+• 0 C=M OR B7N A 80 j 1 1/e NOTE FOR BAWDS AND COLLARS: 1� MODIFICATIONS OF THE DETAILS SHOWN MAY BE USED PROVIDING 1 ,1le EQUAL WATERTIGHTNESS IS MAWAINED AND DETAILED DRAWINGS ARE SUBMITTED AND POvED By THE ENGINEER PRIOR TODE ISOMETRIC VIEW war �L— ,lL wsca�""HtEr n IC =u -m MRO AM 11S VEIOFD IRfl1 A COIIIROIOO" YSIO. NOTE: SLOOTTR DE A OIRSDETAIL F FABRICATION AND NGTM SEW DENSIONS•AROVE M GAGES. vOOWJ 10 -eE •evrka ro GFGiIE1t OF NOTE TWO OTHER TYPES OF ANTI—SEEP COLLARS ARE: 1!]1G1. PPE HYO .. _ 1 EPT SHOP WELDED TO SHORT AI� TS=nON OF O UPPM THE PIPE AND CONNECTED WITN- CONNECTING BANDS TO. THE. PIPE.. PARTIAL ELEVATION z MUM WITH R¢3 FEBAARNCDT SPCDT HKHORIIZOOHTA6LLLYUND THE PIPE AND VERTICALLY. DETAIL Helical Pipe Plate 4.26L Anti -seep Collar Details Source: NRCS 3. UNASsEYBLED COLLARS SHALL BE MARKED BY PANTING OR TAGGING TO IDENTIFY MATCHING ROTES FOR COl1AR5i PAIRS, 1. ALL MATERIALS TO BE IN ACCORDANCE WITH 4. THE LAP RE7WEEN THE TWO HALF SECTIONS AND CONNECTING SAND CONSTRUCTION AND CONSTRUCTION MATERIAL ANO BETWEEN THE PIPE SHALL BE CAULKED WITH ASPHALT MASTIC AT SPECIFICATIONS. 2 WHEN SPECIRED ON THE PLANS, COATING OF TtME'or INSTALLATION. BE FURNISHEDWITH O NR ON(C ACCORDANCE WITH MATERIAL 5. 1 /Y IAME>ER R �i STANDARD TA CONSTRUCTION CONSTRUCTION LUGS FOR CONNECTING COLLARS TO PIPE. SPECIFICATIONS. DETAIL Corrugated Metal SIZE AND SPACING OF SLOTTED OPENINGS SHALL BE THE SAME AS SHOWN FOR CM COLLAR. USE RODS AND LUGS TO CLAMP BANDS SECURELY TO PIPE. 1Y tRNA I MAO OF 2 NaICV. PWS I1 Thor .E l 9101 " ORAWIIr+• 0 C=M OR B7N A 80 j 1 1/e NOTE FOR BAWDS AND COLLARS: 1� MODIFICATIONS OF THE DETAILS SHOWN MAY BE USED PROVIDING 1 ,1le EQUAL WATERTIGHTNESS IS MAWAINED AND DETAILED DRAWINGS ARE SUBMITTED AND POvED By THE ENGINEER PRIOR TODE ISOMETRIC VIEW war �L— ,lL wsca�""HtEr n IC =u -m MRO AM 11S VEIOFD IRfl1 A COIIIROIOO" YSIO. NOTE: SLOOTTR DE A OIRSDETAIL F FABRICATION AND NGTM SEW DENSIONS•AROVE M GAGES. vOOWJ 10 -eE •evrka ro GFGiIE1t OF NOTE TWO OTHER TYPES OF ANTI—SEEP COLLARS ARE: 1!]1G1. PPE HYO .. _ 1 EPT SHOP WELDED TO SHORT AI� TS=nON OF O UPPM THE PIPE AND CONNECTED WITN- CONNECTING BANDS TO. THE. PIPE.. PARTIAL ELEVATION z MUM WITH R¢3 FEBAARNCDT SPCDT HKHORIIZOOHTA6LLLYUND THE PIPE AND VERTICALLY. DETAIL Helical Pipe Plate 4.26L Anti -seep Collar Details Source: NRCS No 7 IM 4 Best for POLYETHYLENE CAP . PROVIDE ADEQUATE . ' ST{tAPPING DEPTH _ VARIES AS REQUIRED TACK WELD PERFORATED POLYETHYLENEFOR ORY VtESG(SETEBG4LCULATIOENS IN STORAGE APPENDIX 3.14—A) 1 WET . • FERNCO-STYLE ' COUPLING STORAGE DEWATERING GRIFICE, �HEDUUE 40 STEEL STUS —FOOT WII CORRUGAT@ MaAL RISER SC DNMETER VARIES (SEE CALCULATIONSNltU)A APPENDIX 3.14-0 See Plate 4.26m Perforated Pipe Sediment Basin Dewatering Device Source: Virginia DSWC Qean Masonry sand Rrear Welded or 2 4' Pedaaled Pleads placed Mortared Jaud pullet Y Minimarn with Pedarallons Dawn Bed;inrg ,� Place F over ripe •: ,d' P Y Ris er 1n 4ltrdmm un car en Orasa-s n Oraue piinTr pe inTmeh ErreratalanaM Edge at Pod r n n (] RES" NOTE Se 15 b 2S y Met= lad plre L^. Trerslt .. Plan Yew SQ=M W Be*, _ pnaiile — �— E%Mmirrum Grade -- Plate 4.26n Dewatering a Sediment Basin with Subsurface Drain Source: NRCS rr Florida Erosion and Sediment Control Inspectors Manual This page left intentionally blank 4>98 )ter 4 - Best Management_. Practices for -Erosion: an( 4,30 TEMPORARY SLOPE DRAIN .. (ES BMP 1,30) Definition A flexible tubing or conduit extending from the top to the bottom of a cut or fill slope. " Purpose To temporarily convey concentrated stormwater runoff safely down the face of a cut or fill slope without causing erosion problems on or below the slope. Conditions Where Practice Applies On cut or fill slopes before permanent stormwater drainage structures are installed. Planning Considerations There is often a significant lag between the time a cut or fill slope is completed and the time a permanent drainage system can be installed. During this period, the slope is usually not stabilized and is particularly vulnerable to erosion. This situation also occurs on slope construction which is temporarily delayed before final grade is reached. Temporary slope drains can provide valuable protection of exposed slopes until permanent drainage structures can be installed. Earthen Dike Corrugated'Metal (ComPacted) Extension Collar �—A Waterproof Seal ➢+6" 24:1 Protection / �iIII .IljP' Standard Flar / �llre — End Section Section M Plate 4.30a Temporary Slope Drain Source: Virginia SWCC r Florida Erosion and Sediment Control Inspectors Manual �uu� � DIVERSION DIKE 0 Y J Q IL IL Q STANDARD 0 - ICTAL END F SECTION STRAP o� •° ° 00 o�A�Pj�. 9STA51LIZED -- �,, OUTLET FLEXIBLE VCk*01RAIN OR PLASTIC PIPE OR `:OP��O•P4AcP SOCK' SElNN FILTER 666660 po'o; lI��JJSS22� FAO, �'•Oa ERI.p' ISLAND OVER KO� - INLET J . PLAN VIEW DI Pl E VSTRAP OVERERINLET COLLAR 5TASIL17E OUTLET Plate 4.30b Slope Drain Source: Erosion Draw 4-100 Chapter4- Best Mane ament Practices:'. or rosion When used in conjunction with diversion dikes., temporary slope drains can be used to convey stcrmwater from the entire drainage area above a slope to the base of the slope without erosion. it is very important that these temporary structures be installed properly since their failure will often result in severe gully erosion.. The entrance section must be securely entrenched, all connections must be watertight, and the conduit must be staked securely. Desia_ n criteria Drainage--- Area The maximum allowable drainage area per drain is 5 acres (2 ha). Flexibles uit` 1, The slope drain sha{I consist of heavy duty.flexible material designed for this purpose. The diameter of the slope drain shall be equal over its entire length. Reinforced hold-down grommets shall be spaced at 10 foot (3 m), maximum intervals. 2.. Slope drains shall be sized according to the folipwing table: Table 4.30a SIZE.OF SLOPE DRAIN Maximum Drainage Area (Acresl 0.5 1.5 2.5 3.5 5.0 Piae Diameter in. 12 18 21 24 3p Overside drain ort slopes, an open top chute may be used in place of a pipe. For small flows and/or sh (See Plate 4.30c). Entrance -Sections The entrance to the slope drain shall consist of a Standard FDOT "Flared End -Section for Metal Pipe Culverts." Extension collars shall consist of 12 inch (30 cm) long corrugated metal pipe. Watertight fittings shall be provided. (See Plates 4.30d & 4.309). Florida Erosion and Sediment Control Manual. MAX n1 Y_ !J IL 0 0. OPEN TOP CHUTE o •9 a. TAPERED INLET 0 ANCH o'CA o; D15GHARGE 70 5TABILIZED WATER. LU COURSE Y n 0 v 0 PLAN. VIEW DIKE b° MIN. OPEN TOP CHUTE i ANCHORS AT 10' 04 WITH MIN. OF 36° EMIMVMa T SECTION o Plate 4.30c Overside Drain Source: Erosion Draw 4-102 r Chapter 4. Best Management. Practices for Erosion and. Sediment. Control �® Dike Design 1. An earthen dike shall be used to direct-stormwater runoff into the temporary slope drain and shall be constructed according to the practice entitled DIVERSION - r Section 5.18 (ES BMP 1.18). (See Plate 4.30a) 2. The height of the dike at the centerline of the inlet shall be equal to the diameter of the pipe (D) plus 6 inches (15 cm). Where the dike height is greater than 18 inches (45 cm) at the inlet, it shall be sloped at the rate of 3:1 or flatter to connect with the remainder of the dike. (See Plate 4.30a) Outlet Protection .. The outlet of the slope drain shall be protected from erosion according to the practice entitled OUTLET PROTECTION.- Section 5.36 (ES BMP 1.36). (See Plate 4.30b). W Construction Specifications W M 177 W 1. The measure shall be placed on undisturbed soil or well -compacted fill. 2'. The entrance section shall slope toward. the slope drain at the minimum rate of Yzinch per foot (4 cm/m). 3. The soil around and under the entrance section shall be hand -tamped in 8 inch (20 cm) lifts to the top of the dike to prevent piping failure around the inlet. 4. The slope drain shall. be securely staked to the slope at the grommets provided. 5. The slope drain sections shall be securely fastened together and have watertight fittings. Maintenance The slope drain structure shall be inspected weekly and after every storm, and shall have repairs made if necessary. The contractor should avoid the placement of any material on and prevent construction traffic across the slope.drain.. Plate 4.30d Flared End Section Schematic Source: VDH&T Road Desions and Standards A 4r)3 C ' Plan Eiees[Sw Plate 4.30d Flared End Section Schematic Source: VDH&T Road Desions and Standards A 4r)3 Florida Erosion and Sediment Control inspector's Manual Alternate Connection Thr o Toe plate, ,here needed, to be Punched to match holes in skirt lip. 3/8" gaty. bolls to be lurnisrAd Length of toe plate is W* 10'for 12'1030'dka.Pipe and W�22" for 36' to 60' dio, pipe. skirt secilw for 12' to 30' ala. pipe to be made in one piece. Skirt Sem len for 36" to 540 dIM PIPs may be mode tram two sheets joined by rlYM inq ar bottinq an center I&M,60"may be constructed in 3 pmceL Connector Section, carrier Ptme ano Toe Plate to be sant. sleet 1hicFn as skirt. Ern -sections and fittings ore 10 be golvanixed vied or aiunenurn al{oy for use with like pipe. } I L � I �Agprvx 2 Sg , l sly l '.I f 1 7. i" Typical Cross -Section -r 8" Toe —Plot* Thl 3 6A izoso FLARED END -SECTION (Continued.) PIPE DIA , SHEET THICK- NESS DIMENSIONS A 8 H L W IMT07 Mal i` "T C I " 4" " I t a" I a" 15" I .064" 7" I e" i fi" 26' ! 30' I 24" le" 064" B" t t B' f I' ! a" 24" .D64' 10" 13�' fi' 1� a IN ! ae" I 24" 30" .079" 12" 164 B.'. i 5 f" 00"" 24" 3647-579K 14" 1 19" 9" 6" 1 7 1 3" 42 JOS 16" 22" 1 12V 6 9' I E4 36" 54 109" I 60�e l E1 IBI 3= ! I Z t B ! 36' Plate 4.30e Flared End Section Specifications Source: VDH&T Road Designs and Standards 4-104 liter 4 Best Management Practices. fat Erosiort,and-pediment Control 4.38 TEMPORARY CHECK DAMS Definition Small temporary dams constructed across a swale or stormwater conveyance channel. Pur ose To reduce the velocity of concentrated stormwater flows, thereby reducing erosion of the Swale or ditch. This practice also traps small amounts of sediment generated in the ditch itself. These sediments will require periodic removal. However, this is not a sediment trapping practice and should not be used as such. Conditions JVhere Practice Apples This practice is limited;to use in small open channels which drain 10 acres (4 ha) or less. It should not be used in a live stream. This practice is especially applicable to sloping sites where the gradient of waterways is close to the maximum for a grass lining. Some specific applications include: 1. Temporary ditches orswales which, because of their short length of service, cannot receive a non -erodible lining but still need some protection to reduce erosion. 2. Permanent ditches or swales which for some reason cannot receive a permanent non -erodible lining for an extended period of time. Either temporary or permanent. ditches or swales which need protection during the establishment of grass linings.. Ptannino Considerations .. Temporary check dams can be constructed of filter fence or straw bales forveryshortterm applications; or either stone or logs for longer or permanent applications. Filterfence and straw bale check dams are economical to purchase and simple to install. Log.check dams ,. are economical as for material costs, since logs can usually be salvaged.from clearing operations. However; log :check dams require more time and hand -labor to install. Stone for check darns, on the other hand, must generally be purchased. However, this cost is offset somewhat by the ease of installation.. Specifications No formal design is required for a check dam; however, the following criteria should be adhered to when specifying check dams. r Erosion and Sediment Control Manual m m m L PLAN VIEW 4" TO. b' L065 4' MAX 18° TO 24' VIEW LOOKING UPSTREAM L' = THE PMTANCE SUCH THAT POINTS 'A' AND 'B' ARE OF EQUAL ELEVATION ILI POINT 'A' POINT '8' SPACING BETWEEN CHECK DAMS NOT: KEY THE EH05 OF THE CHECK DAM INTO THE CHANNEL BANK. LO&5 SiiALL BE PRESSUI;M TREATED IF 6R4IDE 5TA$ILIZATION 5TK4TUR2 15 INTENDED TO BE PERMAI%N . Plate 4.38a Log Check Dam Source: Erosion Draw 4-106 ,ter4--Best- Management- Practices for The drainage area of the ditch or swale being protected should not exceed 10 acres (4 ha). The maximum height of the check dam should be 2 feet (60 cm). The center of the check • dam must be at least 6 inches (15 cm) lower than the outer edges. (See Plate 4.38a) The cross-sections of the dams should be as shown in Plates 4.38a through 4.38d, respectively, for logs, stone, straw bales, and filter fence. The maximum spacing between the dams should be such that the toe of the upstream dam is at the same eievation as the top of the downstream dam. (See Plate 4.38c). LooLoa ch� eck dams should be constructed of 4 to 6 inch (10 to 15 cm) logs salvaged from clearing operation site, if possible. The logs should be embedded into the soil at least 18 inches (45 cm). The 6 inch (15 cm) lower height required at the center can be achieved ` either by careful placement of the logs or by. cutting.the logs after they are in place. (See Plate 4:38a). Logs and/or brush should be placed on the downstream side of the dam to prevent scour during high flows. ` Stone check dams should be constructed of FDOT' No. 1 Coarse Aggregate (1.5 to 3.5 inch stone) (4 to 9 cm). The stone should be placed according to the configuration in Plate 4.38b. Hand or mechanical placementwiil be necessary to achieve complete coverage of the ditch or swale and to insure that the center of the dam is lower than the ends. (See Plates 4.38b & 4.38e) r Straw bale and filter fence check dams shall be installed as per STRAW BALE BARRIER Section 4.05 (Channel Flow Applications) (See Plates 4.38c & 4.38f) and SILT FENCE - Section 4.06 (Channel Flow Applications) (See Plate 4.38d). Sediment Removal While this practice is not intended to be used primarily for sediment trapping, some sediment will accumulate behind the check dams. Sediment should be removed from behind the check dams when it has accumulated to half of the original height of the dam. _ Removai Check dams must be removed when their'useful life has been completed. In temporary ditches and swales, check dams should be removed and the ditch filled in when it is no longer needed. In permanent structures, check dams should be removed when a permanent lining can be installed. In grass -lined ditches, check dams should be removed when the grass has matured sufficiently to protect the ditch or swale. The area beneath ` the check dams should be seeded and mulched. or sodded (depending upon velocity) immedlately after they are removed. ` If.stone check dams are used in grass -lined channels which willbe mowed, care should be taken to remove ail the stone from the dam when the dam is removed. This should include r, any stone which has washed downstream. Since log check dams are embedded in the soil, their removal wilt result in more disturbance of the soil than will removal of stone check dams. Consequently, extra care should be taken to restabilize the areawhenlog dams are ,w used in permanent ditches or swales. 4- Erosion and Sediment Control Inspector's Manual VIEW LOOK1Nd UPSTREAM NOTE: K y 5TONE wT0 TFE DITGi-! 5AW5 AND EXTEND IT BEYOND THE ANTS A MINIMUM OF IS" TO FREVENT OVA FL.ON AROLMD DAM. SECTION A - A L' -He 015TANG= SUCH THAT FOINT5 'A' AND 'S' ARF OF EGUAL MLENATION. SPACING BETWEEN CHECK DAMS Plate 4.38b Rock Check Dam Source: Erosion Draw 4-108 4' - Best EN6 POIMS'A' N I BE HIVR THAN L& VIDE LINE POINT a OVERLAP SME &qZS [N FLOV 1Ljj�;E BAUcSiO PREVENT G*S �. �,, a a wit a ` 18 3Z". EEY ¢ Z - � 7 5°!ES 1a LR. < 1 w -3s z•' 35 SO 3" END POINTS MAM KIS BE HI I Z � P1Sl£S Lz°Z1i ff VPiFit THAN FILEN LkE POINT 7G -ER jr A A�� li I. I'1�1� U ILL16f' ,5 10 it �S➢, 0 1 IUWiLY I IlAi PIAV'i PMNT air is �Y LEVEL V1Tr: n -C L= 50 F . aEVATIDT DF ThE l i i 4 � NARROW CHANNELS 1 WIDE CHANNELS Plate 4.38c .Straw Sale Check Dam. Source: HydroDynamics, Inc. A Ann Erosion and Sediment Control Inspector's Manual Maintenance Check dams should be checked for sediment accumulation after each significant rainfall. Sediment should be removed when it reaches one-half of the original height or before. Regular inspections should be made to insure that the center of the dam is lowerthan the edges. Erosion caused by high flows around the edges of the dam should be corrected immediately. Silt Flow Note: Spacing for Type IIL Fence to be in accordance with Chart I, Sheet 1 of 3 and ditch installations at drainage' structures Sheet 2 of 3. Type DI Silt Fence Points A Should be Higher than Point 8 Drainageway installation (Front Elevation) Plate 4.38d Silt Fence Check Dam Source: installation of Straw and Fabric Filter Barriers for Sediment Control Sherwood and Wyant 4-110 rhantar4- Best. 0=50 EONS FILM FLOVLSE S1tFc DF STRI CTUrE Fr/FT) r CF ROD( nay =i 020 Ms aic �7 M^.T1 VA a7TR OVER ROCK (M7 -E9 3 as CO 03 LO L3 t.9 6 14 Is 20 26 3.4 RECOMMENDED ROCK SIZE & FLIN DEPTHS 0.35 FT/FT OR FLATTER r DrH KEL.q FLOW LINE SI CaARSEA and END PMTS v LAl� MIST BE 2D M7 116 11 ft MINIM, DEpTH cF caiRSE7 • 15 FEET R•■ 0 1 ■ iDIFFERENCE V•• i i • t FRONTVINDII-13 17MCH FLM LM IS .5 FEET SIDE VIEW Plate 4,38e Rock Check Dam Details Source: HydroDynamics, Inc. 4.111 Florida Erosion and Sediment Control Inspector's Manual loom PONDING VIEW LOOKING UPSTREAM HEIGHT 4I 'L.''= Tt{E DISTANCE SUCH THAT POINT5'C!:. ANO POINTS 'D" ARE Of EQUAL ELEVATION. POINT 'C' POINT 'D' EMBED STRAH BALE 4" MIN. INTO SOIL. SECTION .A - A SPACING BETWEEN CHECK DAMS NOTFS= 1. Et E2 BALES 4" INTO -TM SOIL ANG "KZ'r' BALES INTO THE CHANNEL. BANKS. 2. POINT 'A' MUST 5E HIGHER- THAN POINT B'. (eFILLti4Y HEIGHT) Plate 4.38f Straw Bale Check Dam Details Source: Erosion Draw U OPTIONAL ENERDY D1551PATOR 3. PLACE BALES.PERPENDICUL.AR TO TriE FLON KTH ENDS TIGHTLY ABUTTING. USE 57RAN,,ROCK5 OR FILTER FABRIC TO FILL ANY GAPS AND TAMP BACKFILL MA'TRIAL TO PREN/ENT ER0510N OR FLON AROUND THE BALES. 4. SPILLNIAY HEIGHT SHALL NOT =XC 24".' 5. INSPECT AFTER EACH 51GNIFICANT STORM, MAINTAIN AND REPAIR PROMPTLY. 4-112 Chapter 4 - Best. Management Practices for -Erosion -.a 4.40 DEWATERING Definition Lowering the water table by means of pumping. Pur ose To allow the construction of structural and stormwater improvements by removing water from excavation areas and allowing construction by conventional "dry" methods. Plannirio Considerations.. 40 The major planning consideration in dewatering is disposal of removed water. Volume; quality, and topography are the factors governing the method and destination of removed water. Discharge from well -point dewatering is relatively clear except for the initial discharge after installation or inactivity. Water pumped from a sump hole is thoroughly sediment laden and must always be treated. Turbid water must either be filtered before it is leaving the site or must be impounded onsite and allowed to settle. In fiat terra sometimes long., sometimes more economical to impound relatively dean water rather than pip distances to a receiving water body. .. Specify ns The two most common meth ods .of dewatering used in Florida are well'point systems and ,,. sump pumps. Awell-point system consists of. one or more rows of small 2" (5 cm) collector pipes which are jetted vertically into theground near the proposed excavation. The small pipes are connected by a larger 6" (15 cm) manifold.pipe which is connected to thdempW ng and discharge line. The sump method is simply a hole in the ground with a pump all of the water flowing into the hole. Excess water is conveyed to the sump by open ditches or perforated pipes embedded in sand or gravel. r Sumps and Ditches ,. The water table is lowered by ditching and conveying water to a lowered sump hole. Water pumped from a sump hole is usually heavily laden with sediments. Water flowing over disturbed and saturated ground detaches and transports all sizes of soil particles into the ., sump pit to be sucked up by the pump. Saturated liquid soil (mud) is also drawn into the pump. The discharged water must be treated.before release into a receiving water body or stormwater system. Placing haybales around the pump intake or outlet is not sufficient effective settling .. filtration. by itself. Turbid water must either be impounded long enough for of fines, or filtered through a temporary filter or sediment tank. Initially the water may percolate freely into the ground, however this will diminish as the fine particles settle and •. clog the surface layer of soil. In situations which preclude the use of filtration or settlement facilities, and turbid water is discharged directly into a water body, a suitably designed floating turbidity barrier must be used. Note that this method does not remove any • sediments, it merely allows for dilution to lower the turbidity level. rosion and Sediment Control Inspector's Manual Horizontal Wells This system also consists of a series of ditches leading to a sump hole or pump. The ditches are filled with sand or gravel surrounding a perforated pipe. A geotextile may also be used to prevent excessive migration of fines into the system. The discharged water must be treated before release as described above. Well -point Systems The well -point system is the preferred system for dewatering and should be used whenever possible. The initial discharge yields the sediments displaced by the installation of the small collector pipes. This can be directed into the excavation, a small settling or filtration facility, or larger temporary impoundment. Thereafter the water is generally clear ground water and may be discharged into a receiving water body prodided that there is suitable conveyance. Maintenance 1. Any water impoundment must be inspected daily to preventfailur e of dikes, berms, or control structures. Minor problems should be repaired at once. Major problems will require a redesign and plan modification. 2. Any filtration device must be inspected and cleaned frequently. The discharge should be monitored daily and whenever the pumps are started. Inspection and maintenance of the system are best performed when the facility is dry. The first signs of diminished performance should be an alarm that maintenance is required. If the facilitywill no longer drain itself, the untreated water must be pumped back to its source, rather than by-passing the facility and discharging to the water body or stormwater system. 3. Floating turbidity barriers shall be maintained as per FLOATING TURBIDITY BARRIER - Section 4.45 4-114 4,45 FLOATING TUREMOITY BARRIER Definition • bed area A floating, geotextils material which minimizes sediment transport from a distur adjacent toor within a. body o#water. land Pur ose.. . w provide sedimentation os on and sediment controls cannot be usedon for a watercourse from , or from dredging or where convention filling within the watercourse... Conditlons Where Practice Ap 1►es !on: into: the Watercourse where in rus b Apphcable o actio t esl'and has tbeen atercourses permuted a d subsequ nt sediment movemen s construction unavoidable.: . . '� Planning Considerations n of MeRt- in time, the -term suspensio Soil lossaatsedimentrmay t avel large distances and aff ctwidesp ead. areas. turbidity suspend .. . curtain enough'Sesidenceaime so that soli pa'rtcd con '!es wdiit all out�tof suspension.and nod arena t travel to r other areas... I the ons. Turbidlty curtain types thmust be selected based onond,flor�a condittid 1i waterco�ursee waterThe +� body, whether it be a flowing channel; lake, p specifications, contained within this, practice pertain to minimal and moderate flow conditions where the velocity of flgw.may reach,5 feet (1.5 m) per second (ora 'current of approximately 3.knots)..Forsituations whee.there are greaterflowweloc�ties`or currents; a qualified engineer and product manufacturer should be consulted: ter vement in channel ow M Consideration must ourtains are not.designed to act asv I en to the direction . of awater inipoundnie t dams and situations. Turbidity cannot be expected to stop the flow of a significant volume of water. They. st designed and installed to trap sediment, not to half the movement of water itself; Inmost situations, andjtjuLr�i i curtains should not be installed across channel flaws: he olume of water be made to ow In tidal or contained (thin thetcurtain er o ato ctaange provisionsmust the tbottom of thecurtain{ain vs weighted and con external anchors a.re firequentlyadded, the voiume ofwater contained within; the curtain will " . be much greater at high tide addition to allowing s low ti e ng s ackid in he curtain toures must arise and wateken to r bnt e curtain from submerging, g. must be ailowedto flow through the curtain if.the curtain is to remain hldved by s roughly the same " placpart of the e and maintain thwoven filterame fabric. abric. he. e. fabriythisc allows the water to. assgthro through the curtain -from a_ heavy Florida Erosion and Sediment Control Inspector's Manual curtain, but retains the sediment particles. Consideration should be given to the volume of water that must pass through the fabric and sediment particle size when specifying fabric permeability. Sediment which has been deflected and settled out by the curtain may be removed if so directed by the on-site inspector or the permitting agency. However, consideration .must be given to the probable outcome of the procedure - will it create more of a sediment problem by resuspension of particles and by accidental dumping of the material by the equipment involved? It is, therefore, recommended that the soil particles trapped by a turbidity curtain only be removed if there has been a significant change in the original contours of the effected area in the. watercourse. Regardless of the decision made, soil particles should always be allowed to settle for a minimum of 6-12 hours before their removal by equipment or before removal of a turbidity curtain. It is imperative that the intended function of the other controls in this chapter, to keep sediment out of the watercourse, be the strategy used in every erosion control plan. However, when proximity to.the watercourse makes successfully mitigating sediment loss impossible, the use of the turbidity curtain during land disturbance is essential. Underno circumstances shall permitted land disturbing activities create violations of water quality standards! Desiqn Criteria 1. Type I configuration (see Plate 4.45a) should be' used in protected areas where there is no current and the area is sheltered from wind and waves.. 2. Type II configuration (see Plate 4.45a) should be used in areas where there may be small to moderate current running (up to 2 knots or 3.5 feet (1 m) per second) and/or wind and wave action can affect the curtain. 3. Type Ill'configuration (see Plate 4.45b) should be used in areas where considerable . current (up..ta 3 knots, or 5 fe..et,.(1.5.m). per second) may be present;_ where tidal action may be present; and/or where the curtain is potentially subject to wind and wave action. 4. Turbidity curtains should extend the entire depth of the watercourse whenever the watercourse in question is not subject to tidal action and/or significant wind and Wave forces. This prevents silt laden water from escaping under the barrier, scouring and resuspending additional sediments. 5. In tidal and/or wind and wave action situations, the curtain should never be so long as to touch the bottom. 'A minimum 1 foot (30 cm) "gap" should exist between the weighted lower end of the skirt and the bottom at "mean". low water. Movement of the lower skirt overthe bottom due to tidal reverses orwind and wave action on the flotation system may fan and stir sediments already settled out. 6. In tidal andlor wind and wave action situations, it seldom practical to extend, a turbidity curtain depth lower than10 to 12 feet (3 to 4 m) .below the surface, even in deep water. Curtains which are installed deeper than this will be subject to very large loads with consequent strain on curtain materials and the mooring system. A.1 IA Chapter 4 ='Besf;Nana - ement Pzactices:fof:.Erosion and Sediment Control ... In addition, a curtain installed in such a manner can "billow up" toward the surface under the pressure of the moving water, which will result in an effective depth which is significantly less than the skirt depth. 7, Turbidity curtains should be located parallel to the direction of flow of a moving body of water. Turbiditycurtains should not be laced across. the main flow of a significant body of moving water. g, When sizing the length of the floating cuitain, allow an additional 10 - 20%variance in the straight-line measurements. This will allow for measuring errors, make _ installing easier and reduce stress from potential wave action during high winds. g, An attempt should.be made to avoid an excessive number of joints in the curtain; a minimum continuous span of 50 feet (15 m) between joints is a good "rule of thumb." tta .. lo. orn'axe to follow. s.of 100 feet (30 m) between anchor or at locations s also a goad 11.. The ends of the curtain, both floating upper and weighted lower, should extend well up into the shoreline, especially if high water conditions are expected. The ends should be secured firmly to the shoreline to fully enclose the area where sediment may enter the water. 12. When there is a specific need to extend the curtain to thebottomvious offiltt e watercourse bric may be in tidal or moving water conditions, a heavy wo�fen"p substituted for the normally reco1.mmended impervious geotextile. This creates a "flow-ituted fo the norr which significantly reduces.th1.e pressure,on the curtain and will help to keep it in the same relative location and shape during the rise and fall Ow of tidal waters. 13. Typical -alignments -of turbidity curtains can be -seen in Plate 4.45c:The number and spacing of external anchors may vary depending on current velocities and potential wind and wave. action; manufacturer's recommendations should' be followed. 14. Be certain -that -the type, location; and. installation of the barrier is as shown on the approved plan and permit Additional permits may be required in navigable waterways, especially when the barrier creates an obstruction. to n Florida. Erosion and Sediment Control Inspector's Manual 5/5 IN. POLYPROPYLENE ROPE 1/4 IN. TIE ROPE FLOATATION FOLDS FOR COMPACT STORAGE ACCORDING TO NEED%/ AVAJLA13LE STANDARD NYLON REINFORCED VINYL ALL SEMIS HEAT SFALED I/4 IN. CHAIN - (BLOW-UP OF SHACKLE CONNECTION) O Typel 18 (OR 2Z) OZ. VINYL COVERED NYLON GALVAN2ED #24 SAFETY. HOOK TOP LOAD LINE \Fr4C, SLOT- CONNECS� 5/16 VINYL COATED CABLE L ;PLATE (TO REMOVE FLOAT7TION7i.SSURE FROM .QATS) IDA FT. STANDARD LENGTH . FOLDS EVERY 6 FFFi DEPTH ACCORDING TO NEED STRESS BANG STRESS PLATE S/16 IN. CHAIN BALLAST & LOAD LINE Type II Plate 4.45a Type I and 11 Floating Turbidity Barriers Source: American Boom and Barrier Corporation 4.118' Chapter4`- Rest Mana ement Practices for Erosion and. Sediment.Contro Construction Sgecificatlons Materials 1. Barriers should be a bright color (yellow or"international" orange are recommended) that will attract the attention of nearby boaters. 2. The curtain fabric must meet the minimum requirements noted in Table 3.27-A. 3. Seams in the fabric shall be either vulcanized welded or sewn;. and shall develop the full strength of the fabric. r ividual 4. Floatation devices shall be flexibie, buoyant units contained in an inaby the r floatation sleeve or collar attached; to the curtain. Buoyancy p. floatation units shall be sufficient to support:the weight of the curtain and maintain a freeboard of at least 3 inches (8 cm) above the.water surface level. (See Plate 4.45c) 5• Load_line .a must be fabricated into the bottom of all floating turbidity curtains. Type II and Type III must have load lines also fabricated into the top o€`the fabric. The top ` load line shall consist of woven webbing or vinyl -sheathed steel cable and shall have a break strength in excess of 1o,000 pounds (4.5 t). The supplemental ` (bottom) load -line shall consist of a chain incorporated into the bottom hem of the curtain of sufficient weight to serve ` as ballast to hold the curtain in a vertical position. Additional anchorage shall be• proVided`as necessary.. The load lines shall have suitable connecting devices which develop the full breaking strength for connecting to load lines in adjacent sections (See Plates 4.45a and. 4.45b which portray this orientation). . 6, Externatanchors may consist of 2 x 4 inch (5x 16 cm) or 2-1/2 inch (6 dm)minimum diameter wooden stakes, or 1.33 pound sllinearfoot (2 kd1m) steel posts when Type CinstMidtfon is. used when Type It orrType 11F.Installations are used, bottom anchors. should be used. 7_ Bolton► anchors must be sufficient to hold the curtain.in the same position relative to the bottom of the watercourse without interfering with the action oethoe may be The anchor may dia into the bottom (grappling hook, plow or fluke-typ ) weighted (mushroom type) and should be attached to a floating anchor buoy via an anchor line. The anchor line would then run from the buoy to the top load line of the curtain. When used with Type Ill installations, these lines must contain enough slack to allow the buoy and curtain to float freely.with tidal changes without pulling VW the buoy or curtain down and must be checked regularly to make sure they do not become entangied with debris. As previously noted, anchor spacing will vary with current velocity and expected wind and wave action; manufacturer's recommendations should be followed. See orientation of external anchors and anchor buoys for tidal installation in Plate 4.45b. a Erosion and Sediment Control Inspeciors lwanual Type III 22 02. NYLON REINFORCED VINYL STRESS BARD FLOATATION PVC SLOT - CONNECTOR r] ACCORDING TO NEED VI 16 NYL COATING CABLE #24 SAFETY HOOK STRESS PLATE 'LIN% 6/CHAIN ' N 130TH SINOF TO REDUCEDES STRIN)CURLAIN Orientation When Installed (Tidal Situation -Type 111). NOTE: ANCHORING WITH BUOYS, ATTACH LINES AUTOMATIC FLASHING AS SHOWN, REMOVES ALL -BUOY TO SHAC%LE LIGHT (ON AT DUSK - VERTICAL FORCES FROM THE ��JJ _OFF AT DAWN) IGO CURTAIN. HENCE; THE CURTAIN 1 „/ J `_n 1 / VCENTER + NAVIGABLE SHALL BE WILL NOT ORDS, FROM WINO OR \ — - - _ 3 CURRENT' LOADS, --��-77 i / � N ONLY MIN 2 .. _............. STANDARD CONrATNA1ENr SYSTEMS LIGHT BUOY ANCHOR (AS, WATER SURFACE .. _ ... RECOMMENDED BY THE MANUFACTURER) ^v7 MIN,. 12CURTAIN RIVERBED e 0 o a o o vv o v v v o v vv. v o v' o v v vo o c o v,o a v v v a 0 0 0 0 0 0 0 .v v v v o 0 0 o v v v v voo 0 0 a v o v o v e v a o v 9 v Plate 4.45b Type III Floating Turbidity Barrier Source: American Boom and Barrier Corporation and VDOT Standard Sheets 4-120 r J r7 W or IM it Installation 1, In the calm water of lakes or ponds (Type 1 installation) it is usually sufficient to merely set the curtain end stakes or anchor points (using anchor buoys if bottom anchors are employed), then tow the curtain In the furled condition out and attach it oyed to these stakes or anchor points. Following this, any additional stakes or bu be set and anchors required to maintain the desired location. of the curtain may. rtain. Only then, the furling lines should be these anchor points made fast to the cu cut to let the curtain skirt drop. 2.. In rivers or in other moving water (Type 11 and Type Ili installations) it is important to set all the curtain holding power to retain fe ust be taken to the curtain under theure texpected chorcurrent at an are of sufficient holding p rled curtain into thewater: Anchor buoys should be conditions, before putting the fu employed on all anchors to prevent the current from submerging the flotation at the anchor points. If the moving water into which the curtain is being installed is tidal and will subject the curtain to currents in both directions as de changes, it is the ti important to provide anchors on both sides of the curtain for two reasons: a) Curtain movement will be minimized during tidal current reversals. b) The curtain will -not overrun the anchors pull there out when the tide reverses. When the anchors are secure, the furled curtain should be secured to the upstream anchorpoint and then sequentially -attached to each next downstream anchor point until the entire curtain is in position. At this point, and before unfurling, the "lay of the curtain should. be assessed ande any. necessary adjustments made to the anchors. Finally; when the location is ascertained to be as desired, the furling lines should be cut to allow the skirt to drop. 3. Alwa s attach'anchorlinesto-the flotattondevice-not to -the r%; the curtain_. r The anchoring line attached to the floatation device on the downstream side. will provide support for the curtain. Attaching the anchors to the bottom of the curtain could cause premature failure of the -.curtain due to the stresses imparted on the .• middle section of the curtain. 4, There is an exception to the rule that turbidity curtains should not be installed across r channel flows -, it occurs when there is a danger of creating a silt buildup in the middle of a watercourse, thereby blocking access or, creating a sand bar. Curtains have been used effectively in large areas of moving water by forming a very +� long -sided, sharp "V" to deflectclean water around a work site, confine a large part of the silt -laden water to the work area inside the "V" and direct much of the silt toward the shoreline. Care must be taken, however, not to install the curtain perpendicular to the water current. 5. See Plate 4.45c for typical installation layouts. 4-121 Florida:Erosion. and Sediment Control Inspectors Manual Typical Layouts Streams, Ponds, and Lakes (Protected and Non.Tidal) STREAH4LOw ANCHOR PT. .. �- STAKE OR ANCHOR, EVERY 100' (TYPICAL) SHORELINE ® FILL AREA CONSCONSTR. �.• OF .. . � SHORELINE ANCHOR PT. TURBIOfry CURMN r. THIS DISTANCE IS VARIABLE Tidal Waters andfor Heavy Wind and Wave Action SHORELINE ANCHOR PT:. • THIS DISTANCE IS VARIABLE EXISTING CAUSEWAY ANCHOR k ANCHOR BUOY BARRIER MOVEMENT DUE TO TIDAL CHANGE ® FILL AREA PROPOSED TOE OF SLOPE SHORELINE ANCHOR PT Plate 4.45c Typical Installation Layouts` Source: FDOT Roadway and Trac Design Standards 4-122 -Best Wanagement Practices for Erosicn: and.Sedtment ont+.w::. g, The effectiveness of the barrier can' be increased by installing two parallel curtains, separated at regular intervals by 101 (3 m) long wooden boards or lengths of pipe. Removal 1, Care should be taken to protect the skirt from damage as the turbidity curtain is dragged from the water. 2. The site -selected to bring the curtain ashore should be free of sharp rocks, broken cement, debris, etc. so as to minimize damage when hauling the curtain over the area. 3. If the curtain has a deep skirt, it can be further protected by running a small boat along its length with a crew installing furling lines before attempting to remove the curtain from the water. Maintenance I= 3. n M M 4-1 The developerlowner shall be responsible for maintenance of the filter curtain for the duration of the project to ensure the continuous protection of the watercourse. Should repairs to the geotextile fabric become necessary, there are normally repair kits available from the manufacturers; manufacturer's instructions must be followed to ensure the adequacy of the repair. When the curtain is no longer required as determined by the inspector, the curtain and related components shall be removed in such a manner as to minimize turbidity. Sediment shall be removed and the original depth ,(or plan elevation) restored before removing the curtain. Remaining sediment shall be sufficiently settled before removing the curtain. Any spoils must be taken to an upland area and stabilized. Florida Erosion and Sediment Control Inspector's Manual This page left intentionally blank 4-124 Chapter 4 - Best Management Practices for Erosion and Sediment Control r REFERENCES Florida Department of Environmental Regulation, 1988, The Florida Development Manuai: A Guide to Sound Land and Water Management (Chapter 6), Tallahassee, FL r ML r ON M M C7 r r r 4-125