HomeMy WebLinkAbout2005-293 CHANGE ORDER NO . 004 - FINAL
DATE OF ISSUANCE : , 2005 EFFECTIVE DATE : , 2005
OWNER : Indian River County
CONTRACTOR : JOBEAR / WARDEN CONSTRUCTION , INC .
Project : EAST ROSELAND STORMWATER IMPROVEMENTS
OWNER's Project No . 0110
OWNER/ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents :
1 . Description : Final reconciliation of quantities for Final Pay Request .
a . 24 " R . C . P . --> DEDUCT 5 . 5 feet at $44 per lineal foot = ($ 242 . 00 )
b . 18 " R . C . P . 4 ADD 1 . 7 feet at $ 35 per lineal foot = $ 59 . 50
c . 30 " A . D . S . 4 ADD 2 . 4 feet at $ 38 per lineal foot = $ 91 . 20
d . 48 " R . C . P . 4 DEDUCT 3 . 6 feet at $ 126 per lineal foot = ($ 453 . 60 )
e . 4 ' tall chain link fence 4 DEDUCT 70 feet at $ 19 . 09 per lineal foot = ($ 1 , 336 . 30 )
TOTAL DEDUCT FROM CONTRACT PRICE _ ($ 1 , 881 . 20 )
CHANGE IN CONTRACT PRICE :
Description Amount
Original Contract Price $383 , 810 . 00
Net increase from previous Change Orders
No . 001 , 002 , and 003 : $ 51 , 205 . 59
Contract Price prior to this Change Order: $435 , 015 . 59
Net DECREASE of this Change Order: $ 1 , 881 . 20
Contract Price with all approved Change
Orders : $433 , 134. 39
CHANGE IN CONTRACT TIMES
Description Time
Original Contract Time Final Com letion 120 days
Net change from Change Orders No , 001 , 30
002 , and 003 :
Contract Time prior to this Change Order: 150 days
Net increase decrease this Change Order: -0-
Contract Time with all approved Change
Orders . 150 days
Change Order #004 - Final
Change Order - 1
FAPublic WorksWeithM\Stormwater Projects\Roseland\Change Orders\Change Order #004 - Final .doc
ACCEPTED : RECOMMENDED , AROVED :000'
r
000'\ ,
By : By' By � �. 5 . .
CONTRACTOR (Signat re) E INEE ignature) OWNER (Stgrraturej
N Keith McCully, P . E . , Indian Thomas S .'-, 4
wther; >Chairri�an , .
R� ea - fpr ' 1 River County Stormwater Board of Co - ' ' ¢gmmissio'ne
VICE RlaotOIE� I Engineer
( Name and Title) rst�
�r' F ` .
Date : 5 '003VT Date : Date : 09 / 06 /06 ose A ,
ollettle. lot
®1nmA nWitIrP+. ..T,
Change Order - 2 Change Order #004 - Final