CHANGE ORDER
No . 1 /
PROJECT Indian River County So. County WTP Wellfield Rehabilitation , Phase II
DATE OF ISSUANCE EFFECTIVE DATE
OWNER Indian River County Department of Utilitv Services
OWNER' s Contract No , Bid No . 5102 CDM Project No . 6706- 38392 - 151
CONTRACTOR Layne Christensen Company ENGINEER Camp Dresser & McKee Inc
You are directed to make the following changes in the Contract Documents :
Description : Miscellaneous project scope modifications See Exhibit A
Reason for change order: Modification of project scope of work See Exhibit A
Attachments : (List documents supporting change). . Exhibit A
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price Original Contract Times
$ 558 , 764 . 55 Substantial Completion : 120 days
Ready for final payment : 150 days
Days or dates
Net changes from previous Change Orders Net change from previous Change Orders
No . to No . No . to No .
$ 0 . 00 0 days
Contract Price prior to this Change Order Contract Time prior to this Change Order
$ 5584764 . 55 Substantial Completion : 120 days
Ready for final payment : 150 days
Das or dates
Net Increase (decrease) in this Change Order Net Increase in this Change Order
$ 134626 . 54 45
days
Contract Price with all approved Change Orders Contract Time with all approved Change Orders
$ 572 ,391 . 09 Substantial Completion : 165 days
Ready for final payment : 195 days
Days or dates
RECOMMEN D : APPRQ1 ACCEPTED :
By : BY By :
Enginee AuAthorized Signature) Cacti # as i rman Conctor ( A horized Signature )
BCS `
Date : �i S o Da$� u Date : 3 -D
EJCDC No . 1910- 8 ( 1996 Edition) ,
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General
Contractors of America .
ATTACHMENT A
mh1600 Change Order.doc
EXHIBIT A
ITEM DESCRIPTIONS
Indian River County, Florida
South County Water Treatment Plant Wellfield Rehabilitation, Phase II
CDM Project No . 6706-38392-151
Change Order No . 1
Item No .
1 Description: Chase and Lead Threads on Well No . 3 Column Pipe
Purpose : Well No . 3 column pipe utilized to extend Well Nos . 1 and 2 while
new Well No . 3 is under construction. Threads on existing
column were found to be galled and needed repair .
Cost: $1 ,500 . 00
Time . 9 days
2 Description: Upgrade Mechanical Seals/ Discharge Heads
Purpose : Seals and discharge heads modified/ upgraded to be compatible
with existing discharge head and conditions .
Cost: $2,305 . 60
Time . 15 days
3 Description: Extend 24-inch steel surface casing
Purpose : Extension required to meet clay formation. Additional 66 feet of
casing was required to be set.
Cost: $9,644 .38
Time : 3 days
4 Description: Extend 16-inch PVC Production Casing
Purpose: Extension to improve well production. The casing was set to a
final depth of 396 ft. , 11 ft. deeper than originally estimated .
Cost: $1 ,317.58
Time . 3 days
ATTACHMENT B A-1 mh1600 .doc
5 Description: Flanged Column Pipe Credit
Purpose : Credit for use of flanged column for Well Nos . 5 and 6 in lieu of
specified threaded column yielded .
Cost: ($1 , 141 . 02)
Time : 0 days
6 Description : Telemetry System Delivery
Purpose : Approved system delivery delayed in fabrication.
Cost: $0 . 00
Time : 15 days
A- 2 mnisoo.aoc
EXHIBIT B
CHANGE ORDER COST & TIME SUMMARY
Indian River County, Florida
South County Water Treatment Plant Wellfield Rehabilitation, Phase II
CDM Project No . 6706-38392-151
Change Order No . 1
ITEM COST / CREDIT TIME (Days)
1 $1 ,500 . 00 9 days
2 $2,305 . 60 15 days
3 $9, 644 . 38 3 days
4 $1 ,317. 58 3 days
5 ($1 , 141 . 02) 0 days
6 $0 . 00 15 days
Totals $13, 626. 54 45 days
This Change Order includes not only all direct costs of Contractor such as labor, material, job
overhead, and profit markup, but also includes any costs for modifications or changes in
sequence of work to be performed, delays, rescheduling, disruptions, extended direct overhead
or general overhead, acceleration, material or other escalation which includes wages, and other
impact costs .
ATTACHMENT C mh1600. doc