Y SC- 13 . 03 . 13 . Delete paragraph GC- 13. 03. B in its entirety, and insert the following in its place: <br /> B . OWNER shall employ and pay for the services of an independent testing <br /> laboratory to perform all initial inspections , tests , or approvals required by the <br /> Contract Documents except those inspections , tests , or approvals listed <br /> immediately below . Subsequent inspections , tests , or approvals required after <br /> initial failing inspections , tests , or approvals shall be paid for by the <br /> CONTRACTOR by backcharge to subsequent applications for payment . <br /> SC- 13 . 03 . 0 Delete GC- 13. 03. 0 in its entirety. <br /> SC- 13 . 04 Uncovering Work <br /> SC - 13 . 04 . 13 Delete portions of the last two sentences as follows: <br /> If , however, such Work is not found to be defective , CONTRACTOR shall be allowed-an <br /> lvgwp � +he rteE) RtFaGt PriGe OF <br /> an extension of the Contract Times ( or Milestones ) ,-Er <br /> beth-, directly attributable to such uncovering , exposure , observation , inspection , testing , <br /> replacement , and reconstruction . If the parties are unable to agree as to the alTleuRt er <br /> extent thereof , CONTRACTOR may make a Claim therefor as provided in paragraph <br /> 10 . 05 . <br /> SC- 13 . 05 OWNER May Stop the Work <br /> SC- 13 . 05 . A . Delete paragraph GC- 13. 05. A in its entirety and insert the following paragraph in its <br /> place: <br /> A . If the Work is defective , or CONTRACTOR fails to supply sufficient skilled <br /> workers or suitable materials or equipment , or fails to comply with permit <br /> requirements , or fails to comply with the technical specifications , or fails to <br /> perform the Work in such a way that the completed Work will conform to the <br /> Contract Documents , OWNER may order CONTRACTOR to stop the Work , or any <br /> portion thereof , until the cause for such order has been eliminated ; however , this <br /> right of OWNER to stop the Work shall not give rise to any duty on the part of <br /> OWNER to exercise this right for the benefit of CONTRACTOR , any <br /> Subcontractor, any Supplier , any other individual or entity , or any surety for , or <br /> employee or agent of any of them . <br /> SC- 14 . 02 Progress Payments <br /> SC- 14 . 02 . 13 . 5 . Add the following paragraphs at the end of paragraph GC- 14. 02. 8. 5: <br /> e . OWNER has been required to pay ENGINEER or ENGINEER ' s Consultant <br /> additional compensation because of CONTRACTOR delays or rejection of <br /> defective Work ; or <br /> f . OWNER has been required to pay an independent testing laboratory for <br /> subsequent inspections , tests , or approvals taken after initial failing inspections , <br /> tests , or approvals . <br /> SC- 14 . 02 . C . 1 . Delete paragraph GC- 14 . 02. C. 1 in its entirety and insert the following <br /> paragraph in its place: <br /> 00800 - Supplementary Conditions 2006041 <br /> All 0080011 <br /> FAPublic Works\Capital Projects\Oslo Road Lateral J\BID DOCUMENTS 2006041 \00800 - Supplementary Conditions 2006041 .doc Rev . 05/01 <br />