ARTICLE 8 TIME <br /> § 8. 1 DEFINITIONS <br /> § 8. 1 . 1 Unless otherwise provided, Contract Time is the period of time, including authorized adjustment , allotted in <br /> the Contract Documents for Substantial Completion of the Work. <br /> § 8. 1 .2 The date of commencement of the Work is the date established in the Agreement. <br /> § 8. 1 . 3 The date of Substantial Completion is the date certified by the Architect in accordance with Sectipn 9 . 8 . <br /> § 8.1 .4 The term "day" as used in the Contract Documents shall mean calendar day unless otherwise specifically <br /> defined . <br /> § 8.2 PROGRESS AND COMPLETION <br /> § 8.2. 1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing th Agreement <br /> the Contractor confirms that the Contract Time is a reasonable period for performing the Work. <br /> § 8.2.2 The Contractor shall notng'�, not, except by agreement or instruction of the Owner in writing, <br /> prematurely commence operations on the site or elsewhere prior to the effective date of insurance required by <br /> Article I I to be furnished by ,the Contractor and Owner. The date of commencement of the Work shall not be <br /> changed by the effective date of such insurance. <br /> Daeuments or- a nefiee to pfeeeed given by the Ownef, the Gentfaeller- shall notify the Ownef in writing hot iess than <br /> five days of other- agreed pe6ed before conmnencing the Work to pem* the fifinely filing Of - nechanie ' s <br /> liens and other- seewity interests . <br /> § 8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion <br /> within the Contract Time. Contractor shall give Owner full information in advance as to its plans for performing <br /> each part of the Work. If at any time during the progress of Work Contractor' s actual progress is inadequate to <br /> meet the requirements of the Contract Owner shall may. but is not ..bragq + so notify Contractor. In such <br /> event Contractor acknowledges and agrees that Contractor shall implement some or all of the following remedial <br /> actions at the sole cost and expense of Contractor: a Increase man ower in such quantities and crafts a necessary <br /> to eliminate the backlog of Work b Increase the number of working hours Wr shift shifts per working day. <br /> working days per 'week the amount of construction equipment, or any combination of the foregoing to a iminate the <br /> backlog of work,• or c Reschedule the Work in conformance with the specification re uirements . Neit ier such <br /> notice by Owner nor Owner ' s failure to issue such notice shall relieve Contractor of its obligation to ac h eve the <br /> uali of Work and rate of progress required by the Contract. Failure of Contractor to implement someDr all of the <br /> remedial actions may be grounds for determination by Owner that Contractor is not prosecuting its Wo r with such <br /> dihizence as will assure com letion within times specified. Upon such determination Owner may termi ate <br /> Contractor' s right to proceed with the performance of the Contract or any separable part thereof, in acco dance with <br /> the applicable provisions of this Contract. <br /> § 8.3 DELAYS AND EXTENSIONS OF TIME <br /> § 8.3.1 If the Contractor Contractor' s performance of this Contract is delayed: i) which delay is delaye�ime <br /> in-beyond the ' gffreasonable control and without thefault oreglest <br /> negligence of the 9waer-Contractor or AA « its subcontractors• or , of of a <br /> 00fitr-aCtff employed by the ii by changes ordered in the Work, and in either event where such delay or <br /> by labor- disputes, fiFe, hanQe in the <br /> Gentfacter-' sWork affects the OwneF pendinglFflediation and afbitfatie i, E)f by <br /> , ritical path, then the Contract Time shall be <br /> extended by Change Order f r- such reasonable time as determined by the Owner and the A ehiteet-ContrAct Sum <br /> may '� be a uitabl ad 'usted for Contractor' s extended ' ob costs limited to the Cost of the Worklitems <br /> enumerated in Article 6 of the Agreement), subject to Contractor' s compliance with the notice requir_�ts of <br /> Paragraph 4.3 of these General Conditions. <br /> 8 . 3 .2 . The Contractor must request the extension of time in writing and must provide the following infor ation <br /> within the time periods stated hereafter. Failure to submit such information and in compliance with the ti ie <br /> requirements hereinafter stated shall constitute a waiver by the Contractor and a denial of the claim for a tension of <br /> AIA Document A201 TM - 1997. Copyright ® 1911 , 1915, 1918, 1925, 1937, 1951 , 1958, 1961 , 1963, 1966, 1967, 1970, 1976g 1987 ar d <br /> 1997 by The <br /> American Institute of Architects. All rights reserved. WARNING: This AIAs Document Is protected by U.S. Copyright law and Inti rnational Treaties. <br /> .27 <br /> Unauthorized reproduction or distribution of this A10 Document, or any portion of it, may result in severe civil and criminal pe aities, and <br />will be <br /> prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 13 :00:02 on 04/19/200$ under Order <br /> No. 1000126313_1 which expires on 6/29/2005, and is not for resale. <br /> User Notes: ( 1205244124) <br />