Act Activity Orig Months
<br /> ID Description Dur .1 1 2 3 4 5 6 7 S 1 9 1 10 1 11 12 1 13 1 14 1 15
<br /> 16 17 18
<br /> SWA36 Site Lighting 15 ®Site Lighting
<br /> SWA40 Irrigation & Landscaping _ 30 Irrigation & Lands ftaping
<br /> SWA44 Demo Fiber Optic, CAN & OH Lines (by others) 15 ®Demo Fiber Optic, CAN & OH Lines (by others)
<br /> SWA48 Pavers & Site Amenities 30 Pavers & Site Amenities
<br /> SWA52 Bldg 1 Building Pad Ready 0 ® Bldg 1 Building Pad Ready
<br /> Building 1 --
<br /> Foundations - Piles thru Lvl 1 Verticals
<br /> B1000 Deep UG MEP Utilities (Below Footings) 10 ®Deep UG MEP Utilities (Below Footings)
<br /> B1004 Excavate, Form, Rebar, Pour, Strip Footings 30 Excavate, Form, Rebar, Pour, Strip Footings
<br /> Structure, Exterior, Roof
<br /> 81008 CMU Walls & Tie-Beams to 2nd Lvl 35 CMU Walls & Tie-Beams to 2nd Lvl
<br /> B1012 Rebar, Form, Pour, Strip Conc Columns to 2nd 15 Rebar, Form , Pour, Strip Conc Columns to 2nd Lvincl any conc beams
<br /> B1016 Backfill & Compact SOG area 20 ®Backfill & Compact SOG area intermittent
<br /> 81020 Scaffold, Set PSI Soffit Bms, Layout for Joists 15 ®Scaffold, Set PSI Soffit Bms, Layout for Joistsincl set spacers
<br /> B1024 Set PSI Joists, Deck, Rebar & Pour 2nd Fir Slab 20 ®Set PSI Joists, Deck, Rebar & Pour 2nd Fir Slab
<br /> 81028 Rebar, Form, Pour, Strip Conc Cols to Roof Lvl 15 I Rebar, Form, Pour, Strip Conc Cols to Roof Lvlincl any conc
<br /> beam
<br /> 81032 Set PreCast Columns, Beams & Arches 15 MONEW PreCast Columns, Beams & Arches
<br /> B1036 CMU Walls & Tie Beams to Roof Lvl 20 ®CMU Walls & Tie Beams to Roof Lvl
<br /> B1040 Metal Pan Stairs, Conc Fill , Railings 20 ®Metal Pan Stairs, Conc Fill, Railings
<br /> 81044 Remove Forms & Shores, UG Utilities thru SOG 25 ®Remove Forms & Shores, UG Utilities thru SOG
<br /> 81048 Erect Structural Steel, Bar Joists & Mtl Deck 25 ®Erect Structural Steel, Bar Joists & Mtl Deck
<br /> 81052 Upper Rf - Lt Gage Frm'g thru Asph Sheets 10 =Upper Rf - Lt Gage Frm'g thru Asph Sheets
<br /> B1056 Upper Rf - Facia, Block'g, Insul, Sheath'g , Ash 20 ffi®U M
<br /> PP 9 9 P Upper Rf - Facia, Block'g, Insul , Sheath 'g , Asph A
<br /> 81060 Upper Rf - Barrel Roof Tile & Gutters 25 ®Upper Rf - Barrel Roof Tile & Gutters
<br /> B1064 Lower Rf - Mansard Trusses, Formdk, Sheathing 15 ®Lower Rf - Mansard Trusses, Formdk, Sheathing As h Sheet
<br /> B1068 Lower Rf - Flat Rf Insulation & Lt Weight Conc 15 ®Lower Rf - Flat Rf Insulation & Lt Weight Conc
<br /> B1072 Lower Rf - Flat Rf Modified Bitumin Roofing 10 =Lower Rf - Flat Rf Modified Bitumin Roofing
<br /> B1076 Lower Rf - Mansard Barrel Tile & Gutters 15 ®Lower Rf - Mansard Barrel Tile & Gutters
<br /> 81080 Lath & Stucco (incl molded crown & trim) 50 Lath & Stucco (incl molded crown & trim)
<br /> B1084 Standing Seam Roof 15 ®Standing Seam Rood incl peel & stick wtr roof membrane
<br /> B1088 Window / Storefront & Ext. Doors 30 ®Window / Storefront & Ext. Doors
<br /> B1092 Exterior Paint 25 ®Exterior Paint
<br /> Interior / Finishes
<br /> 81096 MEP/FS Risers (Vents, Stacks, Fdrs, RWLs) 25 MEP/FS Risers (Vents, Stacks, Fdrs, RWLs)
<br /> 81100 Plumbing Rough-in (incl water piping & insul) 35 ®Plumbing Rough-in (incl water piping & ins l)CW, HW, Dom,
<br /> WV
<br /> 61104 HVAC Rough-in (Ductwork, Insulation) 70 HVAC Rough-in (Ductwork, Insulat on) incis Set AHUs
<br /> B1108 Elect Pwr/Ltg/FA/Systems Rough-in 70 Elect Pwr/Ltg/FA/Systems Rough in Walls/Ceilings
<br /> 81112 Fire Sprinkler Rough-in & Pressure Test 50 ®Fire Sprinkler Rough-in & Pressure Test
<br /> 81116 HMtl Dr Frames, Mtl Stud Walls, Soffits, Ceil'gs 50 HMtI Dr Frames, Mtl Stud Walls, Soffits, Ceil'gs
<br /> B1120 Install Hydraulic Elevators, Finish, Inspections 55 Install Hydraulic Elevators, Finish, Inspections
<br /> 81124 Drywall, Tape & Finish Walls, Soffits & Ceilings 50 ®Drywall , Tape & Finish Walls, Soffits & Celling
<br /> B1128 Main Stair & Balconys - Stru, Railings, Finish 50 Main Stair & Balconys - Stru, Railings, Fini
<br /> B1132 Controls - Wiring , Devices, Test & Check-out 35 ®Controls - Wiring, Devices, Test & Check-ot
<br /> 81136 1st Coat & Prime Paint 40 1st Coat & Prime Paint
<br /> Run Date 26MAY0507:38 IROATurner Construction Company Sheet of R01 Project Schedule
<br /> Finish Date 08DEC06
<br /> Data Date 11APR05 Indian River County Administration Facility
<br /> © Primavera Systems , Inc. GMP Summary Schedule