Laserfiche WebLink
Indian River County Administration Complex <br /> Bldg. 2 - 2nd Floor Punch List - Friday - 05/25/07 <br /> June 5, 2007 <br /> Page 2 <br /> Atrium (continued) <br /> 13. Sprinkler head in front of Door 2.2 - 201 A opening cut too large, needs to be patched and repaired. <br /> 14. Ceiling needs to be refinished, drywall finish on the North side looking South by the paint finish overlaps, not <br /> a uniform finish. <br /> 15. Drywall header between the drywall ceiling and the acoustical ceiling, edges are very rough and irregular, <br /> needs to he sanded and repainted. <br /> 16. Acoustical ceiling grid is installed ceiling tile approximately 10% installed at this time, only at light fixture <br /> and A/C Grilles. <br /> 17. Boxed out column to the left of the Men' s Restroom 102 needs to be repainted, finish on scuff marks . Also, <br /> drywall casing head is cracking at the top by the acoustical ceiling. <br /> Men's Restroom 102 <br /> 1 . Restroom needs to be cleaned completely. <br /> 2. No paper towel and trash receptacle installed . <br /> 3 . No lighting installed at this time. <br /> 4. Ceramic tile needs to be completely cleaned. Also, inside corner needs to be grouted, not grouted at this time <br /> to the inside of the ceramic tile corner. <br /> 5 . Exhaust Grille does not set plumb to the room <br /> 6. Ceiling needs to be re-worked above the Fire Alarm Junction Box . <br /> 7. A/C Grille does not set plumb to the walls of the room. <br /> 8. Left side of the door inside below the center hinge the door is damaged and also, inside face is scratched. <br /> 9. No silencers installed in the door. <br /> 10. The same is true for all Women' s Restroom 103 . <br /> Janitors Closet <br /> 1 . Drywall, frames and doors are not tight and protective of painting. <br /> 2. No vinyl base or vinyl floor installed. <br /> 3 . Walls need to be finished painting. <br /> 4. This room is not in the condition to be punched . <br /> Door 2.2 - 201A <br /> 1 . Door at this time is covered with painting on interior side. <br /> 2. Window frame for the view light paint is peeling, needs to be redone. <br /> 3 . Inside face of door, window frame and view light is also scratched. <br /> 4. Door frame needs to be completely repainted it has been sanded in numerous areas. <br /> Reception Room 201 <br /> 1 . Drywall to the left and right of Door 201 needs to be repainted at the base on either side. <br /> 2. Vinyl base is not completely installed. <br /> 3 . Outside comer of the masonry shaft wall, vinyl base is not adhered. Also, drywall on the outside corner is <br /> irregular, pencil marks on the wall needs to be corrected. <br /> 4. East wall between masonry chase and Door 203 scratched on the drywall above the vinyl base need to be <br /> patched and repaired. <br /> 5 . Drywall wall between Doors 203 & 204 electrical outlet has been patched and repaired, needs to be sanded <br /> and repainted. Also, vinyl base needs to be cleaned in this same area. <br /> 6. Center of the wall touch up marks on the wall not acceptable this is typical throughout the whole wall , needs <br /> to be redone. <br /> 7 . North wall of Reception 201 between Doors 307A & 307B at the Conference Room, drywall needs to be <br /> repainted above the vinyl base and to the right of the fire extinguisher cabinet. <br /> D O N A D I O <br /> & Associates, Architects, P.A. <br />