§ 2.1 .5 PRELIMINARY COST ESTIMATES <br /> § 2. 1 .5. 1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other <br /> basic design criteria, the Construction Manager shall prepare, for the review of the Architect and approval of the <br /> Owner, a,preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques. <br /> § 2.1 .5.2 When Sehematie Design Dersuments have been pr-epaFed by the AmMteet and appmved by Ube <br /> Construetion Manager- shall prepare, 1.16mw dhe Feiriew of the Afehfteet and appreval ef t4e Owner-, a mer-e de aik4 <br /> estimate with supper-ting data. During the pr-epar-afieen of dhe Design Develepment Deeuments, the Censtfuefieff <br /> Manager- shall update and fefine this estimate at appr-opriate intefvals agreed t"- - Ar-eWteet and <br /> § 2.1 .5.3 , <br /> thR CANStRIA-6 OR Manager- shall pr-epafe a detailed estifnate with suppeffing data fef review by the Ar-ehitec +aW <br /> update and refine this estimate at appropriate inteEvals agreed to by the QwneF, Arehiteet and Censtructiel-A '.41 <br /> § 2. 1 .5.4 If any estimate submitted to the Owner exceeds previously approved estimates or the Owner' s budget, the <br /> Construction Manager shall make appropriate recommendations to the Owner and Architect. <br /> § 2.1 .6 SUBCONTRACTORS AND SUPPLIERS <br /> The Construction Manager shall seek to develop subcontractor interest in the Project and shall furnish tote Owner <br /> and Architect for their information a list of possible subcontractors, including suppliers who are to furnish materials <br /> or equipment fabricated to a special design, Owners cifications of County- wide applicability. or derived from a <br /> pre-existing rice and material schedule to a contract between a s cific vendor and Owner or the State of Florida <br /> or the United States General Services Administration from whom proposals will be requested for each principal <br /> portion of the Work. The Architect will promptly reply in writing to the Construction Manager if the Arch tect or <br /> Owner ' know of any objection to such subcontractor or supplier. The receipt of such list shall not require the Owner <br /> or Architect to -investigate the qualifications of proposed subcontractors or suppliers, nor shall it waive the right of <br /> the Owner or Architect later to object to or reject any proposed subcontractor or supplier. <br /> § 2.1 .7 LONG-LEAD-TIME ITEMS <br /> The Construction Manager, shall recommend to the Owner and Architect a schedule for procurement of to g-leadtime items which will constitute pact <br /> of the Work as required to meet the Project schedule. If such long-lead-time <br /> items are procured by the Owner, they '.shall be procured on terms and conditions reasonably acceptable to the <br /> Construction Managef� Upon Manager and where applicable in accordance with the terms of <br /> the[Censtmeden Managef' ssGuamnfeed Maximum Pfiee proposal, all eentf-aets fef such items shall be assigned by <br /> Utie Qvfflpw to46 Genstsietion Managef, who shall aceept responsibility for- sueh items as if PT-eeurned by tte <br /> . Direct Purchase Procedure section of this contract . The Construction Manager shall expedite <br /> the the delivery of long-lead-time items. <br /> § 2.1 .8 EXTENT OF RESPONSIBILITY <br /> The Construction Manager does not warrant or guarantee estimates and schedules except as may be inclu d as part <br /> of the Guaranteed Maximum Price. The recommendations and advice of the Construction Manager concerning <br /> design alternatives shall be subject to the review and approval of the Owner and the Owner' s professional <br /> consultants. Itis not the Construction Manager' s responsibility to ascertain that the Drawings and Specifications are <br /> in accordance with applicable laws, statutes, ordinances, building codes, rules and regulations. However, i the <br /> Construction Manager recognizes that portions of the Drawings and Specifications are at variance therewith, the <br /> Construction Manager shall promptly notify the Architect and Owner in writing . -writing andspecify such variances . <br /> § 2.1 .9 EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION <br /> IThe Construction. Manager shall comply with applicable laws, regulations and special requirements of the Contract <br /> Documents regarding equal employment opportunity and specify such variances. <br /> § 2.1 .10 <br /> The Construction Manager and . the Owner acknowledge and agree that the <br /> Construction Manager may need to apply fora permit from Indian River Coun for the Project prior to th <br /> acceptance of the Guaranteed Maximum Price and any such application does not start the Construction Ph se of this <br /> Contract. C. A .1# of the *.�er-k as defined in Aftiele 6 of this Agreement is ngEmj1* <br /> AIA Document A121 TMCMe — 2003 and AGC Document 565. Copyright © 1991 and 2003 by The American Institute of Architects and The Associated <br /> General Contractors of America. All rights reserved. WARNING: This document Is protected by U.S. Copyright Law and Internatic nal Treaties. 4 <br /> Unauthorized reproduction or distribution of this document, or any portion of It, may result in severe civil and criminal penaltie , and will be <br /> prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 12:50:12 on 04/19/2005 under Order <br /> No. 1000126313_I which expires on 6/29/2005, and is not for resale. (1413727908) <br /> User Notes: <br />