Laserfiche WebLink
Indian River County Administration Complex <br /> Bldg. 1 - 1st Floor Punchlist - Friday 04/20/07 <br /> May 07, 2007 <br /> Page 8 <br /> Office 214 (continued) <br /> 6. To the left at the quad outlet below the quad outlet drywall is a little irregular, needs to be sanded and <br /> repainted. <br /> 7. Exterior window to the left and right, edges need to be repainted. Also, to the right jamb glob of paint on the <br /> right needs to be sanded and removed. <br /> 8. East wall to the right of the door, paint on the wall needs to be cleaned . <br /> Mail Room 215 <br /> 1 . To the left of the opening the North wall adjacent to the sink drywall needs to be patched and repaired and <br /> cleaned and repainted where it has been chipped, scuffed. Also, electrical outlet to the right of the sink, <br /> drywall needs to be patched and repaired around the outlet and to the bottom right where the screw is <br /> penetrating. <br /> 2 . Drywall on the South wall about the center of the wall, screw holes penetrating through the drywall, this <br /> needs to be patched and repaired. Also, a scratch mark has been painted over, needs to be patched and <br /> repaired. <br /> 3 . Walls need to be touched up with paint in numerous locations above the cabinetry where there are fingerprints <br /> on the walls. <br /> 4. To the right of the opening to the bottom left the outlet switch needs to be sanded and repainted, wall has been <br /> chipped due to the installation of the cabinetry. <br /> 5. Cabinetry needs to be cleaned of drywall mud, dirt and debris. <br /> 6. Cabinetry needs to be caulked where it abuts the side panels, which are the countertop and the side panel <br /> abutment. <br /> 7. On the Men' s side cabinet underneath the sink eschutheon needs to be installed on a drain line. <br /> 8. Faucet is not set securely to the sink and countertop, very loose. <br /> 9. In front of sink the front left of edge there is a dent and scratch in the stainless steel sink. <br /> 10. Ceiling grid along the Corridor wall above the opening, unacceptable, away from the wall, full of drywall <br /> mud, irregular. <br /> 11 . Inside comers of the vinyl base need to be properly secured and set flush. <br /> Conference 216 <br /> 1 . Hollow metal door frame bottom right outside face, overspray on the hollow metal need to be repainted. <br /> 2. At this time carpet is being laid, no vinyl base in place, flooring tile 70% complete. <br /> 3 . South accent wall needs to be cleaned up of fingerprints, drywall dust, etc. <br /> 4. Dropped soffit needs to be painted, edges have been sanded, not touched up. Above the South wall ceiling <br /> tile is chipped and also grid in numerous areas are laying loose. <br /> 5 . Door 216B - bottom left and right hollow metal frame needs to be touched up with paint. Also, bottom left of <br /> door hinge side bottom hinge on the outside of Door 216 is chipped. <br /> 6. AV Junction boxes and TV brackets have been installed. Drywall has not been patched yet. <br /> Maooine 217 <br /> 1 . Hollow metal door frame 217 , bottom left and right needs to be touched up with paint. <br /> 2. Left of Door 217 vinyl base is not secured to the drywall where it abuts the metal frame. <br /> 3 . Top left and right of the hollow metal door frame needs to be sanded and repainted. <br /> 4. Vinyl tile in place, vinyl base in place and acoustical ceiling in place except for one ceiling tile in this <br /> particular area. <br /> 5 . West wall towards the North end, drywall mud on the wall needs to be cleaned. <br /> 6. System countertops are placed in this room up against the walls and also System Furniture wall panels. <br /> 7 . To the right of Door 217 just above the base mark on the wall needs to be touched up with paint. Also, in this <br /> same area joint and vinyl base not acceptable, not cut even or flushed out. <br /> 8 . Ceiling grid along the wall above Door 217 needs to be cleaned of paint. <br /> DONADIO <br /> & Associates, Architects, P.A . <br />