Laserfiche WebLink
43rd AVENUE / OSLO ROAD IMPROVEMENTS <br /> PRE-BID MEETING <br /> ' TUESDAY, MAY 209 2003 <br /> ATTENDEES : <br /> ' Terry Thompson IRC Capital Projects <br /> Rick Mathis IRC Capital Projects <br /> ' Teresa Allen IRC Capital Projects <br /> Brian Good Kimley-Horn & Associates , Inc . <br /> Ron LaRowe Sheltra & Son <br /> ' Dick Destein Sheltra & Son <br /> A. Eric Kishel Johnson Brothers Corporation <br /> Jake Sedmack North American Properties Southeast, Inc . (NAPSE) <br /> ' Mike Bullock Community Asphalt <br /> John Blum Carter Associates <br /> Bill Yoder Ranger Construction <br /> Tim Rose Timothy Rose Contracting, Inc . <br /> Terry opened the meeting and described the project as replacement of the two (2) lane bridge <br /> with a five (5 ) lane bridge, widening the intersection and putting in turn lanes and signalization. <br /> Terry stated the bid opening is scheduled for June 4, 2003 and the anticipated Notice to Proceed <br /> is August 1 , 2003 . Terry stated there are utility lines that need to be relocated before the Notice <br /> to Proceed is issued. The right-of--way on Oslo north of the bridge will change and will increase <br /> to one-hundred thirty ( 130) feet . Terry stated the changes would be issued in the addendum. <br /> Terry explained that if the Contractor would like to have the notice to proceed earlier, with the <br /> understanding that the utilities have not been relocated and the County will not pay for any <br /> remobilization, the County will consider issuing it earlier. If the Notice to Proceed is issued <br /> earlier the County would extend the Contract time . The time would be increased the same <br /> number of calendar days between Notice to Proceed and when the overhead lines are relocated. <br /> Terry went over the items in the plans that she has found. She stated the items will be included <br /> in the first addendum . The minutes to the meeting will be attached to the first addendum also . <br /> Any questions after the Pre-Bid Meeting should be addressed in writing to Brian Good at <br /> ' Kimley-Hom. Terry stated the answers to the questions will be sent back to everyone who has <br /> picked up a set of plans . In the Instruction to Bidders there are three (3 ) pages missing, pages <br /> five (5) through eight (8) . Terry stated on the Structural Plans on quantity sheet A-2 , <br /> the <br /> ' approach slabs were left out and the bridge removal will be changed to a lump sum instead of <br /> square foot . Also on the quantities, the pile lengths will be increased. Terry stated on sheet AS - <br /> 1 finish elevations will be put on the approach slab . Terry stated along with all the quantity <br /> ' changes a new bid form will be issued. Terry stated the note regarding removal of the culvert <br /> pipe on sheet eight (8) of the drawings will be eliminated. The Publix Developer is scheduled to <br /> remove this culvert from the sub-lateral canal . Terry stated there is a Publix under construction <br /> at the southeast corner of the intersection. Terry stated Publix anticipates opening Thursday, <br /> November 6 , 2003 . <br /> ' F:\Public Works\Capital Projects\Oslo - 43rd Avenue\Meetings\PreBid5-20-03 .doc <br />