MATERIAL UNIT COST UNITS TOTAL COST
<br />GATE ASSEMBLIES $7,479.00 6 EA. $44,874.00
<br />GATES $500.00 6 EA. $3,000.00
<br />GATE FOUNDATIONS $575.00 6 EA. $3,450.00
<br />CANTILEVERS 34' $19,183.00 2 EA. $38,366.00
<br />CANTILEVER FOUNDATIONS $3,200.00 2 EA. $6,400.00
<br />WIRED CASE, 4AB WITH HXP-3R2 $78,479.00 1 EA. $78,479.00
<br />BATTERY BOX $675.00 2 EA. $1,350.00
<br />BATTERIES, SAFT SPL250 $212.00 50 EA. $10,600.00
<br />MISC. GROUND MATERIAL $2,712.52 1 PKG. $2,712.52
<br />CONDUIT & DIRECTIONAL BORE $45.00 220 FT. $9,900.00
<br />CABLE $71500.00 1 PKG. $7,500.00
<br />MISCELLANEOUS RELAY EQUIPMENT $1,120.00 1 PKG. $1,120.00
<br />POWER SERVICE $1,800.00 1 EA. $1,800.00
<br />MONITORING EQUIPMENT $9,821.00 1 PKG. $9,821.00
<br />SANITATION & DISPOSAL $1,500.00 1 PKG. $1,500.00
<br />FREIGHT & HANDLING $32,906.00
<br />TAX @ 6.5% $14,259.00
<br />TOTAL MATERIALS $268,037.52
<br />EXCAVATING EQUIPMENT PER DAY $181.00 20 DAYS $3,620.00
<br />EQUIPMENT RENTAL PER DAY $125.00 20 DAYS $21500.00
<br />FOREMAN'S TRUCK PER DAY $35.00 20 DAYS $700.00
<br />GANG TRUCK PER DAY $63.00 20 DAYS $1,260.00
<br />SUPERVISORS TRUCK PER DAY $35.00 20 DAYS $700.00
<br />EQUIPMENT TOTAL $8,780.00
<br />ENGINEERING $6,500.00 1 $6,500.00
<br />ENGINEERING TOTAL $6,500.00
<br />CONSTRUCTION SUPERVISION $312.00 20 DAYS $6,240.00
<br />LABOR ADDITIVE $3,476.00
<br />SUPERVISION TOTAL $9,716.00
<br />LABOR PER DAY $1,154.10 $23,082.00
<br />NUMBER OF DAYS 20
<br />LABOR ADDITIVE $13,471.00
<br />TOTAL LABOR $36,553.00
<br />GANG EXPENSES PER DAY $553.00
<br />NUMBER OF DAYS 20
<br />TOTAL GANG EXPENSES $11,060.00
<br />SUB -TOTAL $340,646.52
<br />CONTINGENCIES 5% $17,032.00
<br />TOTAL $357,680.00
<br />DATE:
<br />12/08/05
<br />rr�
<br />FILE:
<br />10.2
<br />rt
<br />TYPE:
<br />IV
<br />CLASS:
<br />III
<br />FLORIDA EAST COAST RAILWAY
<br />NO. OF DAYS:
<br />20
<br />OFFICE OF THE GENERAL MANAGER
<br />AAR / DOT #:
<br />272195P
<br />OF SIGNALS AND COMMUNICATIONS
<br />MILE POST:
<br />228+118'
<br />Project Type:
<br />FDOT
<br />ESTIMATED COST FOR HIGHWAY CROSSING WARNING DEVICES AT 16th
<br />STREET VERO BEACH.
<br />This estimate should be considered void after one (1) year.
<br />MATERIAL UNIT COST UNITS TOTAL COST
<br />GATE ASSEMBLIES $7,479.00 6 EA. $44,874.00
<br />GATES $500.00 6 EA. $3,000.00
<br />GATE FOUNDATIONS $575.00 6 EA. $3,450.00
<br />CANTILEVERS 34' $19,183.00 2 EA. $38,366.00
<br />CANTILEVER FOUNDATIONS $3,200.00 2 EA. $6,400.00
<br />WIRED CASE, 4AB WITH HXP-3R2 $78,479.00 1 EA. $78,479.00
<br />BATTERY BOX $675.00 2 EA. $1,350.00
<br />BATTERIES, SAFT SPL250 $212.00 50 EA. $10,600.00
<br />MISC. GROUND MATERIAL $2,712.52 1 PKG. $2,712.52
<br />CONDUIT & DIRECTIONAL BORE $45.00 220 FT. $9,900.00
<br />CABLE $71500.00 1 PKG. $7,500.00
<br />MISCELLANEOUS RELAY EQUIPMENT $1,120.00 1 PKG. $1,120.00
<br />POWER SERVICE $1,800.00 1 EA. $1,800.00
<br />MONITORING EQUIPMENT $9,821.00 1 PKG. $9,821.00
<br />SANITATION & DISPOSAL $1,500.00 1 PKG. $1,500.00
<br />FREIGHT & HANDLING $32,906.00
<br />TAX @ 6.5% $14,259.00
<br />TOTAL MATERIALS $268,037.52
<br />EXCAVATING EQUIPMENT PER DAY $181.00 20 DAYS $3,620.00
<br />EQUIPMENT RENTAL PER DAY $125.00 20 DAYS $21500.00
<br />FOREMAN'S TRUCK PER DAY $35.00 20 DAYS $700.00
<br />GANG TRUCK PER DAY $63.00 20 DAYS $1,260.00
<br />SUPERVISORS TRUCK PER DAY $35.00 20 DAYS $700.00
<br />EQUIPMENT TOTAL $8,780.00
<br />ENGINEERING $6,500.00 1 $6,500.00
<br />ENGINEERING TOTAL $6,500.00
<br />CONSTRUCTION SUPERVISION $312.00 20 DAYS $6,240.00
<br />LABOR ADDITIVE $3,476.00
<br />SUPERVISION TOTAL $9,716.00
<br />LABOR PER DAY $1,154.10 $23,082.00
<br />NUMBER OF DAYS 20
<br />LABOR ADDITIVE $13,471.00
<br />TOTAL LABOR $36,553.00
<br />GANG EXPENSES PER DAY $553.00
<br />NUMBER OF DAYS 20
<br />TOTAL GANG EXPENSES $11,060.00
<br />SUB -TOTAL $340,646.52
<br />CONTINGENCIES 5% $17,032.00
<br />TOTAL $357,680.00
<br />
|