Laserfiche WebLink
INDIAN RIVER COUNTY BEACH RESTORATION PROJECT FOR <br /> SECTORS 1 &2 (AMBERSAND BEACH) AND SECTOR 7 <br /> TECHNICAL AND ENVIRONMENTAL SPECIFICATIONS <br /> 1 . SCOPE AND FILL QUANTITY <br /> The CONTRACTOR shall provide all machinery, labor, equipment, supplies, and materials as <br /> necessary for all operations in connection with excavating, transporting, placement and grading of <br /> sand, planting and restoring vegetation and dune crossover structures, as indicated in the following <br /> Technical Specifications and the Construction Plans for this project. Standby for the diedgeis ) is <br /> anticipated . and in stimated to be 100 hours for the inlet sand source for the Sectors 1 & 2 portion of Deleted: i <br /> the project and 5 days for the Sectors 1 & 2 (Offshore Sand Source) and Sector 7 portions of the <br /> proyeet. Potential bidders are advised that the beach fill quantity may be adjusted by the COUNTY <br /> without re-negotiations of unit price or terms. The COUNTY shall not consider the terms of the <br /> Contract to be satisfied unless at least ninety-five percent (95%) of the final design quantity is placed <br /> on the beach and is distributed so that each acceptance section contains no less than ninety-five <br /> percent (95%) of its design quantity. <br /> 2. CONSTRUCTION WINDOW <br /> All equipment shall be removed from the beach and work must be completed prior to May 1 ',,2 <br /> - Deleted: 2006 <br /> Commencement, prosecution, and completion of the work are also addressed in the General - Deleted: zoo? <br /> Provisions. The time stated for completion shall include final site restoration of all work areas <br /> including staging areas and beach accesses. <br /> 3 . TIME EXTENSIONS <br /> All construction shall be stopped and all equipment must be removed from the beach prior to May <br /> 1 r', 2�. Time extensions for delays due to weather or equipment failures/availability shall not be Deleted: 2006 <br /> granted. — — — — — — — — — — — — — - _ Deleted: 2007 <br /> 4 . CONFLICTS <br /> To the extent that there is a conflict between the various sections of the contract documents, the <br /> following order of documents shall indicate precedence: <br /> 1 . In order of the most recent document date : Contract Modifications, Change Orders; -- Formatted: Numbered + Level: t + <br /> and/or modifications to the Technical Specifications or Plans authorized by the Numbering Style: 1, 2, 3, _ . + Start <br /> COUNTY at: 1 + Alignment: Left + Aligned at <br /> 58.5 pt + Tab after: 76.5 p[ + <br /> '_ . Technical and Environmental Specifications Indent at: 76.5 pt <br /> 3 . Construction Plans <br /> 4. General Conditions <br /> 3. Florida DOT Specifications for Road and Bridge Construction (2002) <br /> 6 . Proposal and Bonds <br /> TECHNICAL AND ENVIRONMENTAL SPECIFICATIONS Rev October 5 , 2007 TS- 1 <br />