' ARTICLE 6 - CONTRACTOR' S RESPONSIBILITIES
<br /> New Paragraphs 6.02.B.1 , 2, 3, 4, and 5 have been
<br /> ' added. Seethe Supplementary Conditions.
<br /> 6 . 01 Supervision and Superintendence
<br /> 6 . 03 Services, Materials, and Equipment
<br /> A. CONTRACTOR shall supervise, inspect, and
<br /> ' direct the Work competently and efficiently, devoting such A. Unless otherwise specified in the General Re-
<br /> attention thereto and applying such skills and expertise as quirements, CONTRACTOR shall provide and assume full
<br /> may be necessary to perform the Work in accordance with responsibility for all services, materials, equipment, labor,
<br /> ' the Contract Documents . CONTRACTOR shall be solely transportation, construction equipment and machinery,
<br /> responsible for the means, methods, techniques, sequences, tools, appliances, fuel, power, light, heat, telephone, water,
<br /> and procedures of construction, but CONTRACTOR shall sanitary facilities, temporary facilities, and all other
<br /> not be responsible for the negligence of OWNER or facilities and incidentals necessary for the
<br /> performance,
<br /> ' ENGINEER in the design or specification of a specific testing, start-up, and completion of the Work.
<br /> means, method, technique, sequence, or procedure of
<br /> construction which is shown or indicated in and expressly B . All materials and equipment incorporated into the
<br /> ' required by the Contract Documents. CONTRACTOR Work shall be as specified or, if not specified, shall be of
<br /> shall be responsible to see that the completed Work good quality and new, except as otherwise provided
<br /> in the
<br /> complies accurately with the Contract Documents. Contract Documents. All warranties and guarantees
<br /> specifically called for by the Specifications shall expressly
<br /> ' B . At all times during the progress of the Work, run to the benefit of OWNER. If required by ENGINEER,
<br /> CONTRACTOR shall assign a competent resident superin- CONTRACTOR shall famish satisfactory evidence
<br /> tendent thereto who shall not be replaced without written (including reports of required tests) as to the source,
<br /> kind,
<br /> notice to OWNER and ENGINEER except under and quality of materials and equipment. All materials and
<br /> extraordinary circumstances. The superintendent will be equipment shall be stored, applied, installed, connected,
<br /> CONTRACTOR's representative at the Site and shall have erected, protected, used, cleaned, and conditioned in
<br /> authority to act on behalf of CONTRACTOR. All accordance with instructions of the applicable Supplier,
<br /> ' communications given to or received from the superin- except as otherwise may be provided in the Contract Docu-
<br /> tendent shall be binding on CONTRACTOR. ments.
<br /> ' 6.02 Labor; Working Hours 6.04 Progress Schedule
<br /> A. CONTRACTOR shall provide competent, suitably A. CONTRACTOR shall adhere to the progress
<br /> qualified personnel to survey, lay out, and construct the schedule established in accordance with paragraph 2 .07 as
<br /> it
<br /> ' Work as required by the Contract Documents. CON- may be adjusted from time to time as provided below.
<br /> TRACTOR shall at all times maintain good discipline and
<br /> order at the Site . 1 . CONTRACTOR shall submit to ENGI-
<br /> NEER for acceptance (to the extent indicated in
<br /> B . Except as otherwise required for the safety or paragraph 2.07) proposed adjustments in the prog-
<br /> protection of persons or the Work or property at the Site or ress schedule that will not result in changing the
<br /> ' adjacent thereto, and except as otherwise stated in the Contract Times (or Milestones). Such adjustments
<br /> Contract Documents, all Work at the Site shall be will conform generally to the progress schedule then
<br /> performed during regular working hours, and CON- in effect and additionally will comply with any
<br /> TRACTOR will not permit overtime work or the provisions of the General Requirements applicable
<br /> ' performance of Work on Saturday, Sunday, or any legal thereto,
<br /> holiday without OWNER's written consent (which will not
<br /> be unreasonably withheld) given after prior written notice to 2. Proposed adjustments in the progress
<br /> ' ENGINEER. schedule that will change the Contract Times (or
<br /> Milestones) shall be submitted in accordance with
<br /> the requirements of Article 12 . Such adjustments
<br /> may only be made by a Change Order or Written
<br /> ' Amendment in accordance with Article 12.
<br /> r00700 - 20