J,Z <br />,0009 - I•L14 <br />CHANGE ORDER <br />No. 2 <br />PROJECT Vero Lake Estates Master Planned 12" Water Transmission Main <br />DATE OF ISSUANCE November 20, 2007 EFFECTIVE DATE January 3, 2008 <br />OWNER Sheltra & Son Construction Co., Inc. <br />OWNER's Contract No. UCP #2958 SBS Work Order No. 4 <br />CONTRACTOR Sheltra & Son Construction Co., Inc. ENGINEER Schulke. Bittle & Stoddard, LLC <br />You are directed to make the following changes in the Contract Documents: <br />Description: Additional lengths of bore <br />Reason for change order: Additional 188 ft directional bore lengths to accommodate reverse Lap, due to <br />inflexibility of 12" HDPE and a paved roadway as requested by IRCDUS field personnel Delete <br />equivalent amount of PVC pipe asphalt overlay and sod <br />Attachments: (See Attached Exhibit "A" <br />RECOM EN `-APPRgyjrDi <br />BY: B <br />Engineer (Authorized Signature`) x., 4a4t!ure) <br />Date: �IZI(�g —f Sandra l • Bxden .Chairman <br />Date is a; <br />EJCDC No. C-700 (2002 Edition) <br />Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated <br />General Contractors of America. <br />CHANGE IN CONTRACT PRICE <br />CHANGE IN CONTRACT TIME <br />Original Contract Price <br />Original Contract Times <br />$ <br />968.328.00 <br />Substantial Completion: 240 <br />Ready for final payment: <br />Das or dates <br />Net <br />changes from previous Change Orders <br />Net change from previous Change Orders <br />No._ <br />to No. 1 <br />No. to No. 1 <br />$ <br />103.248.00 <br />30 davs <br />Contract Price prior to this Change Order <br />Contract Time prior to this Change Order <br />$ <br />12071,576.00 <br />Substantial Completion: 270 <br />Ready for final payment: <br />Days or dates <br />Net <br />Increase (decrease) in this Change Order <br />Net Increase in this Change Order <br />$ <br />10,949.60 <br />0 <br />days <br />Contract <br />Price with all approved Change Orders <br />Contract Time with all approved Change Orders <br />$ <br />1,082,525.60 <br />Substantial Completion: 270 <br />Ready for final payment: <br />` <br />Days or dates <br />RECOM EN `-APPRgyjrDi <br />BY: B <br />Engineer (Authorized Signature`) x., 4a4t!ure) <br />Date: �IZI(�g —f Sandra l • Bxden .Chairman <br />Date is a; <br />EJCDC No. C-700 (2002 Edition) <br />Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated <br />General Contractors of America. <br />