SECTION 01310 CONSTRUCTION SCHEDULES <br /> 1 . 1 GENERAL REQUIREMENTS <br /> A . No partial payments shall be approved by the ENGINEER until there is an <br /> approved construction progress schedule on hand . <br /> B . Designate an authorized representative who shall be responsible for <br /> development and maintenance of the schedule and of all progress and <br /> payment reports . This representative shall have direct project control and <br /> complete authority to act on behalf of the CONTRACTOR in fulfilling the <br /> commitments of the CONTRACTOR's schedules . <br /> 1 . 2 REVISIONS TO THE CONSTRUCTION SCHEDULES <br /> When the ENGINEER requires the CONTRACTOR to submit revised ( updated ) <br /> progress schedules on a monthly basis the CONTRACTOR shall : <br /> A . Indicate the progress of each activity to the date of submission . <br /> B . Show changes occurring since the previous submission listing : <br /> 1 . Major changes in scope . <br /> 2 . Activities modified since the previous submission . <br /> 3 . Revised projections of progress and completion . <br /> 4 . Other identifiable changes . <br /> C . Provide a narrative report as needed to define : <br /> 1 . Problem areas , anticipated delays , and the impact on the schedule . <br /> 2 . Corrective action recommended and its effect. <br /> 3 . The effect of changes on schedules of other prime contractors . <br /> 1 . 3 SUBMISSION OF THE CONSTRUCTION SCHEDULES <br /> On or before the tenth day after the effective date of the Agreement, submit the <br /> initial schedules to the ENGINEER . The ENGINEER will review the schedules and <br /> return a review copy to the CONTRACTOR within 21 days after receipt . If required <br /> by the ENGINEER , resubmit revised schedules on or before the seventh day after <br /> receipt of the review copy . If required by the ENGINEER , submit revised monthly <br /> progress schedules with that month ' s application for payment . <br /> 1 . 4 DISTRIBUTION OF THE CONSTRUCTION SCHEDULES <br /> A . After receiving approval by the ENGINEER , distribute copies of the <br /> approved initial schedule and all reviewed revisions ( updated ) to : <br /> 1 . Job site file . <br /> 2 . Subcontractors . <br /> 3 . Other concerned parties . <br /> 4 . OWNER (two copies) . <br /> GENERAL PROVISIONS <br /> 01025-7 <br /> F :\Engineering\Capital Projects\0604-12th St Sidewalk Improve between 43rd Ave & 27th Ave\Bid Documents\DIVISION 2 - Technical <br /> Provisions. doc <br />