6 . 01 Supervision and Superintendence tools, appliances, fuel, power, light, heat, telephone, water,
<br /> • sanitary facilities , temporary facilities, and all other
<br /> A. CONTRACTOR shall supervise, inspect, and facilities and incidentals necessary for the performance,
<br /> direct the Work competently and efficiently, devoting such testing, start-up , and completion of the Work.
<br /> attention thereto and applying such skills and expertise as
<br /> may be necessary to perform the Work in accordance with B . All materials and equipment incorporated into the
<br /> the Contract Documents . CONTRACTOR shall be solely Work shall be as specified or, if not specified, shall be of
<br /> responsible for the means, methods , techniques, sequences, good quality and new, except as otherwise provided in the
<br /> and procedures of construction, but CONTRACTOR shall Contract Documents . All warranties and guarantees
<br /> not be responsible for the negligence of OWNER or specifically called for by the Specifications shall
<br /> expressly
<br /> ENGINEER in the design or specification of a specific run to the benefit of OWNER. If required by ENGINEER,
<br /> means, method, technique, sequence, or procedure of CONTRACTOR shall furnish satisfactory evidence
<br /> construction which is shown or indicated in and expressly (including reports of required tests) as to the source,
<br /> kind,
<br /> required by the Contract Documents . CONTRACTOR and quality of materials and equipment. All materials and
<br /> shall be responsible to see that the completed Work equipment shall be stored, applied, installed,
<br /> connected,
<br /> complies accurately with the Contract Documents . erected, protected, used, cleaned, and conditioned in
<br /> accordance with instructions of the applicable Supplier,
<br /> B . At all times during the progress of the Work, except as otherwise may be provided in the Contract Docu-
<br /> CONTRACTOR shall assign a competent resident superin- ments .
<br /> tendent thereto who shall not be replaced without written
<br /> notice to OWNER and ENGINEER except under 6 . 04 Progress Schedule
<br /> extraordinary circumstances . The superintendent will be
<br /> CONTRACTOR' s representative at the Site and shall have A . CONTRACTOR shall adhere to the progress
<br /> authority to act on behalf of CONTRACTOR. All schedule established in accordance with paragraph 2 . 07 as it
<br /> communications given to or received from the superin- may be adjusted from time to time as provided below.
<br /> tendent shall be binding on CONTRACTOR.
<br /> 1 . CONTRACTOR shall submit to ENGI-
<br /> • 6 . 02 Labor; Working Hours NEER for acceptance (to the extent indicated in
<br /> paragraph 2 . 07) proposed adjustments in the prog-
<br /> A. CONTRACTOR shall provide competent, suitably ress schedule that will not result in changing the
<br /> qualified personnel to survey, lay out, and construct the Contract Times (or Milestones) . Such adjustments
<br /> Work as required by the Contract Documents . CON- will conform generally to the progress schedule then
<br /> TRACTOR shall at all times maintain good discipline and in effect and additionally will comply with any
<br /> order at the Site . provisions of the General Requirements applicable
<br /> thereto .
<br /> B . Except as otherwise required for the safety or
<br /> protection of persons or the Work or property at the Site or 2 . Proposed adjustments in the progress
<br /> adjacent thereto, and except as otherwise stated in the schedule that will change the Contract Times
<br /> (or
<br /> Contract Documents, all Work at the Site shall be Milestones) shall be submitted in accordance with
<br /> performed during regular working hours, and CON- the requirements of Article 12 . Such adjustments
<br /> TRACTOR will not permit overtime work or the may only be made by a Change Order or Written
<br /> performance of Work on Saturday, Sunday, or any legal Amendment in accordance with Article 12 .
<br /> holiday without OWNER' s written consent (which will not
<br /> be unreasonably withheld) given after prior written notice to
<br /> ENGINEER.
<br /> New Paragraphs 6.02 .13.1 , 2, 3 , 4, and 5 have been
<br /> added. Seethe Supplementary Conditions.
<br /> 6 . 03 Services, Materials, and Equipment
<br /> A . Unless otherwise specified in the General Re-
<br /> quirements, CONTRACTOR shall provide and assume full
<br /> responsibility for all services, materials, equipment, labor,
<br /> transportation, construction equipment and machinery,
<br /> IRC OPERATIONS COMPLEX 00700 - Standard General Conditions of the Construction Contract
<br /> 00700 -20