4 . Minimum sheet size : 11 " x 17 " <br /> B . Format of listings : The chronological order of the start of each <br /> item of work. <br /> C . Identification of listings : By major specification section numbers . <br /> 1904 CONTENT OF SCHEDULES <br /> A . Construction Progress Schedule shall : <br /> 1 . Show the complete sequence of construction by activity . <br /> 2 . Show the dates for the beginning and completion of each <br /> major element of construction ; specifically list: <br /> a . Subcontractor work <br /> b . Utility construction <br /> C. Restoration <br /> 3 . Show projected percentage of completion for each item , as <br /> of the first day of each month . <br /> 1 .05 PROGRESS REVISIONS <br /> A . Indicate progress of each activity to date of submission <br /> B . Show changes occurring since previous submission of Schedule : <br /> 1 . Major changes in scope . <br /> 2 . Activities modified since previous submission . <br /> 3 . Revised projections of progress and completion . <br /> 4 . Other identifiable changes . <br /> C . Provide a narrative report as needed to define : <br /> 1 . Problem areas , anticipated delays , and the impact on the <br /> schedule . <br /> 2 . Corrective action recommended , and its effect. <br /> 3 . The effect of changes on schedules of other prime <br /> contractors . <br /> 1 .06 SUBMISSIONS <br /> A. Submit initial schedules within ten ( 10) days after award of <br /> Contract; Engineer will review schedules for information only . <br /> B . Submit revised progress schedules with each application for <br /> payment. <br /> 01311 - 2 <br /> \1Ginny%elSpedfiicationM01311 Constw ion Schedules .doc <br />