Laserfiche WebLink
9. 10 Limitations on ENGINEER's Authority and A. CONTRACTOR shall not be entitled to an increase in <br /> Responsibilities the Contract Price or an extension of the Contract Times with <br /> respect to any work performed that is not required by the <br /> A. Neither ENGINEER's authority or responsibility under Contract Documents as amended, modified, or supplemented <br /> this Article 9 or under any other provision of the Contract as provided in paragraph 3.04, except <br /> in the case of an <br /> Documents nor any decision made by ENGINEER in good faith emergency as provided in paragraph 6. 16 or in the case <br />of <br /> either to exercise or not exercise such authority or responsibility uncovering Work as provided in paragraph 13.04. 6. <br /> or the undertaking, exercise, or performance of any authority or <br /> responsibility by ENGINEER shall create, impose, or give rise to 10.03 Execution of Change Orders <br /> any duty in contract, tort, or otherwise owed by ENGINEER to <br /> CONTRACTOR, any Subcontractor, any Supplier, any other A. OWNER riate Change Orders mRACTTOORby ENGINEER execute shall <br /> individual or entity, or to any surety for or employee or agent of Wnt ep Amendments) covering: <br /> any of them. <br /> B. ENGINEER will not supervise, direct, control, or have 1 . changes in the Work which are: (i) ordered by <br /> authority over or be responsible for CONTRACTOR's means, OWNER pursuant to paragraph 10.01 .A, (ii) required <br /> methods, techniques, sequences, or procedures of because of acceptance of defective Work under <br /> construction, or the safety precautions and programs incident paragraph 13.08.A or OWNER's correction of defective <br /> thereto, or for any failure of CONTRACTOR to comply with Work under paragraph 13.09, or (iii) agreed to by <br /> the <br /> Laws and Regulations applicable to the performance of the parties; <br /> Work. ENGINEER will not be responsible for CONTRACTOR's 2 changes in the Contract Price or Contract Times <br /> failure to perform the Work in accordance with the Contract <br /> Documents. which are agreed to by the parties, including any <br /> undisputed sum or amount of time for Work actually <br /> C. ENGINEER will not be responsible for the acts or performed in accordance with a Work Change Directive; <br /> omissions of CONTRACTOR or of any Subcontractor, any and <br /> Supplier, or of any other individual or entity performing any of 3 changes in the Contract price or Contract Times <br /> the Work. <br /> which embody the substance of any written decision <br /> D. ENGINEER's review of the final Application for rendered by ENGINEER pursuant to paragraph 10.05; <br /> Payment and accompanying documentation and all provided that, in lieu of executing any such Change <br /> maintenance and operating instructions, schedules, guarantees, Order, an appeal may be taken from any such decision <br /> Bonds, certificates of inspection, tests and approvals, and other in accordance with the provisions of the <br />Contract <br /> documentation required to be delivered by paragraph 14.07A Documents and applicable Laws and Regulations, but <br /> will only be to determine generally that their content complies during any such appeal, CONTRACTOR shall cant' on <br /> with the requirements of, and in the case of certificates of the <br /> Work <br /> and <br /> adhere <br /> a to the <br /> progress schedule as <br /> inspections, tests, and approvals that the results certified Provin paragraph 9 P <br /> indicate compliance with , the Contract Documents. 10.04 Notification to Surety <br /> E. The limitations upon authority and responsibility set <br /> forth in this paragraph 9. 10 shall also apply to ENGINEER's A If notice of any change affecting the general scope of <br /> Consultants, Resident Project Representative, and assistants. the Work or the provisions of the Contract Documents <br /> (including, but not limited to, Contract Price or Contract Times) <br /> ARTICLE 10 - CHANGES IN THE WORK; CLAIMS is required by the provisions of any Bond to be given to a surety, <br /> the giving of any such notice will be CONTRACTOR's <br /> responsibility. The amount of each applicable Bond will be <br /> 10.01 Authorized Changes in the Work adjusted to reflect the effect of any such change. <br /> A Without invalidating the Agreement and without notice 10.05 Claims and Disputes <br /> to any surety, OWNER may, at any time or from time to time, <br /> order additions, deletions, or revisions in the Wait by a Written A. Notice. Written notice stating the general nature of <br /> Amendment, a Change Order, or a Work Change Directive. each Claim, dispute, or other matter shall be delivered <br /> by the <br /> Upon receipt of any such document, CONTRACTOR shall claimant to ENGINEER and the other party to the <br /> Contract <br /> promptly pmoeed with the Work involved which will be promptly (but in no event later than 30 <br />days) after the start of <br /> performed under the applicable conditions of the Contract the event giving rise thereto. Notice of the amount <br /> or extent of <br /> Documents (except as otherwise specifically provided). the Claim, dispute, or other matter with supporting data shaft be <br /> delivered to the ENGINEER and the other party to the Contract <br /> B. If OWNER and CONTRACTOR are unable to agree within 60 days after the start of such event (unless ENGINEER <br /> on entitlement to, or on the amount or extent, if any, of an allows additional time for daimant to submit additional <br /> or more <br /> adjustment in the Contract Price or Contract Times, or both, that accurate data in support of such Claim, dispute, or <br /> other <br /> should be allowed as a result of a Work Change Directive, a matter). A Claim for an adjustment in Contract Price <br /> shall be <br /> Claim may be made therefore as provided in paragraph 10.05. prepared in accordance with the provisions of paragraph <br /> 12.01 . 13. A Claim for an adjustment in Contract Time shall be <br /> 10.02 Unauthorized Changes in the Work prepared in accordance with the provisions of paragraph <br /> 12.02.6. Each Claim shall be accompanied by claimants <br /> written statement that the adjustment claimed is the entire <br /> 00700 - 24 <br />