Laserfiche WebLink
B . Manufacturer's Certification <br /> Contractor shall coordinate with the Manufacturer' s of major control components and pump <br /> equipment to provide all pre start-up work and inspections as necessary to prepare the pump <br /> station for final start-up. At start-up , the Manufacturer' s representatives shall be present for a <br /> minimum of one &hour day to provide the following services: <br /> 1 . Check final installation of equipment <br /> 2. Provide start-up of equipment <br /> 3 . Run specified tests <br /> 4 . Train personnel in operation and maintenance of equipment <br /> ` 5 . Certify as to acceptability of final installed and tested product <br /> C . The pump test shall demonstrate their ability to: <br /> 1 . Operate without vibration or overheating at the specified conditions. <br /> 2 . Perform as specified. <br /> 3 . Load test, check amperage, phase to voltage test and insulation test. <br /> 4 . Flow test based on timed draw down of the wet well and force main pressure reading. <br /> D. All defects revealed by or noted during the tests shall be corrected or equipment replaced <br /> promptly at no additional expense to the Owner. <br /> E. Should the Contractor be unable to demonstrate to the satisfaction of the Engineer that the <br /> units will satisfactorily perform the service required, the units may be rejected. Contractor <br /> shall remove and replace the equipment at his own expense. <br /> F. Prior to final acceptance by the Owner, all required: as-built record drawings; pump curves; <br /> operation and maintenance manuals; special tools necessary to disassemble, service, repair <br /> and adjust the equipment and all spare parts shall be delivered to the Owner. <br /> END OF SECTION <br /> w <br /> 02539-14 02539 — Submersible Pump Station (Rev.) <br />