check and verify pertinent figures therein and all applicable field <br /> measurements . CONTRACTOR shall promptly report in wrifing 1 . The progress schedule will be acceptable to <br /> to ENGINEER any conflict, error, ambiguity, or discrepancy ENGINEER if it provides an orderly progression of the <br /> which CONTRACTOR may discover and shall obtain a written Work to completion within any specified Milestones and <br /> interpretation or clarification from ENGINEER before proceeding the Contract Times . Such acceptance will not impose <br /> with any Work affected thereby; however, CONTRACTOR shall on ENGINEER responsibility for the progress schedule, <br /> not be liable to OWNER or ENGINEER for failure to report any for sequencing, scheduling, or progress of the Work nor <br /> conflict, error, ambiguity, or discrepancy in the Contract interfere with or relieve CONTRACTOR from <br /> Documents unless CONTRACTOR knew or reasonably should CONTRACTOR's full responsibility therefore. <br /> have known thereof. <br /> 2. CONTRACTOR's schedule of Shop Drawing and <br /> B. Preliminary Schedules: Within ten days after the Sample submittals will be acceptable to ENGINEER if it <br /> Effective Date of the Agreement (unless otherwise specified in provides a workable arrangement for reviewing and <br /> the General Requirements), CONTRACTOR shall submit to processing the required submittals . <br /> ENGINEER for its timely review. <br /> 3. CONTRACTOR's schedule of values will be <br /> 1 . a preliminary progress schedule indicating the acceptable to ENGINEER as to form and substance if it <br /> times (numbers of days or dates) for starting and provides a reasonable allocation of the Contract Price to <br /> completing the various stages of the Work, including component parts of the Work. <br /> any Milestones specified in the Contract Documents ; <br /> 2. a preliminary schedule of Shop Drawing and ARTICLE 3 - CONTRACT DOCUMENTS : INTENT, <br /> Sample submittals which will list each required submittal AMENDING, REUSE <br /> and the times for submitting, reviewing, and processing <br /> such submittal; and <br /> 3. 01 Intent <br /> 3. a preliminary schedule of values for all of the <br /> Work which includes quantities and prices of items A. The Contract Documents are complementary; what <br /> which when added together equal the Contract Price is called for by one is as binding as if called for by all. : <br /> and subdivides the Work into component parts in <br /> sufficient detail to serve as the basis for progress B. It is the intent of the Contract Documents <br /> to describe <br /> payments during performance of the Work. Such prices a functionally - complete Project (or part thereof) to be <br /> will include an appropriate amount of overhead and constructed in accordance with the Contract Documents. Any <br /> profit applicable to each item of Work. labor, documentation, services , materials, or equipment that <br /> may reasonably be inferred from the Contract Documents or <br /> C. Evidence of Insurance: Before any Work at the Site is from prevailing custom or trade usage as being required <br /> to <br /> started, CONTRACTOR and OWNER shall each deliver to the produce the intended result will be provided whether or not <br /> other, with copies to each additional insured identified in the specifically called for at no additional cost to OWNER. <br /> Supplementary Conditions , certificates of insurance (and other <br /> evidence of insurance which either of them or any additional C. Clarifications and interpretations of the Contract <br /> insured may reasonably request) which CONTRACTOR and Documents shall be issued by ENGINEER as provided in Article <br /> OWNER respectively are required to purchase and maintain in 9. <br /> accordance with Article 5. <br /> 3. 02 Reference Standards <br /> 2. 06 Preconstruction Conference <br /> A. Standards, Specifications, Codes, Laws, and <br /> A. Within 20 days after the Contract Times start to run, Regulations <br /> but before any Work at the Site is started, a conference <br /> attended by CONTRACTOR, ENGINEER, and others as 1 . Reference to standards, specifications, manuals , <br /> appropriate will be held to establish a working understanding or codes of any technical society, organization, <br /> or <br /> among the parties as to the Work and to discuss the schedules association, or to Laws or Regulations, whether such <br /> referred to in paragraph 2.05. 6, procedures for handling Shop reference be specific or by implication, shall mean the <br /> Drawings and other submittals , processing Applications for standard, specification, manual, code, or <br /> Laws or <br /> Payment, and maintaining required records. Regulations in effect at the time of opening of Bids (or <br /> on the Effective Date of the Agreement if there were no <br /> 2.07 Initial Acceptance of Schedules Bids), except as may be otherwise specifically stated in <br /> the Contract Documents . <br /> A. Unless otherwise provided in the Contract Docu- <br /> ments, at least ten days before submission of the first 2. No provision of any such standard, <br /> specification, <br /> Application for Payment a conference attended by CON- manual or code, or any instruction of a Supplier shall <br /> be <br /> TRACTOR, ENGINEER, and others as appropriate will be held effective to change the duties or responsibilities <br /> of <br /> to review for acceptability to ENGINEER as provided below the OWNER, CONTRACTOR, or ENGINEER, or any of <br /> schedules submitted in accordance with paragraph 2.05.6. their subcontractors, consultants, agents, or employees <br /> CONTRACTOR shall have an additional ten days to make from those set forth in the Contract Documents, <br /> nor <br /> corrections and adjustments and to complete and resubmit the shall any such provision or instruction be effective to <br /> schedules. No progress payment shall be made to CON- assign to OWNER, ENGINEER, or any of ENGINEER's <br /> TRACTOR until acceptable schedules are submitted to Consultants, agents , or employees any duty or authority <br /> ENGINEER. to supervise or direct the performance of the Work or <br /> 6706-38392\8/20/03 00700-8 VRB <br />