Ms. Polly Kratman <br /> 17 January 2007 <br /> Page 4 <br /> • Phase 2 : GCCS Phasing Plan <br /> Each of these tasks is briefly described below . <br /> Task 1 : General Consulting/Meeting Support/Project Management <br /> Task 1 consists of three components : general consulting, meeting support, and project <br /> management. GeoSyntec will provide SWDD with consulting services necessary to initiate the <br /> project and attend pre-application and in-progress review meetings with the FDEP Central <br /> District office. GeoSyntec will prepare presentation graphics, engineering drawings, and other <br /> documents required to support the meetings and project coordination activities . <br /> A kickoff meeting with SWDD is proposed before the start of project activities so that the <br /> specific project requirements can be discussed. If required by SWDD, GeoSyntec will prepare <br /> for and attend a meeting with the SWDD Board to explain the project scope and budget <br /> requirements . GeoSyntec will also schedule and attend, with SWDD staff, a meeting with the <br /> Central District office of FDEP to discuss specific permitting issues . In addition, review <br /> meetings will be held with SWDD as necessary during design and prior to the FDEP submittal . <br /> Following each meeting, GeoSyntec will prepare meeting minutes that document decisions <br /> reached in the meetings. <br /> Project management activities will include : budget and schedule tracking, invoice review, and <br /> project communications, including the preparation of a monthly progress report . The project <br /> report will include a description of the activities completed during the month and planned <br /> activities for the following month. In addition, the progress report will identify any technical or <br /> administrative issues that require SWDD ' s attention and the current status of the budget and <br /> schedule. <br /> For the purpose of this budget estimate, GeoSyntec has included six meetings : (i) one kickoff <br /> meeting with SWDD; (ii) two in-progress design review meetings with SWDD; (iii) two <br /> meetings with FDEP and SWDD staff, and (iv) one meeting with the SWDD Board, if requested <br /> by SWDD. <br /> Task 2 : Closure of C&D Debris on Segment 1 Landfill <br /> Task 2 consists of the design, permitting, and construction certification of the closure of the <br /> C&D debris on the Segment 1 landfill . For budgeting purposes this task has been divided in the <br /> following five phases, as presented below. <br /> XL.06230/01 - 17-2007 JL70002doc <br /> rnint � n ScientistS I in11ovrato1,5 <br />