Laserfiche WebLink
TABLE 3 <br />VACUUM SEWER SYSTEM IMPROVEMENTS <br />PRELIMINARY PROJECT SCHEDULE <br />Duration Cumulative Time <br />Activity Months Months <br />Authorization to Proceed 0 0 <br />Route Survey / Data Gathering 3 3 <br />Design Memorandum 1 3 <br />Submit Plans and Specifications (50% Submittal) 2 5 <br />Receive CLIENT Review Comments 0.5 5.5 <br />Submit Plans and Specifications (100% Submittal) 2.0 7.5 <br />Receive CLIENT Review Comments 0.5 8.0 <br />Finalize Contract Documents (Final Submittal) 0.5 8.5 <br />Permitting 1.0 9.5 <br />Bidding and Award 2.0 11.5 <br />Construction 10.0 21.5 <br />Detailed schedule will be provided upon receipt of authorization to proceed and will include specific submittal <br />dates. <br />(Remainder of this page left blank intentionally) <br />Page 14 of 17 <br />