and have the rights and authority assigned to ENGINEER in the Contract Documents in connection <br /> with completion of the work in accordance with the Contract Documents , <br /> ARTICLE 3 CONTRACT TIME <br /> 3 . 1 . Contract Times , The CONTRACTOR shall be substantially completed with the following <br /> timeframe <br /> (a) Within 15 calendar days from effective date of Notice to Proceed , Contractor shall <br /> complete the following tasks : <br /> 1 . Obtain all necessary permits . <br /> 2 . Receive approved shop drawings for all materials and equipment to be <br /> utilized in the job . <br /> 3 . Perform all photographic recording and documentation of conditions prior to <br /> construction . <br /> 4 . Locate all existing utilities in the area of work . <br /> 5 . Submit and secure approval of shop drawings . <br /> 6 . Mobilize all labor, equipment, and materials . <br /> 7 . Deliver and store all equipment and materials to the job site . <br /> 8 . Notify all utilities and other affected parties prior to initiating construction . <br /> (b) From 16 calendar days to 60 calendar days from the effective date of Notice to <br /> Proceed , the CONTRACTOR shall complete the following tasks : <br /> 1 . Install all pipe and appurtenant items . <br /> 2 . Perform all testing . <br /> 3 . Restore all disturbed areas to their pre-construction condition . <br /> 4 . Correct all deficiencies noted by Engineer. <br /> Completion of all tasks outlined above (i . e . , Subparagraphs a) and b) constitutes <br /> Substantial Completion . <br /> (c) From 61 calendar days to 75 calendar days from the effective date of Notice to <br /> Proceed , the CONTRACTOR shall complete the following tasks . <br /> 1 . Clean up project area . <br /> 2 . Remove all equipment and material from project site . <br /> 3 . Perform contract closeout procedures . <br /> 3 . 2 . Completion of all tasks outlined above ( i . e . , Subparagraphs a , b , and c) constitute <br /> Final Completion . <br /> 3. 3 Liquidated Damages . OWNER and CONTRACTOR recognize that time is of the <br /> essence of this Agreement and that OWNER will suffer financial loss if the work is not completed <br /> within the times specified in Paragraph 3 . 1 above , plus any extensions thereof allowed in accordance <br /> with Article 12 of the General Conditions . They also recognize the delays , expense and difficulties <br /> involved in proving in a legal proceeding the actual loss suffered by OWNER if the work <br /> is not <br /> completed on time . Accordingly , instead of requiring any such proof, OWNER and CONTRACTOR <br /> agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER <br /> Four Hundred and Fifty ($450. 00) for each day that expires after the time specified in Paragraph <br /> 3. 1 for Substantial Completion , if CONTRACTOR shall neglect , refuse or fail to complete the <br /> remaining work within the Contract Time or any proper extension thereof granted by OWNER , <br /> 00530-2 <br />