Laserfiche WebLink
3 . The CONSULTANT shall prepare schematic level drawings, based on the programming efforts. <br /> Drawings shall include : <br /> (i) Schematic level floor plans and elevations <br /> (ii) Conceptual site plan <br /> (iii) Preliminary stormwater modeling <br /> 4 . The CONSULTANT shall prepare a schedule of development, including timeframes for design, <br /> permitting, bidding, construction, and contract close-out. <br /> S . The CONSULTANT shall prepare submittals for and attend applicable pre-application conference(s) <br /> with IRC, SJRWMD, IRF WCD, IRCDUS, FPL, EMS , IRC Bldg Div . , etc . <br /> 6 . The CONSULTANT shall prepare detailed site development evaluations, including : <br /> (i) Survey — boundary, tree, topographic <br /> 7 . The CONSULTANT will prepare a Preliminary Cost Estimate, based on the schematic plans and <br /> programming requirements . <br /> (b) PHASE 2 - PRELIMINARY DESIGN DOCUMENTS PHASE : <br /> 1 . CONSULTANTshall prepare Preliminary Design Documents consisting of design development <br /> drawings, outline specifications and other documents sufficient to establish the size, quality and <br /> character of the site development, including the civil engineering, architectural, structural , <br /> mechanical and electrical systems, and other such elements of the project as may be appropriate . <br /> Drawings shall be a refinement of the schematic drawings, and shall further define the project <br /> scope, relationships, forms, size and appearance . Drawings and specifications shall include : <br /> (i) Bldg: Plans, sections, elevations, typ , construction details, equipment lay-out. <br /> (ii) Site : Preliminary Site Plan —bldg location(s), paving and drainage, stormwater system(s), <br /> utility locations, typical construction details . <br /> (iii) Specifications : identify major materials and systems and quality levels for both building and <br /> site . <br /> 2 . The CONSULTANT shall prepare a Concurrency Application and supporting documentation and <br /> evaluation of Public infrastructure impacted by the development, including: <br /> (i) Stormwater management calculations and hydraulic and hydrological modeling of the on- <br /> site drainage basin(s) and adjacent off-site drainage basins impacted by the development. <br /> 3 . The CONSULTANT shall prepare an updated detailed site and building construction plan cost <br /> estimate, based on the preliminary Design Documents, and reconcile design with project budget. <br /> (c) PHASE 3 - FINAL DESIGN AND PERMITTING PHASE <br /> 1 . The CONSULTANT will perform all necessary surveying, civil engineering, architectural, <br /> mechanical and electrical engineering and structural design, and incidental work for the site and <br /> Building. Based on the preliminary design development documents, final construction plans and <br /> technical specifications shall be prepared, establishing in detail the material and systems required <br /> for the project, including the incorporation of Sustainable building and site design principles and <br /> systems. <br /> 2 . The CONSULTANT shall Design and prepare a complete set of construction plans for the buildin <br /> suitable for obtaining County Site Plan Approval , Building Permits, and Health Department <br /> permits, and other permits required for the work . The design shall be in accordance with the 2010 <br /> Page 7of18 <br /> F:\Public Works\ENGINEERING DIVISION PROJECTS\1135-5 County Park Intergeneratllonal Rec FacAlty\Admlm\Wd documents\Agreement with Borrelli and Partners. Inc <br /> 03-20-12.doc <br />