EXHIBIT A <br />SCOPE OF WORK <br />INDIAN RIVER COUNTY <br />SOUTH COUNTY WATER TREATMENT PLANT <br />FINAL DESIGN, PERMITTING AND BIDDING SERVICES <br />FOR PROPOSED WELL NO. 7 <br />This Authorization, when executed, shall be incorporated in and become part of the Contract for <br />Consulting/Professional Services between the Indian River County (County), and CDM Smith Inc. <br />(Consultant), dated December 6, 2011 hereafter referred to as the Contract. <br />BACKGROUND <br />The County owns and operates the South County Water Treatment Plant (WTP) which currently <br />operates with six existing Upper Floridan Aquifer (UFA) production wells. The existing Consumptive Use <br />Permit (CUP) for the South County WTP also includes a future permitted seventh well that has not yet <br />been constructed. In August 2009, the Board of County Commissioners approved a Work Order for the <br />Consultant to design, permit and provide services during construction of the proposed well and raw <br />water pipeline. After reaching the 100 percent design level (minus the County's front-end documents), <br />staff decided to put the project on hold and not construct the well. The County now wishes to finalize <br />design, complete the bid package and finalize permitting of the proposed well at the South County WTP. <br />During the 2009 effort, coordination with the Parks Department County environmental personnel, and <br />the fish and wildlife service (FWS) took place, resulting in the utility department mitigating for scrub jay <br />impacts already incurred by the park development. Additional coordination was undertaken with FWS to <br />determine whether or not a connection to the Well No. 4 transmission piping (in lieu of connecting to <br />Well No 6) was feasible. This effort is outlined in Task No. 1. No additional mitigation activities will be <br />required for the scrub jay area. <br />The following is the scope of services to be provided under this authorization. <br />SCOPE OF SERVICES <br />Consultant will perform the following task services: <br />Task 1.0 COORDINATION WITH FWS <br />In preparation for the effort of updating the project documents from 2009 to current, it was discovered <br />that improvements within the South County park since 2009 have resulted in several obstacles being <br />constructed between the proposed Well No 7 location and the connection point to the Well No. 6 <br />transmission piping One alternative that will be considered is revisiting the potential to use a horizontal <br />directional drill (HDD) under the scrub jay conservation area with connection to the Well No. 4 <br />transmission piping to the east. In 2009, FWS indicated that such an activity may be detrimental to the <br />Scrub Jays due to noise and vibration impacts; however, CDM Smith will reach out to FWS to confirm <br />their stance on this issue. CDM Smith will participate in up to 2 meetings to determine if these activities <br />will be detrimental to the Scrub Jays. This task provides for coordination with FWS. <br />TASK 2.0 MEETING WITH SJRWMD <br />The proposed Well No. 7 is included in the County's existing CUP. While no increase in allocation is <br />proposed (operational flexibility only), coordination with St. Johns River Water Management (SJRWMD) <br />A-1 <br />jj1490.doc <br />