A. CONTRACTOR and OWNER recognize that time is of the essence for this Agreement <br /> and that OWNER will suffer financial loss if the Work is not completed on or before the <br /> date specified in paragraph 4 .02 above, plus any extensions thereof allowed in <br /> accordance with Article 12 of the General Conditions . The parties also recognize the <br /> delays , expense, and difficulties Involved in proving in a legal proceeding the actual loss <br /> suffered by OWNER if the Work is not completed on time. Accordingly, instead of <br /> requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages <br /> for delay (but not as a penalty) , CONTRACTOR shall pay OWNER $500 for each calendar <br /> day that expires after the date specified in paragraph 4 . 02 for Final Completion , until the <br /> Work is finally complete and ready for final payment. <br /> ARTICLE 5 = CONTRACT PRICE <br /> 5 . 01 OWNER shall pay CONTRACTOR for completion of the Work in accordance with the <br /> Contract Documents, an amount in current funds equal to the sum of the amounts <br /> determined pursuant to paragraph 5 . 01 .A and summarized in paragraph 5. 01 . 8 , below: <br /> A. For all Work, at the prices stated in CONTRACTOR's Bid , attached " hereto_ as an exhibit. <br /> B . THE CONTRACT SUM subject to additions and deductions provided in the Contract: <br /> Numerical Amount: $ 5 , 856, 660 . 20 <br /> Written Amount: Five million eight hundred fifty-six thousand six hundred sixty <br /> dollars and twenty cents <br /> ARTICLE 6 - PAYMENT PROCEDURES <br /> 6 . 01 Submittal and Processing of Payments <br /> A. CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the <br /> General Conditions. Applications for Payment will be processed by ENGINEER as <br /> provided in the General Conditions. <br /> 6. 02 Progress Payments; Retainage <br /> A. OWNER shall make progress payments on account of the Contract Price on the basis of <br /> 0,ONTRACTOR's Applications fdr IPPayrnerit ,al enrols: net less than grace each month <br /> during performance of the Work as provided in paragraph 6. 02A. 1 below. All such <br /> payments will be measured by the schedule of values established in paragraph 2 . 07 .A of <br /> the General Conditions (and in the case of Unit Price Work based on the number of units <br /> completed) or, in the event there is no schedule of values , as provided in the General <br /> Requirements : <br /> 1 . Progress payments will be made in an amount equal to the percentage indicated <br /> below, less the aggregate of payments previously made and less such amounts as <br /> ENGINEER may determine or OWNER may withhold , in accordance with paragraph <br /> 14 . 02 of the General Conditions: <br /> a . Ninety percent (90% ) of Work completed (with the balance being retainage) . <br /> There will be no payment for the cost of materials and equipment not incorporated <br /> in the Work but stored on the Project site. <br /> 00520 - Agreement = ADDENDUM No. 2 <br /> ADDENDUM NO. 2 00520 - 2 <br /> \\Fileserver2XPublic\Purchasing\Bid312012-2013 FY (2013000)12013030 PC South Brine Di3poselW0520 - Agreement - ADDENDUM No, 2.doc Rev. 05/01 <br />