SECTION 01311 <br /> CONSTRUCTION SCHEDULES <br /> PART 1 -- GENERAL <br /> 1 . 01 REQUIREMENTS INCLUDED <br /> A . Promptly after award of the Contract, Contractor shall prepare and <br /> submit to the Engineer estimated construction progress for the Work, <br /> with sub - schedules of related activities which are essential to its <br /> progress . <br /> B . Coordinate the work and scheduling with and around other contractors <br /> and individual trades performing work on the Project . <br /> C . Submit revised progress schedules with each application for payment . <br /> D . Progress Schedule shall become part of Contract Documents after <br /> approval by Engineer . <br /> 1 . 02 RELATED REQUIREMENTS <br /> A . In other parts of the Contract Documents : <br /> 1 , General Conditions : <br /> a . Articles 2 and 6 — Schedules, Reports , and Records <br /> b . Sections 6 . 1 and 6 . 2 — Supervision by Contractor <br /> C . Article 15 — Supervision of Work, Termination , and <br /> Delay <br /> B . Specified in other sections : <br /> 1 . Section 01000 : Summary of Work <br /> 2 . Section 01200 : Preconstruction Conference <br /> 3 , <br /> 1 . 03 FORM OF SCHEDULES <br /> A . Prepare schedules in the form of a horizontal bar chart as follows : <br /> 1 . Provide separate horizontal bar for each trade or operation <br /> 2 . Horizontal time scale : Identify the first work day of each week . <br /> 3 . Scale and spacing : To allow space for notations and future <br /> revisions . <br /> 4 . Minimum sheet size : 11 " x 17 " <br /> 01311 - 1 <br />