B . Format of listings : The chronological order of the start of each item of <br /> work . <br /> C . Identification of listings : By major specification section numbers . <br /> 1 . 04 CONTENT OF SCHEDULES <br /> A . Construction Progress Schedule shall : <br /> 1 . Show the complete sequence of construction by activity . <br /> 2 . Show the dates for the beginning and completion of each major <br /> element of construction ; specifically list : <br /> a . Subcontractor work <br /> b . Utility construction <br /> C . Restoration <br /> 3 . Show projected percentage of completion for each item , as of <br /> the first day of each month . <br /> 1 . 05 PROGRESS REVISIONS <br /> A . Indicate progress of each activity to date of submission <br /> B . Show changes occurring since previous submission of Schedule : <br /> 1 . Major changes in scope . <br /> 2 . Activities modified since previous submission . <br /> 3 . Revised projections of progress and completion . <br /> 4 . Other identifiable changes . <br /> C . Provide a narrative report as needed to define : <br /> 1 . Problem areas, anticipated delays , and the impact on the <br /> schedule . <br /> 2 . Corrective action recommended , and its effect . <br /> 3 . The effect of changes on schedules of other prime contractors . <br /> 1 . 06 SUBMISSIONS <br /> A . Submit initial schedules within ten ( 10 ) days after award of Contract; <br /> Engineer will review schedules for information only . <br /> B . Submit revised progress schedules with each application for payment . <br /> C . Submit the number of opaque reproductions which the Contractor <br /> requires, plus two ( 2 ) additional copies; one for Owner and one for <br /> Engineer . <br /> 01311 - 2 <br />