for in this Contract . The Owner will promptly investigate the conditions , and if it finds that such conditions <br /> do materially so differ and cause an increase or decrease in the Contractor' s cost of, or the time required <br /> for , performance of any part of the Work under this Contract , a Change Order shall be issued accordingly <br /> based on the Schedule of Values and executed by the Owner and the Contractor . Contractor' s failure to <br /> provide notice upon discovery of the differing site condition shall waive any entitlement to such an <br /> adjustment in the Contract Price or Contract Time . Further , no Claim of the Contractor under this <br /> paragraph 4 . 03A shall be allowed unless the Contractor has given the notice as required in this paragraph <br /> 4 . 03A . <br /> SC 4 . 03C1 Delete subparagraph 4 . 03C1 of the General Conditions in its entirety . <br /> SC 4 . 03 - C . 3 : Delete the words : " arbitration or" in line 10 of paragraph 4 . 03 - C . 3 of the General Conditions . <br /> SC -4 . 05A . Add the following new paragraph immediately after paragraph 4 . 05A . of the General Conditions <br /> to read as follows : <br /> B . Engineer may check the lines , elevations , reference marks , batter boards , etc . , set by Contractor , and <br /> Contractor shall correct any errors disclosed by such check . Such a check shall not be considered as <br /> approval of Contractor' s work and shall not relieve Contractor of the responsibility for accurate construction <br /> of the entire Work . Contractor shall furnish personnel to assist Engineer in checking lines and grades . <br /> SC 4 . 06D Delete the last sentence of paragraph 4 . 06D of the General Conditions in its entirety <br /> SC 4 . 06G Delete paragraph 4 . 06G of the General Conditions in its entirety . <br /> SC 4 . 07 Add the following new paragraph immediately after Paragraph 4 . 061 of the General Conditions . <br /> SC 4 . 07 Archaeological or Resources at Site <br /> SC4 . 07A If Archaeological or Historical Resources are revealed , uncovered or discovered at site , <br /> Contractor shall cease work immediately and solicit the services of an Archaeologist Registered with the <br /> Registry of Professional Archaeologists . Based on Archaeologist' s determination , Contractor shall then <br /> submit a Change Order in order to avoid resources or mitigate as required to proceed with project . <br /> ARTICLE 5 - BONDS AND INSURANCE <br /> SC 5 . 01A Replace the words " performance and payment bonds " with the words " Public Construction <br /> Bond . " ; then add the following sentence immediately after the existing text in paragraph 5 . 01A of the <br /> General Conditions : <br /> Pursuant to Florida Statutes section 255 . 05 ( 1 ) ( a ) ( 2007 ) , any claimant ( as such term is defined in Florida <br /> Statutes section 713 . 01 ) may apply to Indian River County as Owner for copies of the Agreement and the <br /> recorded payment and performance bonds and shall thereupon be furnished with certified copies of such <br /> documents . <br /> SC 5 . 0313 Delete existing paragraph 5 . 03B of the General Conditions in its entirety . <br /> SC 5 . 04B Delete existing paragraph 5 . 04B of the General Conditions in its entirety and replace with the <br /> following : <br /> B . The Contractor shall not commence Work under the Agreement until it has obtained all insurance <br /> required under the Agreement and the Indian River County Risk Manager has approved such insurance . <br /> 00800 - 5 <br /> F :\Utilities\UTILITY - Engineering\Projects - Utility Construction Permits\IRC - Reuse Automation- UCP 4065\13id Documents - Reuse <br /> Automation\00800 supplementary Conditions Reuse Automation . doc <br />