Metadata
Fields
Template:
Official Documents
Official Document Type
Agreement
Approved Date
09/07/2010
Control Number
2010-212
Agenda Item Number
12.J.2
Entity Name
Derrico Construction Coroporation
Subject
Reclaimed Water Line Replacements
Requirements Labor Contract
Project Number
UCP#4054
Bid Number
2010052
Supplemental fields
SmeadsoftID
9776
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
6
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
3 . 2 Liquidated Damages . OWNER and CONTRACTOR recognize that time is of the essence of <br /> this Agreement and that OWNER will suffer financial loss if the work is not completed within the <br /> times specified in Paragraph 3 . 1 above , plus any extensions thereof allowed in accordance with <br /> Article 12 of the General Conditions . They also recognize the delays , expense and difficulties <br /> involved in proving in a legal proceeding the actual loss suffered by OWNER if the work is not <br /> completed on time . Accordingly , instead of requiring any such proof , OWNER and <br /> CONTRACTOR agree that as liquidated damages for delay ( but not as a penalty) CONTRACTOR <br /> shall pay OWNER four- hundred and fifty dollars ( $450 . 00 ) for each day that expires after the time <br /> specified in Paragraph 3 . 1 for Substantial Completion under each individual Work <br /> Authorizations/Work Orders . If CONTRACTOR shall neglect , refuse or fail to complete the <br /> remaining work within the Contract Time or any proper extension thereof granted by OWNER , <br /> CONTRACTOR shall pay OWNER four- hundred and fifty dollars ( $450 . 00 ) for each day that <br /> expires after the time specified in Paragraph 3 . 1 for completion and readiness for final payment . <br /> ARTICLE 4 . CONTRACT PRICE , <br /> 4 . 1 OWNER shall pay CONTRACTOR for completion of the work , as set forth in each individual <br /> Work Authorization /Work Order in accordance with the Contract Documents , the amount and time <br /> set forth in each individual Work Authorization/Work Order , based on the prices set forth in the <br /> Bid Proposal ( Schedule of Bid Items ) attached to the CONTRACTOR ' s Bid Form . <br /> ARTICLE 5 . PAYMENT PROCEDURES . <br /> 5 . 1 . Progress Payments . The Owner shall make progress payments to the Contractor on the <br /> basis of the approved partial payment request as recommended by Engineer in accordance with <br /> the provisions of the Local Government Prompt Payment Act , Florida Statutes section 218 . 70 et . <br /> seq . where the amount of the individual Work Authorization /Work Order is in excess of <br /> $ 100 , 000 . 00 ( One Hundred Thousand dollars ) . <br /> 5 . 2 Retainage . The Owner shall retain ten percent ( 10 % ) of the payment amounts due to the <br /> Contractor until fifty percent (50 % ) completion of the Work . After fifty percent (50 % ) completion of <br /> the Work is attained as certified to Owner by Engineer in writing , Owner shall retain five percent <br /> ( 5 % ) of the payment amount due to Contractor until final completion and acceptance of all Work <br /> to be performed by Contractor under the Contract Documents . Pursuant to Florida Statutes <br /> section 218 . 735 ( 8 ) ( b ) , fifty percent ( 50 % ) completion means the point at which the County as <br /> Owner has expended fifty percent ( 50 % ) of the total cost of the construction services Work <br /> purchased under the Contract Documents , together with all costs associated with existing change <br /> orders and other additions or modifications to the construction services Work provided under the <br /> Contract Documents . <br /> 5 . 3 . Pay Requests . Each request for a progress payment shall be submitted on the application for <br /> payment form supplied by Owner and the application for payment shall contain the Contractor' s <br /> certification . All progress payments will be on the basis of progress of the Work measured by the <br /> schedule of values established ; or , in the case of unit price work ; based on the number of units <br /> completed ; or as otherwise specifically set forth in any specific Work Authorization/Work Order . <br /> After fifty percent ( 50 % ) completion , and pursuant to Florida Statutes section 218 . 735 ( 8 ) ( d ) 7 the <br /> Contractor may submit a pay request to the County as Owner for up to one half ( 1 /2 ) of <br /> the <br /> retainage held by the County , and the County shall promptly make payment to the Contractor <br /> unless such amounts are the subject of a good faith dispute ; the subject of a claim pursuant to <br /> Florida Statutes section 255 . 05 (2008 ) ; or otherwise the subject of a claim or demand by the <br /> County or the Contractor. The Contractor acknowledges that where such retainage is attributable <br /> to the labor, services , or materials supplied by one or more subcontractors or suppliers , the <br /> Contractor shall timely remit payment of such retainage to those subcontractors and suppliers . <br /> Al - 00530 Agreement Between County and Derrico (EJCDC ) <br /> 00530-2 <br />