may be the subject of an adjustment in Contract Price any other party indemnified hereunder to the
<br /> or Contract Times. If OWNER and CONTRACTOR extent caused by or based upon
<br /> are unable to agree on entitlement to or on the CONTRACTOR's performance of the Work,
<br /> amount or extent, if any, of any such adjustment, a
<br /> Claim may be made therefor as provided in paragraph Be Removal of Debris During Performance of the
<br /> 10. 05. Work.& During the progress of the Work CONTRAC-
<br /> TOR shall keep the Site and other areas free from
<br /> 6 . 10 Taxes accumulations of waste materials, rubbish , and other
<br /> debris. Removal and disposal of such waste materi-
<br /> A. CONTRACTOR shall pay all sales, consum- als, rubbish , and other debris shall conform to applica-
<br /> er, use, and other similar taxes required to be ble Laws and Regulations.
<br /> paid by CONTRACTOR in accordance with
<br /> the Laws and Regulations of the place of the C. Cleaning. Prior to Substantial Completion of
<br /> Project which are applicable during the the Work CONTRACTOR shall clean the Site and
<br /> performance of the Work. make it ready for utilization by OWNER. At the com-
<br /> pletion of the Work CONTRACTOR shall remove from
<br /> Be OWNER qualifies for state and local sales tax the Site all tools, appliances, construction equipment
<br /> exemption in the purchase of all material and and machinery, and surplus materials and shall
<br /> equipment. restore to original condition all property not designated
<br /> for alteration by the Contract Documents.
<br /> Vol Use of Site and Other Areas
<br /> D. Loading Struct res: CONTRACTOR shall not
<br /> A. Limitation on Use of Site and Other Areas load nor permit any part of any structure to be loaded
<br /> in any manner that will endanger the structure, nor
<br /> 1 . CONTRACTOR shall confine shall CONTRACTOR subject any part of the Work or
<br /> construction equipment, the storage of adjacent property to stresses or pressures that will
<br /> materials and equipment, and the operations of endanger it.
<br /> workers to the Site and other areas permitted
<br /> by Laws and Regulations, and shall not 6. 12 Record Documents
<br /> unreasonably encumber the Site and other
<br /> areas with construction equipment or other A. CONTRACTOR shall maintain in a safe place
<br /> materials or equipment. CONTRACTOR shall at the Site one record copy of all Drawings, Specifica-
<br /> assume full responsibility for any damage to tions, Addenda, Written Amendments, Change
<br /> any such land or area, or to the owner or Orders, Work Change Directives, Field Orders, and
<br /> occupant thereof, or of any adjacent land or written interpretations and clarifications in good order
<br /> areas resulting from the performance of the and annotated to show changes made during
<br /> Work. construction . These record documents together with
<br /> all approved Samples and a counterpart of all
<br /> 2. Should any claim be made by any approved Shop Drawings will be available to ENGI-
<br /> such owner or occupant because of the NEER for reference. Upon completion of the Work,
<br /> performance of the Work, CONTRACTOR shall these record documents, Samples, and Shop
<br /> promptly settle with such other party by Drawings will be delivered to ENGINEER for OWNER.
<br /> negotiation or otherwise resolve the claim by
<br /> arbitration or other dispute resolution 6 . 13 Safety and Protection
<br /> proceeding or at law.
<br /> A. CONTRACTOR shall be solely responsible
<br /> 3. To the fullest extent permitted by for initiating, maintaining and supervising all safety
<br /> Laws and Regulations, CONTRACTOR shall precautions and programs in connection with the
<br /> indemnify and hold harmless OWNER , Work. CONTRACTOR shall take all necessary
<br /> ENGINEER, ENGINEER's Consultant, and the precautions for the safety of, and shall provide the
<br /> officers, directors, partners, employees, agents, necessary protection to prevent damage, injury or loss
<br /> and other consultants of each and any of them to:
<br /> from and against all claims, costs, losses, and
<br /> damages (including but not limited to all fees 1 . all persons on the Site or who may
<br /> and charges of engineers, architects, attorneys, be affected by the Work;
<br /> and other professionals and all court or
<br /> arbitration or other dispute resolution costs) 2, all the Work and materials and equip-
<br /> arising out of or relating to any claim or action , ment to be incorporated therein , whether in
<br /> legal or equitable, brought by any such owner storage on or off the Site; and
<br /> or occupant against OWNER, ENGINEER, or
<br /> 00700 - General Conditions REV 04w07,doc
<br /> 00700 . 22
<br /> PIPublic Works\ENGINEERING DIVISION PROJECTS\0545=66Th Ave SR60 to 57th St (Arcadis)\Admim\Bid Documents\00700 - General Conditions REV 04-07.doc
<br />
|