ANSWER N0 . 5 <br /> The Contractor is responsible for sprigging and grow- in of sprigs to obtain fully covered playing fields . The <br /> Contractor is responsible for the fields until Final Acceptance of the project . <br /> QUESTION NO . 6 <br /> For the grass fields areas we just have to strip grass and regrade, correct ? is there a spec for the <br /> fill we <br /> must use ? <br /> ANSWER NO. 6 <br /> There is estimated to be 2, 445 CY of in - place fill required to bring the fields to proposed grade, as indicated <br /> in the contract documents . The existing grass must be eliminated by Contractor at method of his choosing. <br /> Cutting existing sod and removing from site will require more fill material . Fill quantities are measured <br /> from existing grade to proposed grade . Any additional fill material needed , due to removal of existing <br /> material , will be at Contractor' s expense . The fill material must be free of any aggregate V or larger and <br /> must have a minimum permeability rate of 12 feet per day . <br /> QUESTION NO. 7 <br /> For the clay area on the senior field can we just add clay as needed ? <br /> ANSWER NO. 7 <br /> Existing clay shall be carefully removed and stored . It shall be used on bottom of clay area with new clay on <br /> top after grading is performed . <br /> QUESTION NO. 8 <br /> Is there a spec for the warning track around the senior track ? <br /> ANSWER NO . 8 <br /> All warning track material for this project shall be the same . See No . 2 above . <br /> QUESTION NO . 9 <br /> For the little league, I see we have to remove clay for the sodded area , is there a spec for total <br /> depth and <br /> what they want replaced for the fill ? <br /> ANSWER NO. 9 <br /> Clay shall be minimum 4" thickness . <br /> Page 3 of 6 <br /> F:IPub&c WorkslENGINEERING DIVISIONPROJECTSI M&Gifford Senior BalylddlAdminl bid documentslADDENDUMSIADDENDUM NO I IM& <br />