6 . 12 Record Documents or ENGINEER's Consultant, or anyone employed by
<br /> any of them , or anyone for whose acts any of them
<br /> A. CONTRACTOR shall maintain in a safe place may be liable, and not attributable, directly or
<br /> at the Site one record copy of all Drawings, Specifica- indirectly, in whole or in part, to the fault or
<br />negligence
<br /> tions, Addenda, Written Amendments , Change of CONTRACTOR or any Subcontractor, Supplier, or
<br /> Orders, Work Change Directives , Field Orders, and other individual or entity directly or indirectly employed
<br /> written interpretations and clarifications in good order by any of them ) . CONTRACTOR's duties and
<br /> and annotated to show changes made during responsibilities for safety and for protection of the
<br /> construction . These record documents together with Work shall continue until such time as all the Work is
<br /> all approved Samples and a counterpart of all completed and ENGINEER has issued a notice to
<br /> approved Shop Drawings will be available to ENGk OWNER and CONTRACTOR in accordance with
<br /> NEER for reference. Upon completion of the Work, paragraph 14 . 07. 13 that the Work is acceptable
<br /> these record documents, Samples, and Shop (except as otherwise expressly provided in connection
<br /> Drawings will be delivered to ENGINEER for OWNER. with Final Completion ) ,
<br /> 6 . 13 Safety and Protection 6 . 14 Safety Representative
<br /> A. CONTRACTOR shall be solely responsible A. CONTRACTOR shall designate a qualified
<br /> for initiating , maintaining and supervising all safety and experienced safety representative at the Site
<br /> precautions and programs in connection with the whose duties and responsibilities shall be the
<br /> Work. CONTRACTOR shall take all necessary prevention of accidents and the maintaining and
<br /> precautions for the safety of, and shall provide the supervising of safety precautions and programs,
<br /> necessary protection to prevent damage , injury or loss
<br /> to: 6 . 15 Hazard Communication Programs
<br /> 1 . all persons on the Site or who may A. CONTRACTOR shall be responsible for
<br /> be affected by the Work; coordinating any exchange of material safety data
<br /> sheets or other hazard communication information
<br /> 2 . all the Work and materials and equip- required to be made available to or exchanged be-
<br /> ment to be incorporated therein , whether in tween or among employers at the Site in accordance
<br /> storage on or off the Site; and with Laws or Regulations .
<br /> 3 , other property at the Site or adjacent 6 . 16 Emergencies
<br /> thereto, including trees , shrubs, lawns, walks ,
<br /> pavements , roadways, structures, utilities, and A. In emergencies affecting the safety or protec-
<br /> Underground Facilities not designated for tion of persons or the Work or property at the Site or
<br /> removal , relocation , or replacement in the adjacent thereto, CONTRACTOR is obligated to act to
<br /> course of construction . prevent threatened damage , injury, or loss.
<br /> CONTRACTOR shall give ENGINEER prompt written
<br /> B . CONTRACTOR shall comply with all applica- notice if CONTRACTOR believes that any significant
<br /> ble Laws and Regulations relating to the safety of changes in the Wont or variations from the Contract
<br /> persons or property, or to the protection of persons or Documents have been caused thereby or are required
<br /> property from damage, injury, or loss; and shall erect as a result thereof. If ENGINEER determines that a
<br /> and maintain all necessary safeguards for such safety change in the Contract Documents is required be-
<br /> and protection . CONTRACTOR shall notify owners of cause of the action taken by CONTRACTOR in
<br /> adjacent property and of Underground Facilities and response to such an emergency, a Work Change
<br /> other utility owners when prosecution of the Work may Directive or Change Order will be issued .
<br /> affect them , and shall cooperate with them in the
<br /> protection , removal , relocation , and replacement of 6 . 17 Shop Drawings and Samples
<br /> their property. All damage , injury, or loss to any
<br /> property referred to in paragraph 6. 13 .A. 2 or 6 . 13 .A. 3 A. CONTRACTOR shall submit Shop Drawings
<br /> caused , directly or indirectly, in whole or in part, by to ENGINEER for review and approval in accordance
<br /> CONTRACTOR , any Subcontractor, Supplier, or any with the acceptable schedule of Shop Drawings and
<br /> other individual or entity directly or indirectly employed Sample submittals. All submittals will be identified as
<br /> by any of them to perform any of the Work, or anyone ENGINEER may require and in the number of copies
<br /> for whose acts any of them may be liable, shall be specified in the General Requirements. The
<br />data
<br /> remedied by CONTRACTOR (except damage or loss shown on the Shop Drawings will be complete with
<br /> attributable to the fault of Drawings or Specifications respect to quantities, dimensions , specified perfor-
<br /> or to the acts or omissions of OWNER or ENGINEER mance and design criteria, materials , and similar data
<br /> 00700 - General Conditions REV 570-13
<br /> 00700 - 23
<br /> FAPublic Works\ENGINEERING DIVISION PROJECTS\1336-Gifford Senior BallfieldWdmin\bid documents\MasterContract\Contract Documents\00700 - General Conditions REV 510-
<br /> 13.doc