Laserfiche WebLink
334-5 Acceptance of the Mixture. <br /> 334-5 . 1 General : The mixture will be accepted at the plant with respect to gradation (P_g <br /> and P.200) , asphalt content (Pb) , and volumetrics (volumetrics is defined as air voids at Nae,;,,) <br /> The mixture will be accepted on the roadway with respect to density of roadway cores . <br /> Acceptance will be on a LOT -by-LOT basis (for each mix design) based on tests of random <br /> samples obtained within each sublot taken at a frequency of one set of samples per sublot. A <br /> roadway LOT and a plant production LOT shall be the same . Acceptance of the mixture will be <br /> based on Contractor Quality Control test results that have been verified by the Department . <br /> 334-5 . 1 . 1 Sampling and Testing Requirements : Obtain the samples in <br /> accordance with FM 1 -T 168 . Obtain samples at the plant of a sufficient quantity to be split into <br /> three smaller samples ; one for Quality Control, one for Verification and one for Resolution <br /> testing; each sample at approximately 35 pounds . The split samples for Verification testing and <br /> Resolution testing shall be reduced in size and stored in three boxes each . The approximate size <br /> of each box must be 12 inches x 8 inches x 4 inches . Provide, label and safely store sample boxes <br /> in a manner agreed upon by the Engineer for future testing . r <br /> The asphalt content of the mixture will be determined in accordance with <br /> FM 5 - 563 . In the event the FM 5 - 563 ignition oven goes out of service during production, the <br /> Contractor may elect to use a replacement oven at another location for no more than 72 hours <br /> while the oven is being repaired . The gradation of the recovered aggregate will be determined in <br /> accordance with FM 1 -T 030 . Volumetric testing will be in accordance with AASHTO T 312 - 08 <br /> and FM 1 -T 209 . Measure the inside diameter of gyratory molds in accordance with FM 5 - 585 . <br /> Prior to testing volumetric samples , condition the test- sized sample for one hour plus or minus <br /> five minutes at the target roadway compaction temperature in a covered, shallow, flat pan , such <br /> that the mixture temperature at the end of the one hour conditioning period is within plus or <br /> minus 20°F of the roadway compaction temperature . Test for roadway density in accordance <br /> with FM 1 -T 166 . <br /> 334-5 . 1 .2 Acceptance Testing Exceptions : When the total combined quantity of <br /> hot mix asphalt for the project, as indicated in the plans for Type SP and Type FC mixtures only, <br /> is less than 2000 tons , the Engineer will accept the mix on the basis of visual inspection . The <br /> Engineer may require the Contractor to run process control tests for informational purposes , as <br /> defined in 334-4 , or may run independent verification tests to determine the acceptability of the <br /> material . <br /> Density testing for acceptance will not be performed on widening strips or <br /> shoulders with a width of 5 feet or less , open- graded friction courses , variable thickness <br /> overbuild courses , leveling courses , any asphalt layer placed on subgrade (regardless of type) , <br /> miscellaneous asphalt pavement, bike/shared use paths , crossovers , or any course with a <br /> specified thickness less than 1 inch or a specified spread rate that converts to less than 1 inch as <br /> described in 334 - 1 . 4 . Density testing for acceptance will not be performed on asphalt courses <br /> placed on bridge decks or approach slabs ; compact these courses in static mode only per the <br /> density testing for acceptance will not be performed on <br /> requirements of 330 - 10 . 1 . 8 . In addition, <br /> the following areas when they are less than 1 , 000 feet (continuous) in length : turning lanes , <br /> acceleration lanes , deceleration lanes , shoulders , parallel parking lanes or ramps . <br /> Density testing for acceptance will not be performed in intersections . The <br /> limits of the intersection will be from stop bar to stop bar for both the mainline and side streets . <br /> A random core location that occurs within the intersection shall be moved forward or backward <br /> from the intersection at the direction of the Engineer. <br /> - 89 - <br /> FPID (S ) : 423186 - 1 - 58 - 01 <br /> x <br />