§ 9.3.1 .1 As provided in Section 7. 3 . 9, such applications may include requests for payment on account of changes in
<br /> the Work that have been properly authorized by Construction Change Directives, or by interim determinations of the
<br /> Architect; but not yet included in Change Orders.
<br /> § 9.3. 1 :2 Applications for Payment shall not include requests for payment for portions of the Work for which the
<br /> Contractor does not intend to pay a Subcontractor or material supplier, unless such Work has been performed by
<br /> others whom the Contractor intends to pay.
<br /> § 9.3.2 Unless otherwise .provided in the Contract Documents, payments shall be made on account of materials and
<br /> equipment delivered and suitably stored at the site for subsequent incorporation in the Work. If approved in advance
<br /> by the Owner, payment may similarly be made for materials and equipment suitably stored off the site at a location
<br /> agreed upon in writing. Payment for materials and equipment stored on or off the site shall be conditioned upon
<br /> compliance by the Contractor with procedures satisfactory to the Owner to establish the Owner' s title to such
<br /> materials and equipment or otherwise protect the Owner' s interest, and shall include the costs of applicable
<br /> Kit
<br /> nsurance, storage and transportation to the site for such materials and equipment stored off the site.
<br /> §
<br /> 9.31 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner
<br /> no later thanthe time "of payment. The Contractor further warrants that upon submittal of an Application for
<br /> Payment all Work for which Certificates for Payment have been previously issued and payments received from the
<br /> Owner shall, to the best of the Contractor' s knowledge, information and belief be free and clear of liens, claims,
<br /> security interests or encumbrances in favor of the Contractor, Subcontractors, material suppliers, or other persons or
<br /> entities making a claim by reason of having provided labor, materials and equipment relating to the Work.
<br /> § 9.4 CERTIFICATES FOR PA1fMENT
<br /> § 9.4. 1 The Architect wf ll, within seven days after receipt of the Contractor' s Application for Payment, either issue
<br /> to the Owner a Certificate for, Payment, with a copy to the Contractor, for such amount as the Architect determines
<br /> is properly due, or notify the Contractor and Owner in writing of the Architect' s reasons for withholding
<br /> certification in whole or
<br /> in part as provided in Section 9 . 5 . 1 .
<br /> § 9,4.21h6issuance - f a Certificate for Payment will constitute a representation by the Architect to the Owner,
<br /> based on the Architect ' s evaluation of the Work and the data comprising the Application for Payment, that, to the
<br /> best of the Architect' s knowledge, in
<br /> and belief the Work has progressed to the point indicated and that
<br /> the quality of the Work is in accordance.with the Contract Documents. The foregoing representations are subject to
<br /> An evaluation :of the Work for conformance with the Contract Documents upon Substantial Completion, to results of
<br /> subsequent testsand inspections, to correction of minor deviations from the Contract Documents prior to completion
<br /> and to, specific qualifications 'expressed by the Architect. The issuance of a Certificate for Payment will further
<br /> Lim I
<br /> constitute a representation that the Contractor is entitled to payment in the amount certified. However, the issuance
<br /> of a Certificate for PaymentAl ill not be a representation that the Architect has ( 1 ) made exhaustive or continuous on-
<br /> site inspections to check the qualityor quantity of the Work, (2) reviewed construction means, methods, techniques,
<br /> sequences or procedures, (3 ) reviewed copies of requisitions received from Subcontractors and material suppliers
<br /> and other data requested by the Owner to substantiate the Contractor' s right to payment, or (4) made examination to
<br /> ascertain how or for what purpose the Contractor has used money previously paid on account of the Contract Sum.
<br /> § 9.5 DECISIONS TO WITHHOLD CERTIFICATION
<br /> § 9.5. 1 The Architect may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary
<br /> to protect the Owner, if in the Architect' s opinion the representations to the Owner required by Section 9.4.2 cannot
<br /> be made. If the Architect is unable to certify payment in the amount of the Application, the Architect will notify the
<br /> Contractor and Owner as provided in Section 9.4. 1 . If the Contractor and Architect cannot agree on a revised
<br /> amount, the Architect will promptly issue a Certificate for Payment for the amount for which the Architect is able to
<br /> make such representations to the Owner. The Architect may also withhold a Certificate for Payment or, because of
<br /> subsequenI It
<br /> tly discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued, to
<br /> 1, rim rm
<br /> % such extent as may necessary in the Architect' s opinion to protect the Owner from loss for which the Contractor
<br /> is responsible; including loss resulting from acts and omissions described in Section 3 . 3 .2, because of
<br /> .1 defective Work not remedied;
<br /> .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless
<br /> security acceptable to the Owner is provided by the Contractor;
<br /> Init. AIA Document A201 TM — 2007. Copyright ® 1911 , 1915 , 1918, 1925, 1937, 1951 , 1958, 1961 , 1963, 1966, 1970, 1976, 1987, 1997
<br />and 2007 by The American
<br /> Institute of Architects. All rights reserved. WARNING : This AIA® Document Is protected by U.S. Copyright Law and International Treaties. Unauthorized
<br /> reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted
<br /> to the
<br /> maximum extent possible underthe law. This document was produced by AIA software at 11 :28: 34 on 12/21 /2012 under Order No.4386727979 1 which
<br /> expires on 02/05/2013, and is not for resale.
<br /> User Notes: (811102566)
<br />
|