ARTICLE 10 - CHANGES IN THE WORK ; CLAIMS <br /> 10 . 04 Notification to Surety <br /> A . If notice of any change affecting the general scope of <br /> 10 . 01 Authorized Changes in the Work the Work or the provisions of the Contract Documents <br /> (including, but not limited to, Contract Price or Contract <br /> A . Without invalidating the Contract and without notice Times) is required by the provisions of any bond to be <br /> to any surety , Owner may , at any time or from time to given to a surety , the giving of any such notice will be <br /> time, order additions , deletions , or revisions in the Work Contractor ' s responsibility . The amount of each <br /> by a Change Order , or a Work Change Directive . Upon applicable bond will be adjusted to reflect the effect of <br /> receipt of any such document, Contractor shall promptly any such change. <br /> proceed with the Work involved which will be performed <br /> under the applicable conditions of the Contract 10 . 05 Claims <br /> Documents (except as otherwise specifically provided) . <br /> A:Engineer-s De�ision 'egudxedlll r laims except <br /> B . If Owner and Contractor are unable to agree on those waived pursuant to Paragraph 14 . 0 hall"be <br /> entitlement to, or on the amount or extent, if any , of an referred to the Engineer for decis��i na°-A decision by <br /> adjustment in the Contract Price or Contract Times, or Engineer shall be require as�rcondition precedent to any <br /> both , that should be allowed as a result of a Work Change exercise by Ower-or ontractor of any rights or remedies <br /> Directive, a Claim may be made therefor as provided in either may$Iherwise have under the Contract Documents <br /> Paragraph 10 . 05 . .o>ub_y awsand..Regulations in respect ofsuch_Claims. <br /> 10 . 02 Unauthorized Changes in the Work $ , � <br /> f <br /> each Claim shall be delivered by the claimant to E neer <br /> A . Contractor shall not be entitled to an increase in the; and the other party to the Contract promptly (bu n no <br /> Contract Price or an extension of the Contract Times with event later than 30 days) after the start of the ent giving <br /> respect to any work performed that is not required by the rise thereto . The responsibility to substanti e a Claim <br /> Contract Documents as amended, modified, or shall rest with the party making the Clai Notice of the <br /> supplemented as provided in Paragraph 3 . 04 , except in the amount or extent of the Claim , with s porting data shall <br /> case of an emergency as provided in Paragraph 6 . 16 or in be delivered to the Engineer and th other party to the <br /> the case of uncovering Work as provided in Paragraph Contract within 60 days after the art of such event <br /> 13 . 04 . 13 . (unless Engineer allows additii mal time for claimant to <br /> submit additional or more a 6urate data in support of such <br /> 10 . 03 Execution of Change Orders Claim) . A Claim for an astment in Contract Price shall <br /> be prepared in accorda . with the provisions of <br /> A . Owner and Contractor shall execute appropriate Paragraph 12 . 01 . 8 laim for an adjustment in Contract <br /> Change Orders recommended by Engineer covering : Time shall be pre,pp red in accordance with the provisions <br /> of Paragraph 12sb2 .B . Each Claim shall be accompanied <br /> 1 . changes in the Work which are : ( i ) ordered by by claimantl'ritten statement that the adjustment <br /> Owner pursuant to Paragraph 10 . 01 . A, (ii) required claimed is the entire adjustment to which the claimant <br /> because of acceptance of defective Work under believe sit is entitled as a result of said event . The <br /> Paragraph 13 . 08 . A or Owner ' s correction of oppo ing party shall submit any response to Engineer and <br /> defective Work under Paragraph 13 . 09 , or ( iii) agreed th claimant within 30 days after receipt of the claimant ' s <br /> to by the parties ; l -subm•i•ttal-Fun•4®ss Fnginee allow s-additional-time. <br /> 2 . changes in the Contract Price or Contract Times Crrgcrree�^=s54et�ewgi>3ee�-�y� lj �� � <br /> which are agreed to by the parties, including any and , within 30 days after receipt of the last submitt 1 <br /> of <br /> undisputed sum or amount of time for Work actually the claimant or the last submittal of the opposi �rty , if <br /> performed in accordance with a Work Change any, take one of the following actions in w r ing : <br /> Directive ; and <br /> l . deny the Claim in whole n part, <br /> 3-`—�elrarrges�-i�-tdae�e�•tt• =is®-e�C_e��ast-�Fiaaa�- <br /> which embody the substance of any written e ion 2 . approve the Clai r <br /> rendered by Engineer pursuant to Pa e00 <br /> 10 . 05 ; <br /> provided that, in lieu of executin ny such Change 3 . notify the mrties that the Engineer is unable to <br /> Order, an appeal may bet from any such deci - resXthem if, in the Engineer ' s sole discretion , <br /> sion in accordance ith the provisions of the it ppropriate for the Engineer to do so . <br /> Contract Doct nts and applicable Laws and Fof further resolution of the Claim , such <br /> Regulation� , Lit during any such appeal , Contractor +�ti(h�' n <br /> sha Carry on the Work and adhere to the Progress <br /> - �hgctute'asprovided-tn-Paragraplr6-1-8:/�: <br /> EJCDC C-700 Standard General Conditions of the Construction Contract. <br /> Copyright © 2002 National Society of professional Engineers for EJCDC. All rights reserved . <br /> 00700 - 29 <br />