Laserfiche WebLink
reasonably have known thereof. <br /> D . Scheduling : Unless it prejudices Work already excavated and uncovered , Contractor shall schedule layout, <br /> excavating and uncovering of Work or Underground Facilities a sufficient time in advance to allow the Engineer' s <br /> review, and the possible amending or supplementing of the Contract Documents . <br /> E . UTILITY COORDINATION . <br /> 1 . CONTRACTOR ' S Responsibility : The CONTRACTOR shall be responsible for making all necessary <br /> arrangements with governmental departments , public utilities , public carriers, service companies and corporations <br /> owning or controlling roadways , railways , water, sewer, gas , electrical , cable television , telephone , and telegraph <br /> facilities such as pavements , tracks , piping , wires , cables, conduits , poles , guys , etc . , including incidental <br /> structures connected therewith , that are encountered in the Work in order that such items may be properly shored, <br /> supported and protected , or the Contractor shall be solely responsible for coordinating their relocation . The <br /> Contractor shall give proper notices , shall comply with requirements of such parties in the performance of its <br /> Work, shall permit entrance of such parties on the Work, and shall pay all charges and fees made by such parties <br /> for its Work. The Contractor ' s attention is called to the fact that there may be delays on the Project due to Work to <br /> be done by governmental departments , public utilities , and others in repairing poles , conduits, etc . The Contractor <br /> shall cooperate with the above parties, in every way possible, so that the construction can be completed in the least <br /> possible time . <br /> 2 . Connection : At all points where the Work constructed by the Contractor connects to existing utilities and <br /> services , the actual Work of making the necessary connection to the existing service or utility shall be arranged for <br /> by Contractor at no additional expense to Owner (unless specifically indicated otherwise) . Services and utilities <br /> included within (but not limited to) this responsibility are roads , ditches, electrical , sewer, mechanical , utilities , <br /> water, fencing, etc . Connections shall be made at a time that will result in the least possible interference with <br /> existing services . <br /> Sc 4 . 03A Delete 4 . 03 A of the General Conditions in its entirety and replace it with the following : <br /> A . Notice. The Contractor shall promptly, and before such conditions are disturbed , and in no event later than 10 <br /> days after first observance of the conditions . Notify the Owner and Engineer in writing of: ( 1 ) subsurface or latent <br /> physical conditions at the site differing materially from those indicated in this Contract, or (2 ) unknown physical <br /> conditions at the site of an unusual nature , differing materially from those ordinarily encountered and generally <br /> recognized as inherent in Work of the character provided for in this Contract. The Owner will promptly investigate <br /> the conditions , and if it finds that such conditions do materially so differ and cause an increase or decrease in the <br /> Contractor ' s cost of, or the time required for, performance of any part of the Work under this Contract, a Change <br /> Order shall be issued accordingly based on the Schedule of Values and executed by the Owner and the Contractor. <br /> Contractor ' s failure to provide notice upon discovery of the differing site condition shall waive any entitlement to <br /> such an adjustment in the Contract Price or Contract Time . Further, no Claim of the Contractor under this <br /> paragraph 4 . 03A shall be allowed unless the Contractor has given the notice as required in this paragraph 4 . 03A . <br /> SC 4 . 03B . Delete paragraph 4 . 0313 of the General Conditions in its entirety. <br /> SC 4 . 03C1 Delete subparagraph 4 . 03C1 of the General Conditions in its entirety . <br /> SC 4 . 03C . 1 . Delete subparagraphs 4 . 03C1a . and b . of the General Conditions in its entirety . <br /> SC 4 . 03C3 . Delete paragraph 4 . 03C3 . of the General Conditions in its entirety . <br /> SC -4 . 05A . Add the following new paragraph immediately after paragraph 4 . 05A . of the General Conditions to <br /> read as follows : <br /> 00800 -5 <br />