e r <br /> PART 3 - EXECUTION <br /> 3 . 01 RESPONSIBILITY FOR SCHEDULE COMPLIANCE <br /> A . The Contractor agrees that whenever it becomes apparent from the current monthly <br /> schedule that delays to the critical path have resulted, and hence, that the contract <br /> completion date will not be met or when so directed by the Owner, he will take some or <br /> all of the following actions at no additional cost to the Owner, submitting to the Owner <br /> for approval , a written statement of the steps he intends to take to remove or arrest the <br /> delay to the critical path in the approved schedule . <br /> 1 . Increased construction manpower in such quantities and crafts as will <br /> substantially eliminate, in the judgment of the Owner ' s representative, the <br /> backlog of Work . <br /> 2 . Increase the number of working hours per shift, shifts per working days per <br /> week, the amount of construction equipment, or any combination of the <br /> foregoing, sufficiently to substantially eliminate, in the judgment of the Owner ' s <br /> representative, the backlog of work . <br /> 3 . Reschedule activities to achieve maximum practical concurrency of <br /> accomplishment of activities , and comply with the revised schedule . <br /> 4 . Costs incurred by the Owner arising from such lengthening of hours , including <br /> furnishing of Inspectors, shall be the Contractor ' s responsibility and shall be <br /> deducted from monies due him . Failure of the Contractor to comply with the <br /> requirements of the Owner ' s representative may be grounds for determination by <br /> the Owner that the Contractor is not proceeding at such rates as will insure I If <br /> completion within the specified time and may result in the termination of the <br /> right of the Contractor to continue the Work . <br /> 3 . 02 ADJUSTMENT OF CONTRACT SCHEDULE AND COMPLETION TIME <br /> A . If the Contractor desires to make changes in his method of operating which affect the <br /> approved schedule, he shall notify the Owner in writing stating what changes are <br /> proposed and the reason for the change . If the Owner approves these changes, the <br /> Contractor shall revise and submit for approval , without additional cost to the Owner, all <br /> of the affected portion of the schedule . The schedule shall be adjusted by the Contractor <br /> only after prior approval of his proposed changes by the Owner. <br /> B . Adjustments may consist of changing portions of the activity sequence and/or activity <br /> durations, division of approved activities, or other adjustments as may be approved by the <br /> Owner. The addition of extraneous, non -working activities and/or activities which add <br /> unapproved restraints to the schedule shall not be approved . <br /> C . If the completion of any activity, whether or not critical , falls more than 100 percent <br /> behind its approved duration , the Contractor shall submit for approval a schedule <br /> adjustment showing each such activity divided into two activities reflecting completed <br /> versus uncompleted work . <br /> D . Shop drawings which are not approved on the first submittal or within the scheduled time <br /> shall be immediately rescheduled, as well as pipelines and tanks which do not pass leak <br /> tests . <br /> E . The contract completion time will be adjusted only for causes specified in this contract . <br /> In the event the Contractor requests an extension of any contract completion date , he <br /> 01311 - 3 <br /> 77r <br /> If <br />