which was not shown or indicated in the Drawings or Specifications or identified in the Contract
<br /> Documents to be within the scope of the Work appear in paragraph 4 . 06 of the General
<br /> Conditions .
<br /> 4 . 05 Upon a request directed to the ENGINEER (Arjuna Weragoda , P . E . 772-226- 1931 ) 7
<br /> OWNER will provide Bidder access to the Site to conduct such examinations , investigations ,
<br /> explorations , tests , and studies as Bidder deems necessary for submission of a Bid . Bidder shall
<br /> fill all holes and clean up and restore the Site to its former condition upon completion of such
<br /> explorations , investigations , tests , and studies .
<br /> 4 . 06 Reference is made to Article 7 of the General Conditions for the identification of any other
<br /> work that is to be performed at the Site by OWNER or others (such as utilities and other prime
<br /> contractors ) that relates to the Work for which a Bid is to be submitted . On request , OWNER will
<br /> provide to each Bidder for examination access to or copies of Contract Documents (other than
<br /> portions thereof related to price ) for such other work .
<br /> 4 . 07 It is the responsibility of each Bidder before submitting a Bid to :
<br /> A. examine and carefully study the Bidding Documents , including any Addenda and the other
<br /> related data identified in the Bidding Documents ;
<br /> B . VISIT THE SITE AFTER CONTACTING THE ENGINEER (ARJUNA WERAGODA, P . E . ,
<br /> (772) 226 -1931 ) TO MAKE ARRANGEMENTS IN ADVANCE, AND BECOME FAMILIAR WITH
<br /> AND SATISFY BIDDER AS TO THE GENERAL, LOCAL, AND SITE CONDITIONS THAT MAY
<br /> AFFECT COST, PROGRESS , AND PERFORMANCE OF THE WORK;
<br /> C . become familiar with and satisfy Bidder as to all federal , state , and local Laws and
<br /> Regulations that may affect cost, progress , or performance of the Work ;
<br /> D . carefully study all reports of explorations and tests of subsurface conditions at or
<br /> contiguous to the Site and all drawings of physical conditions in or relating to existing surface or
<br /> subsurface structures at or contiguous to the Site (except Underground Facilities ) which have
<br /> been identified in the Supplementary Conditions as provided in paragraph 4 . 02 of the General
<br /> Conditions , and carefully study all reports and drawings of a Hazardous Environmental Condition ,
<br /> if any, at the Site which have been identified in the Supplementary Conditions as provided in
<br /> paragraph 4 . 06 of the General Conditions ;
<br /> E . obtain and carefully study (or assume responsibility for doing so) all additional or
<br /> supplementary examinations , Investigations , explorations , tests , studies , and data concerning
<br /> conditions (overhead , surface , subsurface , and Underground Facilities) at or contiguous to the
<br /> Site which may affect cost, progress , or performance of the Work or which relate to any aspect of
<br /> the means , methods , techniques , sequences , and procedures of construction to be employed by
<br /> Bidder, including any specific means , methods , techniques , sequences , and procedures of
<br /> construction expressly required by the Bidding Documents , and safety precautions and programs
<br /> incident thereto ;
<br /> F . agree at the time of submitting its Bid that no further examinations , investigations ,
<br /> explorations , tests , studies , or data are necessary for the determination of its Bid for performance
<br /> of the Work at the price bid and within the times and in accordance with the other terms and
<br /> conditions of the Bidding Documents ;
<br /> G . become aware of the general nature of the work to be performed by OWNER and others
<br /> at the Site that relates to the Work as indicated in the Bidding Documents ;
<br /> 00200 - Instructions to Bidders REV 04-07 . doc
<br /> 00200 - 3
<br /> FAPublic Works\ENGINEERING DIVISION PROJECTS\0745-Indian River Blvd Sidewalk Imp. Proj 12th_17th St. (LAP)\Admim\bid documents\00200 - Instructions to Bidders
<br /> REV 04-07.doc Rev. 05/01
<br />
|