Laserfiche WebLink
12.1. PUBLIC WORKS <br />12.1.1. STAFF UPDATE — SECTOR 3 BEACH RENOURISHMENT PROJECT <br />(Clerk's Note: this Item was heard after Item 12.J.3 and is placed here for continuity.) <br />Public Works Director Chris Mora provided the Board with a project update using a <br />PowerPoint Presentation (on file). He acknowledged staff had received the final permits and <br />Notice to Proceed, and on February 9th staff issued the Notice to Ranger Construction to begin <br />the construction work. He said beach compatible sand was currently being mined primarily from <br />the Ranch Road Lake Mine, and trucks were using Golden Sands and Wabasso Beach Parks as <br />the two entry points. He informed the Board that the production numbers would be about 5,000 <br />cubic yards per day, about 300 trucks per day, and running 10 hours each day, Monday through <br />Saturday, through April 30th, 2010. He provided information pertaining to beach park closures, <br />showed photos of the ongoing project, pointed out that Phase I is growing from 202,000 to <br />316,000 cubic yards of sand, and that staff was anticipating a second Change Order from Ranger <br />Construction identifying the additional costs associated with this increase. <br />There was a brief discussion regarding truck traffic and monitoring the operation. <br />12..1. UTILITIES SERVICES <br />12.J.1. APPROVAL OF BID AWARD FOR IRC BID NO. 2010029, ANNUAL BID FOR <br />THE OPERATION OF THE BIOSOLIDS DEWATERING FACILITY, SLUDGE <br />DEWATERING AND HAULING <br />(Clerk's Note: Items 12.11., 12.12., and 12.13. were heard before Item 12.1.1. and are <br />placed here for continuity) <br />21 <br />February 16, 2010 <br />