Laserfiche WebLink
ARTICLE 12 - CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES <br />SC12.01 C Delete 15 percent" in line 2 of paragraph 12.01 C.2.a of the General Conditions and <br />replace with 10 percent". <br />SC12.01C Delete 15 percent" in line 6 of paragraph 12.01C.2.c of the General Conditions and <br />replace with 10 percent". <br />12.03A and B Delete paragraphs 12.03.A and 12.03B of the General Conditions in their entirety <br />and replace with the following: <br />A. Where Contractor is delayed or prevented from completing any part of the Work within the <br />Contract Times due to delay beyond the control of Contractor, the Contract Times (or Milestones) <br />will be extended in an amount equal to the time lost due to such delay if M a Claim is made <br />therefore as provided in paragraph 12.02.A and (2) Contractor provides evidence that the delay <br />impacted the critical path of the Project. Delays beyond the control of Contractor shall include, but <br />not be limited to, acts or neglect by Owner, acts or neglect of utility owners or other contractors <br />performing other work as contemplated by Article 7, fires, floods, abnormal weather conditions or <br />acts of God. The Contractor must request the extension of time in writing and must provide the <br />following information within the time periods stated hereafter. Failure to submit such information and <br />in compliance with the time requirements hereinafter stated, shall constitute a waiver by the <br />Contractor and a denial of the claim for extension of time: <br />1. Nature of the delay or change in the Work; <br />2. Dates of commencement and cessation of the delay or change in the Work; <br />3. Activities on the current progress schedule affected by the delay or change in the Work; <br />4. Identification and demonstration that the delay or change in Work affects the critical path; <br />5. Identification of the source of delay or change in the Work; <br />6. Anticipated extent of the delay or change in the Work; and <br />7. Recommended action to minimize the delay. <br />B. Contractor hereby affirms that the extension of time granted herein is the Contractor's sole and <br />exclusive remedy. Apart from extension of time, no payment or claim for damages shall be made to <br />the Contractor as compensation for damages for any delays or hindrances from any cause <br />whatsoever in the progress of the Work whether such delay is avoidable or unavoidable. <br />SC 12.03C Delete paragraph 12.03.0 of the General Conditions in its entirety. <br />SC 12.03D Delete paragraph 12.03D of the General Conditions in its entirety and replace with <br />the following: <br />In no event shall Owner, Engineer, or the Related Entities of either of them be liable to <br />Contractor, any Subcontractor, any Supplier, any other person or organization, or any surety for <br />or employee or agent of any of them, for any claim, cost, loss, or damages of any nature <br />whatsoever arising out of or resulting from delays. <br />ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF <br />DEFECTIVE WORK <br />SC 13.04C Delete the words: "arbitration or" in line 10 of paragraph 13.04.0 of the General <br />Conditions. <br />00800-12 <br />